“2.22 If the Contractor fails to complete the Works….by the relevant Completion Date, the… Contract Administrator shall issue a certificate to that effect… 2.23.1 Provided: .1 the Contract Administrator has issued a certificate under rule 2.22; and .2 the Employer has informed the Contractor in writing before the date of the Final Certificates that he may require payment of, or may withhold or deduct, liquidated damages, the Employer may, not later than 5 days before the final date for payment of the debt due under the Final Certificate, give notice in writing to the Contractor in the terms set out in clause 2.23.2. .2 A notice from the Employer under clause 2.23 shall state that for the period between the Completion Date and the date of practical completion of the Works…: .1 he requires the Contractor to pay liquidated damages at the rate stated in the Contract Particulars or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; or .2 that he will withhold or deduct liquidated damages at the rate stated in the Contract Particulars…from monies due to the Contractor.” .1 the Contract Administrator has issued a certificate under rule 2.22; and .2 the Employer has informed the Contractor in writing before the date of the Final Certificates that he may require payment of, or may withhold or deduct, liquidated damages, .1 he requires the Contractor to pay liquidated damages at the rate stated in the Contract Particulars or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; or .2 that he will withhold or deduct liquidated damages at the rate stated in the Contract Particulars…from monies due to the Contractor.”
“…Design information was effectively provided on a “design as the Contract went along” basis, which meant that the Claimant was prevented from progressing its work, organising its supplies and lead times properly or working on anything other than limited work fronts at the same time. Particulars of the Claimant’s position as to the delays caused to the Claimant by this approach to design provision by the Defendant are also set out in the Claimant’s formal notification under clause 2.19.1 of23rd December 2008 .”
“Following our meeting a few weeks ago, I will have to issue a certificate on non-completion for the project as no explanation for an extension of time has been received. I still believe that a maximum of 10 week extension from the 22nd September is the most that can be justified, although I will review your information and the level of damages once I receive your details.”