“I refer to our meeting at Fairhill or22nd March 2011 . The purpose of the meeting was an attempt to avoid further correspondence between ourselves arguing our respective positions, and to progress the completion of Fairhill. During the meeting, we both repeated our arguments set out in our previous letters, I can see no purpose or benefit in repeating these here. However, our Client has explained the significant financial consequence of not being able to occupy the property. Therefore, in an order to mitigate these damages, we are arranging for all outstanding works to be attended to by other contractors. You are aware of this by way of copy correspondence we have sent to you so far in connection with the investigation carried out by Smith & Byford… Additionally, we have recently carried out an inspection of the property in order to identify the repairs required at the end of the twelve-month rectification period. We confirm a copy of the schedules prepared by HJP and EPP were emailed to you during that meeting. We are also arranging for these works to be carried out by other contractors…”
“In respect of a defect arising within the Rectification Period (as defined in Contract Particulars) of the JCT Intermediate Form of Contract (“the Contract”), is an “appropriate deduction” under Clause 2.30 of the Contract calculated by reference to: a. The Contract rates/priced schedule of works/Specification; or b. The cost to the Contractor of remedying the defect (including the sums to be paid to third party sub-contractors engaged by the Contractor): or c. The reasonable cost to the Employer of engaging another contractor to remedy the defect; or d. The particular factual circumstances and/or expert evidence relating to each defect and/or the proposed remedial works.” a. The Contract rates/priced schedule of works/Specification; or b. The cost to the Contractor of remedying the defect (including the sums to be paid to third party sub-contractors engaged by the Contractor): or c. The reasonable cost to the Employer of engaging another contractor to remedy the defect; or d. The particular factual circumstances and/or expert evidence relating to each defect and/or the proposed remedial works.”
“The Contractor shall carry out and complete the Works in accordance with the Contract Documents”
“2.1A.1 The Contractor warrants to the Employer that:2.1A.1.1 all workmanship, manufacture and/or fabrication will be good of up-to-date practice and of a standard appropriate to the Works;2.1A.1.2 the Works when completed will comply with the Statutory Requirements, the Contract Drawing and Specification.”
“When in the opinion of the [CA] practical completion of the Works…is achieved and the Contractor has complied sufficiently with clause 3.18.3, then: .1 in the case of the Works, the [CA] shall forthwith issue a certificate to that effect (‘the Practical Completion Certificate’)… and practical completion of the Works…shall be deemed for all the purposes of this Contract to have taken place on the date stated in that certificate.”
“4.13.2 The Contract Sum shall be adjusted:.1 for any amounts agreed by the Employer and the Contractor in respect of Variations and for all Valuations, as referred to in clause 5.2;.2 for amounts referred to in clause 4.7.2 and the deductions referred to in clause 4.7.3, each as finally ascertained;.3 by deduction of all Provisional Sums and the value of any works for which an Approximate Quantity is included in the Contract Documents; and.4 by the amount of any deduction under clause 2.30.”
“3.9 If within 7 days after receipt of a written notice from the Architect/Contract Administrator requiring compliance with an instruction the Contractor does not comply, the Employer may employ and pay other persons to execute any work whatsoever which may be necessary to give effect to that instruction. The Contractor shall be liable for all additional costs incurred by the Employer in connection with such employment and an appropriate deduction shall be made from the Contract Sum.”
“2.30 Any defects, shrinkages or other faults in the Works or a Section which appear and are notified by the …Contract Administrator to the Contractor not later than 14 days after the expiry of the Rectification Period, and which are due to materials or workmanship not in accordance with this Contract, shall at no cost to the Employer be made good by the Contractor unless the…Contract Administrator with the consent of the Employer shall otherwise instruct. If he does so otherwise instruct, an appropriate deduction shall be made from the Contract Sum in respect of the defects, shrinkages or other faults not made good.”
“Any defects, excessive shrinkages or other faults which appear within three months of the date of the practical completion and are due to materials or workmanship not in accordance with the contract or frost occurring before practical completion shall be made good by the Contractor entirely at his own cost unless the Architect/Supervising Officer shall otherwise instruct.”
“When the Architect issues his certificate of practical completion (clause 2.4), the contractor leaves the site. He has, apart from special arrangement, no more work to do. Clause 2.5 then provides for “defects ...or other faults” which appear during the defects liability period which follows. The only express provisions [are] that these “shall be made good by the Contractor entirely at his own cost unless the Architect shall otherwise instruct.”
“I am in no doubt that the last proposition misstates the law. What it should have said was "where the employer fails to give the contractor an opportunity to rectify defects in the work that may amount to a failure to mitigate the losses". “This is said to indicate an error of law; an error of law to the effect that the Recorder was wrongly translating a contract where there was an express defects liability clause, as there was in Pearce and High, to a contract where there was no such express clause, and that he was making the decision he did on a misunderstanding as to the law. In my judgment that is not a sustainable submission. The sentence which I have read in subparagraph 5 of paragraph 42 is not saying "I am applying Pearce and High to the facts of this case"; it is simply indicating that the consequences of not giving the contractor an opportunity to rectify defects, when for one reason or another he should have been given that opportunity, would be that the defendants are not entitled to recover more than the amount it would have cost the claimant to rectify the defects. That is a proposition which applies just as much to a contract with an express defects liability clause as it does to considerations, which I am satisfied the Recorder was undertaking, of whether or not the Conwells had failed to mitigate their loss.”
“4.8.3 Not later than 5 days before the final date for payment the Employer may give a written notice to the Contractor which shall specify any amount proposed to be withheld and/or deducted from the amount due…”