“Throughout the Term where and so often as the occasion shall require to keep the whole of the Premises including the Building . . . in good and substantial repair and condition (damaged by any of the Insured Risks only excepted . . .”
“When necessary to replace and renew and to keep clean all windows in the Premises.”
“No case, in my opinion, has been a more misunderstood, or more frequently misapplied, then Proudfoot v Hart, as I think that further information supplied in the present case well illustrates.”
“Repair is not confined to houses; it applies to chattels, and it connotes the idea of making good damage so as to leave the subject so far as possible as though it had not been damaged. It involves renewal of subsidiary parts; it does not involve renewal of the whole. Time must be taken into account; an old article is not to be made new; but so far as repair can make good, or protect against the ravages of time and the elements, it must be undertaken.”
“. . . well and sufficiently maintain, uphold, support, and keep in good, substantial, and tenantable repair, order, and condition, all and singular the premises hereby demised.”
“GRP roof lights worn, some degraded and fibres exposed.”
“Some of the rooflights appear to be approaching the end of their life expectancy and will soon require attention. UV attack has caused degradation of the external surface resulting in opaque, fibrous sheets.”
“3.1 Glass fibre reinforced polyester (GRP) has been manufactured into profiled roof lights since circa 1955. Performance was greatly improved in the late 1970s with development of gelcoats and thin films applied during manufacture which reduced ultraviolet light transmission into the polyester resin layers and erosion of the exposed surface. Ultraviolet light degrades plastics including polyester causing the rooflights to turn brown in colour, become more brittle and loose the polyester resin from the surface as they age. This degradation of the exposed surface reduces the light transmission into the building. Pre 1980s polyester resin formulations tended to fail between 10 and 15 years. During the 1980s there were significant improvements to durability as the resin chemicals were developed for this market increasing the functional life to between 20 and 30 years. 3.2 Once the resin has been abraded by wind driven dirt the glass fibres are exposed on the top surface. The glass fibres then trap dirt and the light transmission into the building will be significantly reduced.”
“As agreed with Chris Collins this morning, the cladding panels to the rear and side elevation that are damaged due to tenant impact damage are not to be replaced. The cladding works to these elevations will therefore only involve the replacement of panels identified as having been damaged by the blast, utilising panels obtained from the other side elevation where the cladding has been completely replaced. Chris reported that his (sic) will check one last time with the tenants, but if we do not here (sic) from him by the end of the week we are to proceed in this manner.”
“(1) Where a claimant has delayed unreasonably in commencing or prosecuting proceedings, the court may exercise its discretion either to disallow interest for a period or to reduce the rate of interest. (2) In exercising that discretion the court must take a realistic view of delay. In the case of business disputes, litigation is, for all parties, an unwelcome distraction from their proper business. It is not reasonable to expect any party to take every litigious step at the first possible moment, or to concentrate on litigation to the exclusion of all else. Delay should only be characterised as unreasonable for present purposes when, after making due allowance for the circumstances, it can be seen that the claimant has neglected or declined to pursue his claim for a significant period. (3) When determining what disallowance or reduction of interest should be made to mark a period of unreasonable delay, the court should bear in mind that the defendant has had the use of the money during that period of delay.”