“The remedial works to the slabs under Warehouses 1 and 2 reasonably required to address the breaches pleaded in paragraphs 33 and 36 above. Although the Claimant began with a scheme of repairs to the slabs, it is becoming increasingly clear that the scale and extent of the defects in the slabs could only be satisfactorily addressed, with proper assurance of satisfactory performance of the slabs in the future, by complete removal and replacement of the whole of the slabs. The Claimant’s decision to replace the slabs was a reasonable decision, based upon a proven approach to the desire to let the Property to a tenant whose exact operational requirements could not be known. Only replacement gave the Claimant the confidence that the terms of the Employer’s Requirements - including Clause 2.08 of the Specification - would be satisfied." 9. A somewhat more detailed explanation is given at Paragraphs 83F to I of the proposed amended Schedule of Loss: “[83E was the same as Paragraph 83F of the earlier draft] 83F. The Claimant concluded, as the repair scheme was being implemented and indeed extended to cope with further areas of discovered damage as the slabs were opened up, that all of the slab in both warehouses was at risk of failure and that the only reasonable engineering and commercial response was the replacement of the whole of the slab using the incumbent remedial works contractor. 83G. The Claimant’s decision to replace the whole of the slabs under Warehouses 1 and 2 resulted from the on-going testing and inspection of the areas excavated as part of the repair scheme. As a result of on-going testing and inspection of areas opened up, the Claimant was increasingly concerned about (a) highly variable thickness of the slab; (b) further cracking evident to the slabs; (c) the generally very poor standard of construction of the slabs and the concern that the full extent of deficiencies in the slab could never be safely addressed by a repair scheme, since, unless identified and removed, further defects would always be a matter of concern and speculation: the increasing concern that the Defendant had delivered a generally ‘rogue floor’ and (d) the realisation that the slabs had never been subject to design load (as per Specification) and yet had failed in large measure, so that a future tenant wishing to impose load up to that permitted by the Specification would likely expose the slabs, if left or only partly repaired, to substantial risk of future cracking and/or failure. Whilst it is accepted that the discovery of the inadequacy of fibre content within the slabs represented, as the Claimant saw it, further and additional reasons to replace the slabs on grounds of widespread and serious poor design and/or workmanship, the decision to replace the slabs was, and was reasonably, justified on the basis of the concerns - summarised in this paragraph - which in turn derived from the breaches pleaded in paragraphs 33 and 36 of the Re-Amended Particulars of Claim. 83H. For the avoidance of doubt, as part of the process of deciding whether to repair or replace the slab, the Claimant and its experts have had available the Defendant’s proposal for the repair of the slab. The Defendant’s proposal has been rejected as inadequate on grounds which have been made known to the Defendant on an open basis. 83I. In all of the premises, the Claimant contends that the replacement of the slab was and is reasonably necessary and was, and remains, a reasonable course of action for the Claimant to have taken having regard to the nature and extent of the breaches pleaded in paragraphs 33 and 36 and as will be more fully updated and explained in the Claimant’s expert evidence in due course (or in a Scott Schedule of Defects if one is so ordered by the Court)…”
“…designed in accordance with the BCA Interim Technical Note II, Loading Category 3, Classification “Heavy” and will accommodate a uniformly distributed superimposed loading on 50.00 KN/m2 (1000 lbs/ft2) and pallet racking of 70 KN/leg (racking leg loading based on leg centres of 2.70m along length, 0.09m centres across width and 0.20m centres for back legs where positioned back to back)…”
“If, contrary to the case set out above, the Claimant is not entitled to recover the cost of complete replacement, the Claimant will claim the costs that would have been incurred to partially replace the floor slabs in the areas affected by the defects pleaded. The Claimant’s best estimate of that cost at present is the estimated cost of partial replacement projected in Cost Report number 8 in the sum of£822,899.07 .”
“The cost of reinstatement by reference to transportation and modification costs that have not been and will never be incurred, and which it would be unreasonable to incur, cannot fairly be regarded as caused by the defendants’ tort.”