“The governing load from the wind turbine is the overturning moment and it can fundamentally be transferred as a force-couple in the top and the bottom of the grouted region. Hence, unlike traditional grouted pile/sleeve connections used offshore (mainly axial loaded) the present application does not need shear keys to transfer loads.”
“A100 General 101 This offshore standard provides principles, technical requirements and guidance for design, construction and in-service inspection of offshore wind turbine structures. … 103 The standard shall be used for design of support structures and foundations for offshore wind turbines. The standard shall also be used for design of support structures and foundations or other structures in an offshore wind farm, such as transformer stations and meteorological masts. The standard can be used as a stand-alone document.”
“M.10.3: Grouting … No shear keys are included as the connection easily can transfer the axial force through friction between steel and grout. ... M.10b.5: Grouting 1. The grouted joint at the substation foundation is similar to the one at the wind turbine foundation. Shear keys are not included as the axial capacity of the connection can be sustained by friction between the pile and transition piece.”
“‘Fit for Purpose’ means fitness for the purpose in accordance with, and as may properly be inferred from, the Employer’s Requirements. ‘Good Industry Practice’ means in relation to any particular undertaking or task … those standards, practices, methods and procedures … to be performed with the exercise of skill, diligence, prudence and foresight that can ordinarily be expected from a fully skilled contractor who is engaged in a similar type of undertaking or task in similar circumstances consistent with recognised international standards.”
“8.1 GENERAL OBLIGATIONS The Contractor shall, in accordance with this Agreement, design, manufacture, test, deliver and install and complete the Works: (i) with due care and diligence expected of appropriately qualified and experienced designers, engineers and constructors (as the case may be). … (iv) in a professional manner … in accordance with … Good Industry Practice … (viii) so that the Works, when completed, comply with the requirements of the Agreement. … (x) so that each item of Plant and the Works as a whole shall be fit for its purpose as determined in accordance with the Specification using Good Industry Practice. … (xv) so that the design of the Works and the Works when completed by the Contractor shall be wholly in accordance with this Agreement and shall satisfy any performance specifications or requirements of the Employer as set out in this Agreement, and …. 30.2 MAKING GOOD DEFECTS The Contractor shall be responsible for making good any defect in or damage to any part of the Works including spares held in the Employers inventory which may appear or occur before or during the Defects Liability Period and which arises from, any of the following: a) any defective materials, workmanship or design, or … … d) Works not being Fit For Purpose providing that the Employer has substantially complied with the requirements of the Operations and Maintenance manuals and ‘Defect’ shall be construed accordingly. The Contractor shall forthwith make good the defect or damage including replacing all defective inventory and at his own cost in the minimum time practicable.”
“1.6 Key Functional Requirements The Wind Farms are to be designed, constructed and operated to provide the lowest lifetime cost option capable of meeting the full requirements of this Specification. … All main works items shall be of a design that has demonstrated successful service elsewhere, preferably in an offshore environment, and the Contractor shall complete Schedule 1.3, which provides details of such service. … The Works elements shall be designed for a minimum site specific ‘design life’ of twenty (20) years without major retrofits or refurbishments; all elements shall be designed to operate safely and reliably in the environmental conditions that exist on the site for at least this lifetime. … The Contractor shall identify in Schedule 1.4 any components which the contractor considers cannot be designed for a life of twenty (20) years and any components or systems which are not designed for this minimum operating life.”
“It is stressed that the requirements contained in this section and the environmental conditions given are the MINIMUM requirements of the Employer to be taken into account in the design. It shall be the responsibility of the Contractor to identify any areas where the Works need to be designed to any additional or more rigorous requirements or parameters.” and “The Contractor shall undertake the detailed engineering design of all structures, fixtures and fittings required to comply with the requirements of this Agreement and the Conditions of Contract. The Contractor shall assume full responsibility for design and installation of the structures.”
“3.2.2.2 Detailed Design Stage The detailed design of the foundation structures shall be according to the method of design by direct simulation of the combined load effect of simultaneous load processes (ref: DNV-OS-J101). Such a method is referred to throughout this document as an ‘integrated analysis’ The design of the foundations shall ensure a lifetime of 20 years in every aspect without planned replacement. … 3.2.3.2 Document Hierarchy Subject to current legislation, the Contractors design shall be in accordance with international and national rules, circulars, EU directives executive orders and standards applying to the Site. Unless otherwise specified in the Contract, the following hierarchy of standards shall apply (1 highest and 8 lowest):.. 1. IEC 61400-3 (if formally published). See note below regarding draft standards. 2. DNV-OS-J101:2004. … 7. Other standards…. Where conflict arises between standards, the standard with the highest priority as indicated above shall take precedence. … Where aspects of the foundation design are not covered explicitly by standards, or the Contractor’s design departs from standard (i.e. the implementation of recent research papers to effect economies) such aspects and departures shall be specifically stated as part of the tender documentation or the detailed design documentation, as appropriate ….”
“All parts of the Works, except wear parts and consumables shall be designed for a minimum service life of 20 years.”
“3b.5.1 Scope The design of the structures addressed by this Design Basis shall ensure a lifetime of 20 years in every aspect without planned replacement. The choice of structure, materials, corrosion protection system operation and inspection programme shall be made accordingly. … 3b.5.6 Service Life All parts of the Works, except wear parts and consumables shall be designed for a minimum service life of 20 years.”
“10.2.5 Structural Design … The design shall also address, but not be limited to such specific aspects not covered by standards as: … The use or otherwise of shear keys in grouted connections …. All primary structures shall be designed to require no scheduled inspection or maintenance in the operational life of the wind farms … 10.5.1 Grouted Connection … The connection shall be designed to require no scheduled inspection or maintenance. … The Contractor shall determine whether to employ shear keys within the grouted connection. If shear keys are used, the design and detailing shall take due account of their presence for both strength and fatigue design to the satisfaction of the Certifying Authority and the Engineer. If shear keys are to be omitted then the Contractor shall demonstrate with test data, that the grouted connection is capable of transmitting axial loads at the grout/steel interface without dependence upon flexural (normal) contact pressures, which may not always be present, to the satisfaction of the Certifying Authority and the Engineer. Such demonstration shall also account for joint performance under different temperature conditions ….” … The design shall also address, but not be limited to such specific aspects not covered by standards as: … The use or otherwise of shear keys in grouted connections …. All primary structures shall be designed to require no scheduled inspection or maintenance in the operational life of the wind farms … … The connection shall be designed to require no scheduled inspection or maintenance. … The Contractor shall determine whether to employ shear keys within the grouted connection. If shear keys are used, the design and detailing shall take due account of their presence for both strength and fatigue design to the satisfaction of the Certifying Authority and the Engineer. If shear keys are to be omitted then the Contractor shall demonstrate with test data, that the grouted connection is capable of transmitting axial loads at the grout/steel interface without dependence upon flexural (normal) contact pressures, which may not always be present, to the satisfaction of the Certifying Authority and the Engineer. Such demonstration shall also account for joint performance under different temperature conditions ….”
“… an autonomous and independent foundation with the objectives of safeguarding life, property and the environment, at sea and onshore. DNV undertakes classification, certification, and other verification and consultancy services relating to quality of ships, offshore units and installations, and onshore industries worldwide, and carries out research in relation to these functions.”
“A100 General 101 This offshore standard provides principles, technical requirements and guidance for design, construction and in-service inspection of offshore wind turbine structures. … 103 The standard shall be used for design of support structures and foundations for offshore wind turbines. … 106 The standard has been written for general world-wide application. National and governmental regulations may include requirements in excess of the provisions given by this standard depending on the size, type, location and intended service of the wind turbine structure. A200 Objectives 201 The standard specifies general principles and guidelines for the structural design of offshore wind turbine structures. 202 The objectives of this standard are to: - provide an internationally acceptable level of safety by defining minimum requirements for structures and structural components (in combination with referenced standards, recommended practices, guidelines, etc.) - Serve as a contractual reference document between suppliers and purchasers related to design, construction, installation and in-service inspection - serve as a guideline for designers, suppliers, purchasers and regulators - specify procedures and requirements for offshore structures subject to DNV certification - serve as a basis for verification of offshore wind turbine structures for which it DNV is contracted to perform the verification.”
“101 Shall: Indicates a mandatory requirement to be followed for fulfilment or compliance with the present standard. Deviations are not permitted unless formally and rigorously justified, and accepted by all relevant contracting parties. 102 Should: Indicates a recommendation that a certain course of action is preferred or is particularly suitable. Alternative courses of action are allowable under the standard where agreed between contracting parties, but shall be justified and documented. 103 May: Indicates a permission, or an option, which is permitted as part of conformance with the standard.”
“H100 Definition 101 The structural reliability, or the structural safety, is defined as the probability that failure will not occur or that a specified failure criterion will not be met within a specified period of time.”
“A200 Design principles 201 Design rules for grouted connections are given for axial loading combined with torque and for bending moment combined with shear loading, respectively. Guidance note: Long experience with connections subjected to axial load in combination with torque exists, and parametric formulas have been established for design of connections subjected to this type of loading. For connections subjected to bending moment and shear force, no parametric design formulas have yet been established. Therefore, detailed investigations must be carried out for such connections. 202 For design of grouted connections, it may be conservative to assume that axial load and bending moment do not interact. When it can be demonstrated for a grouted connection that it will be conservative to assume that axial load and bending moment do not interact, the grouted connection shall satisfy two separate requirements. The first requirement to satisfy is the capacity requirement specified for the combined action of axial load and torque under the assumption of no concurrently acting bending moment and shear force. The second requirement to satisfy is the capacity requirement specified for the combined action of bending moment and shear force under the assumption of no concurrently acting axial force and torque. … 204 A grouted connection can be established with or without shear keys as shown in Fig. 1. Guidance note: Shear keys can reduce the fatigue strength of the tubular members and of the grout due to the stress concentrations around the keys. If shear keys are used in a grouted connection subjected to bending, they should be placed at the mid level of the connection in order to minimise the influence on the fatigue damage, because the maximum grout stresses from bending will develop at the top and bottom of the grout member.”
“B100 General 101 The ultimate capacity of axially loaded grouted tubular connections may be calculated according to the method given in DNV Rules for Fixed Offshore Installations, January 1998. The method is reproduced in the guidance note with torque included.”
“The upper limit for the ratio RP/tP can be exceeded for low utilization of the axial capacity of the grouted connection. The allowable upper limit for RP/tP must be evaluated for the actual connection and the actual utilization.”
“101 … The design lifetime shall be based on the specified service life of the structure. If a service life is not specified, 20 years should be used.”
“D100 Experimental verification 101 If no sufficient documentation of the behaviour of a grouted connection is available, experimental verification of the behaviour must be carried out.”
“(1) As a result of the JIP work, the understanding of how grouted connections without shear keys behaved had improved. As a result, it was understood that axial capacity could be explained in terms of surface irregularity. This meant both surface roughness (as a result of steel production and corrosion) and tolerances (both circumferentially and longitudinally). (2) Initially, capacity depended on surface roughness and tolerances, giving (in effect) a bond (as shown in Fig 3 stage I at C16/26/13). As the bond capacity was exceeded, a slip occurred. (3) After a slip had occurred, the capacity depended on tolerances and radial stiffness. It was likely that immediately after installation there was significant axial capacity because of such tolerances, the likelihood being that the circumferential welds provided significant irregularities. (4) However, there was no specification of minimum tolerances, and so no basis upon which one could document a reliable capacity. (5) As a bending moment was applied, it was likely that the grouted connection experienced ovalisation. This had the effect of breaking the initial bond around the circumference. (6) The deformations of the joint led to relative sliding between the steel and the grout. While these individual movements may be small, the accumulated effect may be large. (7) The accumulated effect of many small movements is that wear occurred to the grout surface and capacity was reduced over time. (8) The laboratory tests showed that the long term resistance to sliding was so much reduced that a ‘reliable lower bound on resistance to be used in design can hardly be provided. This means that design solutions should be sought that can be documented to show sufficient capacity with a resistance between steel and grout surface equal to zero for cylindrical shaped grouted connections.’ (9) ‘Due to the low long-term axial capacity of cylindrical shaped grouted connections, it is believed that the design of such connections in monopiles can no longer be recommended’. The 3 reasons given were the problems caused to interface shear capacity by increasing diameter, the low long term effective resistance and the lack of requirements for minimum tolerances.”
“(a) In producing the original version of the equation in J101 which described interface shear capacity, Sele and Kjeoy had in a paper in 1989 expressed /Rp as a constant (0.25*10-3). Data from the Department of Energy gave rise to a different constant (0.34*10-3), but with the difference being explained by the difference in surface finish of the tubes used in testing. Although the JIP could not precisely trace the evolution of these figures to that in J101 (0.37*10-3), it was speculated that this may have been due to further tests, or to consideration of changed grout strengths. However, this difference was not regarded as being significant in the light of what the JIP had determined about more generally. (b) The JIP’s work led it to decide that ought in fact to be a constant, and so not vary with Rp, and the tests carried out during the JIP suggested it should have a value of between about 0.066 and 0.077. A plot of the observed settlements reported in 2010 and the test data is shown at Figure 10, the red function representing a constant parameter ( = 0.070mm) (C16/11/25). The black line represents the J101 variable parameter.”
“1 Summary and Motivation Recent experience and new test data of plain grouted connections shows that the static axial capacity for large diameter connections is significantly lower than that expressed through design practice until 2009 … It is realised that this new learning will have an impact on the design practice for grouted connections with shear keys that are subjected to alternating dynamic loading. (By alternating dynamic loading is understood a similar load amplitude in positive axial direction as in the negative direction …) By a significant reduction in the capacity of large diameter connections without shear keys, this will also thus lead to significant reduction in capacity of grouted connections with shear keys subjected to alternating dynamic loading … It is realised that there are insufficient test data for grouted connections with shear keys subjected to alternating dynamic loading. This makes design of such connections difficult as the safety level is unknown and recommendations can hardly be given in design standards by any responsible organisation. ... 3 Objective The objective of the proposed project is to provide a sound data basis and to establish a reliable design methodology for grouted connections with shear keys in: ● Large diameter monopile structures subjected to a static axial load and alternative dynamic bending moment where grouted connections are used to transfer the forces from the transition piece to the monopile.”
“The effect would be that the 2 isolated references to ‘ensure’ in general sections of the Specification would supersede all the more detailed and specific references to ‘design life’. That cannot be right. There is, it is submitted, no way of reading the two provisions together - one must trump the other.”
“Sometimes, again, a contractor will expressly undertake to carry out work which will perform a certain duty or function in conformity with plans and specifications, and it turns out that the work constructed in accordance with the plans and specifications will not perform that duty or function. It would appear that generally the express obligation to construct a work capable of carrying out the duty in question overrides the obligation to comply with the plans and specifications, and the contractor will be liable for the failure of the work notwithstanding that it is carried out in accordance with the plans and specification. Nor will he be entitled to extra payment for amending the work so that it will perform the stipulated duty.”
“The Supply Contractor warrants … that the Goods … will conform to all applicable Specifications … and, unless otherwise specified, will be fit for the purpose for which they are to be used …. The Supply Contractor warrants and guarantees that the Goods are free from all defects arising at any time from faulty design in any part of the Goods.”
“The general rule is that defects caused by an owner’s specification are not the responsibility of the contractor, unless the contractor expressly guarantees that the construction would be fit for a specific purpose, or a warranty can be implied by the owner’s actual reliance on the contractor’s skill and judgement.”
“Clause 4.4.4 is clear and unambiguous. Reference to authorities that deal with difficulties construing contractual provisions that may contain an implied warranty are of no assistance in this case. North American guaranteed that the pipes would not have defects arising from faulty design. The trial judge held that the pipes did have defects arising from faulty design. In my view, on the plain language of the contract, North American is liable for any damages that resulted from those defects. It does not matter whose design gave rise to the defects. There is no such qualification in clause 4.4.4.”
“The principles have been discussed in many cases, notably of course, as Lord Neuberger MR. said in Pink Floyd Music Ltd v EMI Records Ltd[2010] EWCA Civ 1429 ;[2011] 1 WLR 770 at para 17, by Lord Hoffmann in Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd[1997] AC 749 , passim, in Investors Compensation Scheme Ltd v West Bromwich Building Society[1998] 1 WLR 896 , 912F-913G and in Chartbrook Ltd v Persimmon Homes Ltd[2009] 1 AC 1101 , paras 21-26. I agree with Lord Neuberger (also at para 17) that those cases show that the ultimate aim of interpreting a provision in a contract, especially a commercial contract, is to determine what the parties meant by the language used, which involves ascertaining what a reasonable person would have understood the parties to have meant. As Lord Hoffmann made clear in the first of the principles he summarised in the Investors Compensation Scheme case at page 912H, the relevant reasonable person is one who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.”
“Where the parties have used unambiguous language, the court must apply it. This can be seen from the decision of the Court of Appeal in Co-operative Wholesale Society Ltd v. National Westminster Bank plc[1995] 1 EGLR 97 . The court was considering the true construction of rent review clauses in a number of different cases. The underlying result which the landlords sought in each case was the same. The court regarded it as a most improbable commercial result. Where the result, though improbable, flowed from the unambiguous language of the clause, the landlords succeeded, whereas where it did not, they failed. The court held that ordinary principles of construction applied to rent review clauses and applied the principles in The Antaios (Antaios Compania Naviera SA v Salen Rederierna AB)[1985] AC 191 . After quoting the passage from the speech of Lord Diplock cited above, Hoffmann LJ said, at p 98: “This robust declaration does not, however, mean that one can rewrite the language which the parties have used in order to make the contract conform to business common sense. But language is a very flexible instrument and, if it is capable of more than one construction, one chooses that which seems most likely to give effect to the commercial purpose of the agreement.’” “This robust declaration does not, however, mean that one can rewrite the language which the parties have used in order to make the contract conform to business common sense. But language is a very flexible instrument and, if it is capable of more than one construction, one chooses that which seems most likely to give effect to the commercial purpose of the agreement.’”
“... we had calculations that showed that the axial capacity was only utilised around one third of what was necessary, so it would be strange engineering to put something in that could damage your fatigue life of the grout when you only utilised one third of what was actually necessary.”
“We had a lot of focus on the bending moment of the grouted connection, because that is what was different from the oil and gas. So we analysed it thoroughly and found out that we needed approximately this 1.5 times the diameter to transfer the bending moment. And we then subsequently checked what the axial load capacity of that was inherent in the design that was necessary for the bending moment, and we came up with utilisation ratios of about one third.”
“202 For design of grouted connections, it may be conservative to assume that axial load and bending moment do not interact. When it can be demonstrated for a grouted connection that it will be conservative to assume that axial load and bending moment do not interact, the grouted connection shall satisfy two separate requirements. The first requirement to satisfy is the capacity requirement specified for the combined action of axial load and torque under the assumption of no concurrently acting bending moment and shear force. The second requirement to satisfy is the capacity requirement specified for the combined action of bending moment and shear force under the assumption of no concurrently acting axial force and torque.”
“Generally the ULS analysis of the grouted connection will be performed in accordance to section 9, subsection B of [J101]. Conservatively the grouted connection is analysed for axial loading and bending separately.”
“Conservatively the grouted connection is analysed for axial loading and bending separately.”
“... the possibility of cyclic depletion of the axial load carrying capacity is effectively eliminated by the compressive strength requirements of the grout for it to withstand the governing overturning moment of the ULS, a requirement which ensures that the mechanical frictions will be maintained through the lifetime of the structure.”
“101 If no sufficient documentation of the behaviour of a grouted connection is available, experimental verification of the behaviour must be carried out.”
“I believe, my Lord, that this is not specific to axial capacity. This is a clause that says you can do experimental verification if you wish to do so, if you think that there is not sufficient documentation of the behaviour of the grouted connection that you have designed. Now, when DNV writes standards, they cannot envisage what sort of grouted connections designers will come up with. You could do different things, you could use other grout materials. So far it had been a high performance grout that had been used on the various wind farms. One might suggest that you would do a wind farm with ordinary grout, and in that case it might be that DNV would say: well, we don’t have sufficient documentation for the behaviour. It might also be that you could choose some other steel, or weld in some square brackets, or whatever you could think of in the connection. This is DNV’s way of making sure that they could require additional testing if they thought that it was not documented how the behaviour of the grouted connection is.” and, at page 92: “That is not, my Lord, what I’m saying. What I’m saying is that this is a provision for DNV that if they think that there is not sufficient documentation, then they can call for experimental verification.”
“In my Expert Report I have presented results of finite element analyses which demonstrate a walkdown failure caused by an interaction between the axial load and the bending moments and natural shear forces which I have described as being driven by the axial force and ratcheted down by the bending and shear. This occurs due to the low axial capacity and the distortion of the cross section due to the bending and shear which causes separation (gapping) between the grout and steel thereby further undermining the axial capacity. Professor Schaumann, in his Expert Report, maintains that the interaction between axial load and bending moment is beneficial in increasing the effective axial capacity but that this is undermined by wear of the grout caused by abrasion of the steel against the grout in the regions of sliding and separation. I do not agree with this and in this report have included a reference to research work at E.ON’s Ratcliffe Research Technology Centre which demonstrates the overall wear during the design life of Robin Rigg to be less than 1mm at the ends of the connection.”