“…that in the event that any dispute between the parties was referred to adjudication pursuant to the Scheme and one party paid money to the other in compliance with the adjudicator’s decision made pursuant to the Scheme, that party remained entitled to have the dispute finally determined by legal proceedings and if or to the extent that the dispute was finally determined in its favour, to have that money repaid to it." Paragraphs 13 to 15 address the performance by Aspect of its obligations with an assertion that the survey was carried out with reasonable care. Paragraphs 16 to 35 assert broadly that Higgins’ allegations in the adjudication about Aspect’s performance and on damages were wrong for a variety of reasons. So far as damages are concerned a number of the averments are that Aspect do not admit or put Higgins to proof on the issue of damages. There is then reference to the award of interest being for more than Higgins was entitled and to the adjudicator’s decision. At Paragraphs 40 and 41, it seeks a declaration as referred to above, repayment of the sum of£658,017 awarded against it by the adjudicator and the costs of the adjudication together with interest on any sums recovered by it. At Paragraph 42 it pleads: “Further or alternatively, Aspect paid the said sum to Higgins under compulsion of law. That compulsion will be released upon judgement hearin Aspect’s favour. Aspect will be entitled to restitution of the sum paid.”
“(1) A party to a construction contract has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section. For this purpose “dispute” includes any difference. (2) The contract shall— (a) enable a party to give notice at any time of his intention to refer a dispute to adjudication… (3) The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally “determining the dispute…”. (5) If the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply.”
“2. Where a construction contract does not comply with the requirements of section 108(1) to (4) of the Act, the adjudication provisions in Part I of the Schedule to these Regulations shall apply.”
“23. —(1) In his decision, the adjudicator may, if he thinks fit, order any of the parties to comply peremptorily with his decision or any part of it. (2) The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.”
“Of course that conclusion is not in itself sufficient for the Claimant in this case, because the Claimant is seeking to have the court finally determine the dispute decided by the adjudicator, as opposed to seeking to enforce the adjudicator's decision. It does however provide the platform for the Claimant's second submission that there is additionally an implied term that an unsuccessful party is entitled to bring court proceedings to have the dispute referred to the adjudicator finally determined and, if successful in persuading the court to reach a conclusion different to that reached by the adjudicator, to be repaid all sums paid by him in compliance with the decision.”
"approach was pragmatic. It is not a matter of jurisdiction. It is a matter of discretion. The deployment of negative declarations should be scrutinised and their use rejected where it would serve no useful purpose. However where a negative declaration would help to ensure that the aims of justice are achieved the courts should not be reluctant to grant such declarations. They can and do assist in achieving justice…So in my judgement the development of the use of declaratory relief in relation to commercial disputes should not be constrained by artificial limits wrongly related to jurisdiction. It should instead be kept within proper bounds by the exercise of the courts’ discretion."
“The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties.” (Emphasis added)
“that in the event that any dispute between the parties was referred to adjudication pursuant to the Scheme and one party paid money to the other in compliance with the adjudicator’s decision made pursuant to the Scheme, that party remained entitled to have the dispute finally determined by legal proceedings and if or to the extent that the dispute was finally determined in its favour, to have that money repaid to it.”