“The [Phase 1] contract documents will then be used as a basis for Phase 3 with that works being a variation to the contract based on the agreed sum for Phase 3.”
“Contractor’s Obligations General Obligations 2.1 The Contractor shall carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents, the Construction Phase Plan (where applicable) and other Statutory Requirements, and shall give all notices required by the Statutory Requirements. In relation to the Contractor’s Designed Portion, the Contractor shall: 1. complete the design for the Contractor’s Designed Portion, including the selection of any specifications for the kinds and standards of the materials, goods and workmanship to be used in the CDP Works, so far as not described or stated in the Employer’s Requirements or the Contractor’s Proposals; 2. comply with the Architect/Contract Administrator’s directions for the integration of the design of the Contractor’s Designed Portion with the design of the Works as a whole, subject to the provisions of clause 3∙8∙2; and 3. …”
“The quotations and final detail design for the mechanical and electrical subcontracts are still being finalised and I expect to have them shortly. In the meantime, you can progress all other packages. …”
“The scope of Phase 3 has adjusted slightly since the writing of the Schedule of Works to Phase 1 and reference should be made to the split between work carried out by Pioneer and work carried out by Feltham, appended to this Schedule. Phase 3 generally will comprise the following: • … • The mechanical subcontract installation, comprising the supplying and installation of … a two way logburning stove with heat exchanged [sic], all with insulated stainless steel flues … • The design and installation for the mechanical systems will be carried out by Affleck Mechanical Services Limited. • …” • … • The mechanical subcontract installation, comprising the supplying and installation of … a two way logburning stove with heat exchanged [sic], all with insulated stainless steel flues … • The design and installation for the mechanical systems will be carried out by Affleck Mechanical Services Limited. • …”
“Having successfully carried out the 1st phase of this exciting project, we trust that the professionalism of all staff involved and the quality of works, provides you with the comfort that we are the contractor to deliver the next phase of the project for you.”
“You are instructed to carry out the works relating to Phase 3a, this to include an immediate instruction to place an order with Affleck Mechanical to carry out the work in accordance with the specification as included in your tender submitted by email on28th June 2011 . It is intended that Phase 3b will either continue without interruption or may be deferred until the spring of 2012. [The First Claimant] would want to reserve the right to review any future instruction regarding Phase 3b, which therefore cannot at this stage be fully guaranteed. … The work comprising Phase 3 will continue as a variation to the Phase 1 contract, subject to the further possible adjustments as listed above.” 18. About half and hour after sending that email, the architect sent Feltham another which said: “Apropos my earlier email (below), would you please consider this as “draft”. [The First Claimant] wanted to ensure all points were included in our “email of intent” but he was not going to be able to do so until tomorrow. You wanted the email today in order that you could place your order with Affleck and this you are able to do. …”
“Please carry out and complete the Mechanical Services on the above project in accordance with this order, the Main Contract Conditions, the Sub-Contract Pre-Order minutes, the Standard Form of Subcontract and the subcontract order documents. All for the sum of£209,877.00 . Retention 5%. Fixed price: until main contract completion. No particular, general or printed conditions appearing on your offer which are additional or supplementary to any of the Sub-Contract Conditions shall apply.”
“the remaining causes all relate to the chimney.”
“In summary, the method of installation used by Mr Calloway could not be determined from the physical evidence and no detailed witness evidence has yet been provided. However, the use of screws and possibly a crimping tool ought not to have been necessary and represented a non-standard installation. … In view of the uncertainties in relation to the installation, it was possible that an aspect of the non-standard installation led to the fire. For instance and whilst it is difficult to envisage why the lower sections of the chimney might have moved, it is possible that the screws securing the tip of the male end of Section Q proved inadequate and a gap of unknown size was formed at about roof level between Sections Q and R. … It was also possible that the uppermost sections of the chimney could have moved as a result of strong winds at some time to create a gap at roof level between sections Q and R. …”
“Phase 3 – This involved the fit-out of the [House] and installation of a copper roof on the [House]. As part of the fit-out, a wood burning stove was installed, which was connected to a stainless steel flue that passed through the roof space. Feltham was appointed as the main contractor to carry out the Phase 3 works, pursuant to the terms of the [Phase 1] Contract (as varied by reference to the Phase 3 works and the agreed sum for those works). We understand that Feltham engaged subcontractors to carry out various aspects of the Phase 3 works. … Causation … It is the strong view of our client’s forensic expert that, on the balance of probability, the cause of the fire was the failure to comply with Building Regulations when installing the steel flue, which resulted in the steel flue being installed in close proximity to combustible material, which was ignited when the steel flue became heated following the operation of the wood burning stove. We are not aware that this view is opposed by any other forensic expert engaged by any party to date.”
“Phase 3 There was no separate contract put in place in respect of the Phase 3 works. It appears that it was agreed that the Phase 3 works would continue as a variation to the Phase 1 contract, which according to the Phase 3 Specification for Works would also be governed by the 2005 JCT Intermediate Building Contract conditions. … Causation We confirm that our expert, Mr Jon Boyle, of Hawkins agrees that the witness evidence would place the seat of the fire as being within the roof space of the Property. Notwithstanding that, however, we would submit that it is a significant leap from noting that the fire was first seen in the roof structure in the vicinity of the flue to concluding that the fire was caused by the twin wall insulated flue, which under normal circumstances would be expected to have a relatively low surface temperature. It is denied that the fire was caused by the negligence of either our client or their subcontractors. It is further denied that our client and/or their subcontractors failed to install the wood burning stove and its flue in accordance with the appropriate building regulations and instructions. … We note that it is Mr Goudsmidt’s “strong view” that “on the balance of probability, the cause of the fire was the failure to comply with Building Regulations when installing the flue, which resulted in the steel flue being instead in close proximity to combustible material, which was ignited when the steel flue became heated following the operation of the wood burning stove”
“We are advised that none of the experts demur from the proposition that the cause of the fire is associated with the chimney flue of the woodburner. As we previously stated in our letter of claim of24 August 2012 , clause 6.2 of the contract makes your client liable for all damage and/or loss arising from the performance of the works, including all damage and/or loss arising from the acts and negligence of its subcontractors. It is clear to us that the fire in this case arose from the poor and negligent installation of the chimney flue by your client’s subcontractor.”
“... we are instructed to confirm out agreement to the dis-application of the arbitration provisions of the contract.”
“4. It was agreed between the Referring Party and Mr and Mrs Iliffe that the Phase 3 Works would continue as a variation to Phase 1 of the Main Contract. The specification for these works noted that the Phase 3 works would also be governed by the 2005 JCT Intermediate Building Contract conditions. Phase 3 of the Works involved the installation of the internal finishings, mechanical services and copper roof covering. The Phase 3 Works commenced on6 June 2011 and were due to be completed by27 April 2012 . 5. By way of the Subcontract, the Referring Party subcontracted the provision of the mechanical and electrical services under Phase 3 of the Main Contract to the Responding Party. The Subcontract included the supply and installation of the flue for the wood burning stove and the chimney flue in the living area of the House.”
“6. Phase 3 of the works included installation of the internal finishings, mechanical services and a copper roof covering (“the Phase 3 works”). Pursuant to an agreement with Mr and Mrs Iliffe, Feltham undertook certain Phase 3 works including the installation of the mechanical services. These same mechanical service works were subcontracted in their entirety by Feltham to Affleck pursuant to the Subcontract. In particular, the Subcontract works included the design, supply and installation of a wood burning stove in the living area of the Property and the flue serving it.”
“3. Feltham was employed by the Honourable Mr and Mrs Iliffe (“the Employer”) as Main Contractor for fit-out works to Property (“the Fit-Out Works” or “the Phase 3 Works”
“If the question is whether a term was incorporated into a contract, the subsequent conduct of the parties may be very relevant to the inquiry whether such a term was or was not agreed. Mr Flaux's submissions to the contrary were, with respect, a misapplication of the principle that the subsequent conduct of the parties cannot be relied on as an aid to the construction of the contract, see Miller v. Whitworth Estates [1970] A.C. 583, 603D−E per Lord Reid, 615A per Lord Wilberforce. No such principle exists in relation to the question whether an alleged term of a contract was, in fact, agreed.”
“The fact that the transaction was performed on both sides will also make it unrealistic to argue that there was no intention to enter into legal relations. It will often make it difficult to submit that the contract is void for vagueness or uncertainty. Specifically, the fact that the transaction is executed makes it easier to imply a term resolving any uncertainty, or alternatively, it may make it possible to treat a matter not finalised in negotiations as inessential.”
“Particularly in a case of contracts for future performance over a period, where the parties may desire or need to leave matters to be adjusted in the working out of their contract, the Courts will assist the parties to do so, so as to preserve rather than destroy bargains, on the basis that what can be made certain is itself certain. Certum est quod certum reddi potest. This is especially the case where one party has either already had the advantage of some performance which reflects the parties’ agreement on a long term relationship, or has had to make an investment premised on that agreement. For these purposes, an express stipulation for a reasonable or fair measure or price will be a sufficient criterion for the courts to act on. But even in the absence of express language, the Courts are prepared to imply an obligation in terms of what is reasonable.”