“31.3 DISAGREEMENT ON ADJUSTMENT OF THE CONTRACT PRICE If the Contractor and the Employer are unable to agree on the adjustment of the Contract Price, the adjustment shall be determined in accordance with the rates specified in Part L, Schedule L1.3 Schedule of Rates. If the rates contained in the Schedule of Rates (Schedule L1.3) are not directly applicable to the specific work in question, suitable rates shall be established by the Engineer reflecting the level of pricing in the Schedule of Rates (Schedule L1.3). Where rates are not contained in the said Schedule, the amount shall be such as is in all the circumstances reasonable. Due account shall be taken of any over- or under-recovery of overheads by the Contractor in consequence of the Variation.”
“The Employer has secured the services of the MPI Resolution… . This Variation Order formalises the Employer making available the MPI Resolution and certain project equipment and services to the Contractor for use to install to install (sic) foundations at the Robin Rigg site, in order to mitigate delays to the Works. Deployment of the MPI Resolution partly replaces some of the working time for vessel Lisa A from the scope of the Agreement. … Contractual arrangements shall be as follows: • E.ON contracts directly with MPI for the vessel operational with the personnel and equipment detailed [on an attached sheet]. … • MTH provide supervision on Resolution … • MTH manage/coordinate the overall foundation installation operation by Lisa, Resolution and any other vessels.” • E.ON contracts directly with MPI for the vessel operational with the personnel and equipment detailed [on an attached sheet]. • MTH provide supervision on Resolution • MTH manage/coordinate the overall foundation installation operation by Lisa, Resolution and any other vessels.”
“The Employer has secured the services of the MPI Resolution. This Variation Order formalises the agreed provision by the Employer of the MPI Resolution, and certain project equipment and services, to the Contractor for use to install wind turbine generator foundations at the Robin Rigg site, in order to mitigate delays to the Works. The agreed deployment of the MPI Resolution reduces the work that will be undertaken by the vessel Lisa A. … Contractual arrangements shall be as follows: • MTH retain overall contractual responsibility for design, supply, transportation, storage, handling, and installation of foundations in accordance with the Agreement. … • E.ON contracts direct with MPI for the vessel operational with the personnel and equipment detailed [in an attached document] … • MTH manage/coordinate the overall foundation installation operation by Lisa, Resolution and any other vessels” • MTH retain overall contractual responsibility for design, supply, transportation, storage, handling, and installation of foundations in accordance with the Agreement. … • E.ON contracts direct with MPI for the vessel operational with the personnel and equipment detailed [in an attached document] … • MTH manage/coordinate the overall foundation installation operation by Lisa, Resolution and any other vessels”
“85 In reaching that conclusion I have not had recourse to what is ‘unbusinesslike’, or to ‘commercial sense’ or even to ‘business commonsense’, which are all frequently invoked since the decision in Antaios Naviera SA v Salen Rederierna AB[1985] AC 191 . Those expressions are a temptation for the court to make a contract for the parties; and it has been said many times that the court should not do that. See for example, Lord Mustill in Charter Reinsurance Co Ltd v Fagan [1996] CLC 977 at p. 984B;[1997] AC 313 at p. 388C. 86 If necessary I would refer, as Lord Mustill did, to what Lord Reid said in Wickman Machine Tool Sales v S Schuler AG[1974] AC 235 at p. 251: The fact that a particular construction leads to a very unreasonable result must be a relevant consideration. The more unreasonable the result the more unlikely it is that the parties can have intended it, and if they do intend it the more necessary it is that they shall make that intention abundantly clear. So far as I am aware that sentiment has not been criticised or reversed.”
“Nonetheless, in my judgment the subclause has no very natural meaning and is, at the least, open to two possible meanings or interpretations — one the judge's, the other that it addresses two separate subject-matters. In these circumstances, it is especially important to undertake the exercise on which the judge declined to embark, that is to consider the implications of each interpretation. In my opinion, a court when construing any document should always have an eye to the consequences of a particular construction, even if they often only serve as a check on an obvious meaning or a restraint upon adoption of a conceivable but unbusinesslike meaning. In intermediate situations, as Professor Guest wisely observes in Chitty on Contracts (28th edn.) vol. 1, para. 12–049, a ‘balance has to be struck’ through the exercise of sound judicial discretion.”
“If the language of the bond leads clearly to a conclusion that one or other of the constructions contended for is the correct one, the court must give effect to it, however surprising or unreasonable the result might be. But if there are two possible constructions, the court is entitled to reject the one which is unreasonable and, in a commercial context, the one which flouts business common sense.”
“20It is not in my judgment necessary to conclude that, unless the most natural meaning of the words produces a result so extreme as to suggest that it was unintended, the court must give effect to that meaning. 21 The language used by the parties will often have more than one potential meaning. I would accept the submission made on behalf of the appellants that the exercise of construction is essentially one unitary exercise in which the court must consider the language used and ascertain what a reasonable person, that is a person who has all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract, would have understood the parties to have meant. In doing so, the court must have regard to all the relevant surrounding circumstances. If there are two possible constructions, the court is entitled to prefer the construction which is consistent with business common sense and to reject the other. 22 This conclusion appears to me to be supported by Lord Reid's approach in Wickman Machine Tool Sales Ltd v L Schuler AG[1974] AC 235 quoted by Sir Simon Tuckey and set out above. I am of course aware that, in considering statements of general principle in a particular case, the court must have regard to the fact that the precise formulation of the proposition may be affected by the facts of the case. Nevertheless, there is a consistent body of opinion, largely collated by the buyers in an appendix to their case, which supports the approach of the judge and Sir Simon Tuckey.”
“In determining the meaning of the language of a commercial contract, and unilateral contractual notices, the law therefore generally favours a commercially sensible construction. The reason for this approach is that a commercial construction is more likely to give effect to the intention of the parties. Words are therefore interpreted in the way in which a reasonable commercial person would construe them. And the standard of the reasonable commercial person is hostile to technical interpretations and undue emphasis on niceties of language.”
“WHEREAS i) The Employer wishes to build, own and operate up to 60 wind turbine generators with an electrical output of up to 200 megawatts at Robin Rigg (hereinafter referred to as “the Project”), ii) The Project shall be located at the offshore location of Robin Rigg, off the coast of the Solway Firth, Scotland, iii) The Contractor hereby agrees to undertake to perform the Works in accordance with this Agreement, iv) The Employer hereby appoints the Contractor to complete the Works in consideration for the Contract Price. NOW THEREFORE the Parties hereto agree as follows: Part C, List of Definitions Part D, Conditions of Contract Part E, Commercial Schedules Part L, Schedule of Prices, Payment Profile and draft Programme … Part I, Technical Requirements Part J, Contract Management Park K, Master Programme Annexes …”
“8. OBLIGATIONS OF THE CONTRACTOR 8.1 GENERAL OBLIGATIONS The Contractor shall, in accordance with this Agreement, design, manufacture, test, deliver and install and complete the Works: (i) with due care and diligence expected of appropriately qualified and experienced designers, engineers and constructors (as the case may require); (ii) within the Time for Completion; (iii) providing all necessary Contractor’s Equipment…; 12 CONTRACTOR’S PROGRAMME & EXECUTION PLAN 12.1 PROGRAMME TO BE FURNISHED The Contractor shall submit to the Engineer for approval within eight (8) weeks of the Commencement Date, the Programme which shall provide for each Section of the Works to be completed in accordance with relevant Time for Completion and the initial draft Programme in Part L, Schedule L1.5 and the requirements set out in this Clause and as amplified by the Employer’s Requirements. … … Where the Contractor through its own acts or omissions fails to make available the Programme in accordance with the requirements of this Clause the Engineer shall be entitled to withhold ten per cent (10%) of future milestone payments until the Engineer is reasonably satisfied that the Contractor has submitted a programme that is in accordance with Employer’s Requirements. The Engineer shall provide seven (7) days written notice of its intention to withhold such sums from future milestone payments. 14.1 CONTRACTOR'S EQUIPMENT The Contractor shall provide all the Contractor's Equipment necessary to Complete the Works unless otherwise stated in the Employer's Requirements. All the Contractor's Equipment shall, when brought on to the Site, be deemed to be exclusively intended for the execution of the Works. The Contractor shall not remove from the Site any such equipment, except: (a) when it is no longer required for the Completion of the Works; or (b) when the Engineer has given his consent. …” … 25 COMPLETION 25.1 TIME FOR COMPLETION The Works shall be Completed and shall have passed the Tests on Completion within the Time for Completion. … 26 EXTENSION OF TIME 26.1 EXTENSION OF TIME FOR COMPLETION The Contractor may, after first using Reasonable Endeavours to avoid or mitigate any delay, claim an extension of the Time for Completion if he is or shall be delayed in Completing the Works by any of the following causes: (a) extra or additional work constituting a Variation ordered in writing under Clause 31; … (e) Force Majeure; … … 27 DELAY IN COMPLETION 27.1 LIQUIDATED DAMAGES FOR DELAY IN COMPLETION If the Contractor fails to Complete all Sections A,B,C and D by the Key Date 22 (as set out in Part L, Schedule L1.6) the Contractor shall pay Liquidated Damages as follows:£5,000.00 (five thousand pounds sterling) per day which shall accrue starting from the day immediately following the Key Date 22 and shall continue to accrue until such time as Sections A, B, C and D of the Works have passed the Tests on Completion. … The maximum Liquidated Damages under this Clause is twenty per cent (20%) of the Contract Price. … Such Liquidated Damages shall, without prejudice to the Employer’s rights under Clauses 27, 28 and 45.2, be to the exclusion of any other remedy of the Employer in respect of the Contractor’s failure to Complete within the Time for Completion. … 27.2 PROLONGED DELAY If the Employer has become entitled to the maximum Liquidated Damages under Clause 27.1 he may by notice require the Contractor to Complete the Works. Such notice shall fix a final time for Completion that shall be within such period as shall be reasonable in the circumstances. If the Contractor fails to Complete the Works within such time, and this is not due to a cause for which the Employer or an Employer’s Other Contractor is responsible, the Employer may by further notice to the Contractor either: (a) require the Contractor to Complete the Works; or (b) may himself or by any other contractor Complete at the Contractor’s risk and cost provided that he does so in a reasonable manner; or (c) may agree to accept those parts of the Works that have passed the Tests on Completion and reject those parts of the Works that have not been Completed and shall be entitled to recover all sums paid in respect of those parts of the Works not completed, together with the cost of dismantling the same, clearing the Site and returning such dismantled Plant to the Contractor or otherwise disposing of it in accordance with the Contractor’s instructions; or (d) terminate this Agreement forthwith without prejudice to any other rights of the parties under this Agreement. … 31. VARIATIONS 31.1 ENGINEER’S RIGHT TO VARY The Engineer following consultation with and approval from the Employer may by Variation Order to the Contractor at any time before the Works are Taken-Over, instruct the Contractor to Vary any part of the Works. A Variation Order shall constitute an Engineer’s Instruction. The reasonable cost of preparing information for a Variation by the Contractor shall be deemed to be included in the Contract Price. The Contractor shall not Vary any part of the Works, except in accordance with a Variation Order from the Engineer as set out in Clause 31. 31.2 VARIATION ORDER PROCEDURE Prior to any Variation Order under Clause 31.1, the Engineer shall notify the Contractor of the proposed nature and form of such proposed Variation. As soon as possible after having received such notice and in any event no later than seven (7) days, the Contractor shall submit to the Engineer: (a) a detailed description of work, if any to be performed and a programme for its execution; and (b) the Contractor’s proposals for any necessary modifications to the Programme according to Clause 26.1 [extensions of time] or to any of the Contractor’s obligations under this Agreement; and (c) the Contractor’s proposals for adjustment to the Contract Price. … Following the receipt of the Contractor’s submission the Engineer shall, after due consultation with the Employer and the Contractor, decide as soon as possible whether or not the proposed Variation shall be carried out. If the Engineer decides that the proposed Variation shall be carried out, he shall issue a Variation Order clearly identified as such, in accordance with the Contractor’s submission or as modified by agreement. If the Engineer and the Contractor are unable to agree the adjustment of the Contract Price, the provisions of Clause 31.3 shall apply. Instructions to the Contractor to Vary the Works within the scope of this Agreement shall be given by the Engineer on a standard form entitled “Variation Order” which shall be serially numbered. The Variation Order shall constitute the sole method of authorisation by which the Contractor shall be instructed to vary the Works in accordance with the provisions of this Agreement. The Contractor should ensure that he has received a Variation Order before Varying the Works. Following agreement with the Contractor or determination by the Engineer pursuant to Clause 31.3, of the addition to, or deduction from, the Contract Price attributable to a particular Variation, such addition or deduction shall be evidenced by the issue by the Engineer of a form entitled “Variation to the Contract Price”
"L1.1 Segregation of Price … Total (Euro) 8 Installation of all MP (including mobilization/demobilization) 22,104,888 … 11 Installation of all TP (including mobilization/demobilization) Included in 8 … 16 Wait on Weather Allowance 3,578,593" (2) By Section L1.3: "