“It is assumed that the mix design provided has been adhered to throughout the Site Piling works from January to March 2008. It is also assumed that the cored samples received from the contiguous piled wall cast in March 2008 used the same raw materials as concrete poured at ‘the Site’ in January 2008. If these assumptions are correct, it is not likely that the concrete that entered the Claimant’s sewer was the same concrete poured by the Defendant on or about the 23/24 January 2008 .”
"Mr Abbott’s witness statement introduces the possibility that aggregates, other than those specified in the mix design, might have been present as in the concrete supplied to May Gurney. This therefore infers that the assumptions made on the basis of the evidence provided may not be correct. It also suggests that there is a possibility that the concrete supplied to May Gurney may have contained aggregate types similar to those found in the concrete within the sewer. My conclusions within the report were valid at the time of writing, given the information I was provided with at that time and the samples I examined. The facts of the examination remain the same. The interpretation of those facts, given the addition of the further information supplied, after the submission of my report, would alter my interpretation of the facts. This information raises the possibility that the coarse aggregate in the concrete for both the contiguous piled wall and the concrete from the sewer could have come from the same quarry and yet contain different components."