“2. The Defendant, London & Newcastle (Camden) Ltd ("L&N") was and is the long leaseholder of a site at 30 Oval Road, London NW1. It seems to be a special purpose vehicle and part of the larger London & Newcastle property development group. L&N engaged consultants and contractors, Ardmore, to design and construct a substantial number of luxury flats and social housing at this site. By an agreement in writing dated22 September 2010 made between L&N and Andrie Lazari, the Claimant, L&N agreed to complete the construction of Flat 42 ("the Flat") and to sell it to her on a long lease, the purchase price being£1.45 million . The Lease was dated15 December 2010 . Ms Lazari has not yet moved into the Flat as a result, as she asserts, of a continuing defect or problem which is or at least has been excessive overheating of her flat. Initially, L&N did not consider that there was any problem at all or at least which was its responsibility. Eventually, and upon receipt of a report by BRE, commissioned by her in late 2011, which identified a significant overheating problem, L&N initiated remedial works in or about mid-2012; the main problem appears to have been other hot heating pipes which run immediately under Flat 42 which cause overheating within the Flat. It seems that initially these were unsuccessful or at least not as successful as hoped for. Further work including commissioning and re-commissioning work was done in about September and early October 2012. However, that did not resolve the overheating problem and Ms Lazari, who has a medical condition which has resulted in her walking with crutches and with various access needs, was unable to move in following treatment which she had in mid-September 2012, she says as a result of the continuing and serious overheating problems. 3. She issued proceedings on16 October 2012 following essentially what she regarded as the breakdown in the co-operation which she and her expert required from L&N and its consultant, Mr Dougan of Hoare Lea. Following a contested hearing on24 October 2012 before Mr Justice Edwards-Stuart, he granted injunctions against L&N in effect requiring them to cooperate by providing access for Ms Lazari's expert (Mr Swainson) to inspect the remedial works in various parts of the mechanical installations and to carry out various tests and to provide relevant documents, plans and data germane to the original and remedial works. He ordered L&N to pay her costs of the application.”
“In my view, on the available information, a payment into court by L&N of£30,000 will encourage the parties to start serious settlement discussions and to concentrate minds about economic, timely and effective compliance with all the outstanding orders between now and trial in June 2013. This is a minimum figure which is currently justified on the available evidence: (a) It is highly likely that the expert costs identified will be substantially justified; they are relatively modest as they now stand (at some£6,400 ); they are also continuing. (b) The evidence that the wooden flooring has warped as a result of the sustained overheating is, currently, compelling and is unchallenged on the evidence (albeit it is not admitted in the Defence). Similarly there is no such challenge to the need for and costs of redecoration. The two sums claimed come to some£23,400 . (c) Ms Lazari will probably be entitled to some general damages. (d) It is likely on the available evidence that, either through general damages or by way of substantive damages, she will recover something for loss of the use of the Flat, although the precise time period for that is subject to challenge. At the very least, I can see a strong argument that some months of loss of use may well fall to be compensated to reflect at least the fact that remedial works have taken at least some 15 months to set up and effect.”
“The parties’ experts shall continue to meet with a view to narrowing issues and shall serve and file their joint statement underCPR Part 35.12 (3) by no later than 4pm30 April 2013 .”