“Gas meters are to be situated in the basement in locations as tabled at the Pre-Order meeting. Extra over costs requested for track pipe sub-mains from the meter positions up the risers and into the flat distribution network.”
“Please could you confirm with the consultants as to what size pipe is suitable for the gas runs.”
“Supply of Labour, Materials to include Sanitaryware, and associated Plant to carry out the Plumbing and Heating (Mechanical) Subcontract to the 103 Residential Properties and associated Communal Distribution Network/Pipework at the above Development.”
“2.2 [Mizen] advised that the first area of work would be the installation of the gas pipes, 1st fix to the A block 1st floor flats; screeding is presently programmed to commence on Tuesday,21st November 2006 and then proceed at the rate of 2 flats per day. [West 3] are to advise if they can commence on Monday, 20th November. Post Meeting note: [West 3] have confirmed that they will be commencing on Monday 20th November and will be able to keep in front of the screeders 2.3 [Mizen] are to chase [Wilkins MacKenzie Associates] for issue of revised drawings.”
“The drawing and specifications prepared by Wilkins Mackenzie Associates, against which you tendered and on which basis you completed the project, calls for gas distribution network of varying sizes from 28mm diameter upwards and for a network that delivers the gas to consumer outlets with a pressure drop not exceeding 1mbar. I have become aware that the network is single size (28mm diameter) throughout except for a 1.5/2.0m step down (to 15mm diameter) upside of the boilers. As you can see from the attached report, inter alia, the dynamic pressure loss is measured down to 14/15 mbar from a figure of 21mbar underside of the gas meters. I am aware that you adopted in your tender documents, a 25mm diameter distribution system, but from our perspective that had to be without prejudice to the gas pressure criteria written elsewhere in the paperworkpressure loss ≤ 1.0mbar throughout. Please accept this letter as a Formal Notice of Defect and Claim against West 3 Fabrications Limited in the matter and we urgently call for and await your remediation proposals post haste.”
“6.3 A technical solution is needed with regards to increasing the size of the flues where the [TracPipe] runs up. By increasing the size of the [TracPipe], there is space for fewer [TracPipes]. As such, consideration needs to be given as to whether this flue can be enlarged. 6.4 Mizen have advised that there is a strong possibility that this can be done by drilling through the floor slab.”
“An update was requested on whether it was possible to enlarge the flues containing the gas [TracPipe]. [Mr Charlton] has said that he has submitted the drawings to the Structural Engineers and is awaiting official confirmation that this is possible, [Mr Charlton] to chase.”
“15mm gas point left capped off in cooker space” and in relation to the Combi boiler: “22mm gas carcass rises to boiler turns out and reduces to 15mm to connect to boiler.”
“The pressure drop between the outlets of the meter and the points to be connected shall not exceed 1mbar at maximum flow conditions.”
“At the initial stages of building design and planning the designer/installer shall verify that the installation pipes will be adequate for both immediate and probable future requirements.”
“Subject to the Special Conditions these General Conditions of Sub-Contract are the applicable terms and conditions of the Sub-Contract Agreement and are the entire agreement between the Contractor and the SubContractor and no variation or amendment or the delivery of the Sub-Contractor’s terms and conditions shall have effect unless expressly confirmed in writing by the Contractor. In the event of an inconsistency between the General Conditions and Special Conditions, the Special Conditions shall prevail.”
“The Sub-Contractor shall comply with any instruction issued by the Contractor whether to vary the Sub-Contract Works or otherwise. No variation to the Sub-Contract Works shall be effective unless agreed and set out in writing (both in terms of scope and value) and signed by an authorised representative of the Contractor before execution.”