“The Conditions of Contract are the core clauses for main Option B, dispute resolution Option W and secondary Options X5, X7…of the NEC3 Engineering and Construction Contract June 2005 (with amendments June 2006).”
“Option X5 • The completion date for each section of the works is section description completion date 1 Completion of the powerhouse, including14 February 2011 Installation of the overhead crane, sufficient to allow installation of the SSE switchgear. The powerhouse is secure, wind and watertight section description completion date 1 Completion of the powerhouse, including14 February 2011 Installation of the overhead crane, sufficient to allow installation of the SSE switchgear. The powerhouse is secure, wind and watertight 2 Completion, including testing, of the intake,27 May 2011 penstock pipeline and tailrace and the powerhouse (including building services), to allow Hydro Plant to be installed 3. Completion of all work not included in4 October 2011 sections 1 and 2 Option X7 • Delay damages for each section of the works are section description amount per day 1 Completion of the powerhouse, including£1,000.00 Installation of the overhead crane, sufficient to allow installation of the SSE switchgear. The powerhouse is secure, wind and watertight 2 Completion, including testing, or the intake,£2,544.00 penstock pipeline and tailrace and the powerhouse (including building services), to allow Hydro Plant to be installed 3. Completion of or work not included in£600.00 sections 1 and 2”
“11.1 In these conditions of contract, terms identified in the Contract Data are in italics and defined terms have capital initials… 11.2 (2) Completion is when the Contractor has • done all the work which the Works Information states he is to do by the Completion Date and… If the work which the Contractor is to do by the Completion Date is not stated in the Works Information, Completion is whenthe Contractor has done all the work necessary for the Employer to use the works and for Others to do their work… (4) The Contract Date is the date when this contract came into existence… (9) A Key Date is the date by which work is to meet the Condition stated. The Key Date is the key date stated in the Contract Data and the Condition is the condition stated in the Contract Data unless later changed in accordance with this contract… (10) Others are people or organisations who are not the Employer, the Project Manager, the Supervisor, the Adjudicator, the Contractor or any employee, Contractor or Supplier of the Contractor… (19) Works information is information which either • specifies and describes the works or • states any constraints on how the Contractor Provides the Works and is either • In the documents which the Contract Data states it is in or • In an instruction given in accordance with this contract." (b) Clause 17.1 addresses ambiguities and inconsistencies: “The Project Manager or the Contractor notifies the other as soon as either becomes aware of an ambiguity or inconsistency in or between the documents which are part of this contract. The Project Manager gives an instruction resolving the ambiguity or inconsistency." (c) Clauses 18 and 19 deal with illegality, impossibility and acts of prevention: “18.1 The Contractor notifies the Project Manager as soon as he considers that the Works Information requires him to do anything which is illegal or impossible. If the Project Manager agrees, he gives an instruction to change the Works Information appropriately. 19.1 If an event occurs which • stops the Contractor completing the works or • stops the Contractor completing the Works by the date shown on the Accepted Programme and which • neither Party could prevent and • an experienced contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for it, the Project Manager gives an instruction to the Contract stating how he is to deal with the event." (d) Clause 20.1 requires the Contractor to provide "the Works in accordance with the Works Information". Clause 25.3 states in relation to Key Dates: “If the Project Manager decides that the work does not meet the Condition stated for a Key Date by the date stated and, as a result, the Employer incurs additional cost either • in carrying out work, or • by paying an additional amount to Others in carrying out work on the same project, the additional costs which the Employer has paid or will incur is paid by the Contractor. The Project Manager assesses the additional costs within four weeks of the date when the Condition for the Key Date is met. The Employer’s right to recover the additional cost is his only right in the circumstances." (e) Clause 30 deals with time: “30.1 The Contractor does not start work on the Site until the first access date and does the work so that Completion is on or before the Completion Date. 30.2 The Project Manager decides the date of Completion. The Project Manager certifies Completion within one week of Completion. 30.3 The Contractor does the work so that the Condition stated that each Key Date is met by the Key Date.”
“Section 1 Completion of the powerhouse, including installation and commissioning of the overhead crane, sufficient to allow installation of the Hydro Plant and SSE switchgear. The powerhouse is secure, wind and watertight. Completion of section 1 is defined as completion of the following items of the works: • completion of the powerhouse and building structure including foundations, floors, walls, doors and other wall penetration. • all of the powerhouse overhead crane including testing and commissioning such that it can be used to install the hydro plant. • all of the permanent access tracks. • the penstock pipeline downstream interface with the powerhouse is completed and all testing associated with the interface has been completed. Section 2 Completion, including testing, of the intakes, penstock pipelines and tailrace, and the powerhouse (including building services, to be completed to allow the hydro plant to be tested and commissioned. Completion of section 2 is defined as completion of the following items of the works: • all of the intakes and associated facilities; • all of the penstock pipelines and associated facilities, except the surface reinstatement; • all of the tailrace; • all of the tailrace screen; • all of the supply, installation and testing of communications cable between the powerhouse and the intake; • all of the powerhouse and building services; Section 3 Completion of all of the works not included in Sections 1 and 2 Completion of section 3 is defined as completion of the following items of the works: • completion of all of the works not included in sections 1 and 2 including casting in of the hydro plant and all reinstatement and restoration of the Site.”
“The programme identified as "Black Rock Hydro Scheme Tender Programme-Rev C” is submitted for acceptance and is capable of being developed into the Accepted Programme”
“…that Completion of section 2 of the Works is defined by paragraph 6.2 of the Works Information, Part 1 as completion of the following items of work: • all of the intakes and associated facilities; • all of the penstock pipelines and associated facilities, except the surface reinstatement; • all of the tailrace; • all of the tailrace screen; • all of the supply, installation and testing of communications cable between the powerhouse and the intake; • all of the powerhouse and building services.” • all of the intakes and associated facilities; • all of the penstock pipelines and associated facilities, except the surface reinstatement; • all of the tailrace; • all of the tailrace screen; • all of the supply, installation and testing of communications cable between the powerhouse and the intake; • all of the powerhouse and building services.”
“Completion, including testing, of the intake[s], penstock pipeline[s] and tailrace, and the powerhouse (including building services) to be completed to allow the Hydro Plant to be [tested and commissioned] installed.”