“CBUK confirmed that the current model includes for the slab edge detail that is detailed on WSP latest drawings, with the inverted tee, decking, double edge trim etc, but have made no allowance for the halfen ski assembly or for any temporary edge protection sockets. SRS advise that it was their intention to incorporate all of the above into one composite member if at all possible. CBUK are to advise SRS of a ‘last ditch drop dead’ date for receipt of information to have the model updated to include these prior to fabrication.”
"Early Works", “Main Tower" and "
“We have now received a formal complaint from our clients with regard to the quality of fabrication being produced. We have in the last week had one column returned 15 mm out of square, a column rejected at site with the bearing area underground and two loads rejected yesterday for unacceptable welding. It is difficult to argue that these occurrences are isolated and do not demonstrate a failing of our quality system as all items are allegedly inspected 100%, the requirements are clearly shown on the dimensional reports and the required weld finish on the drawings. Please provide an explanation on how and why these failing[s] occurred and what measures have been put in place to prevent a re-occurrence…”
“The attached is totally unacceptable! In general, our quality standards are dropping and it is concerning. We have well bedded systems in place that had been successful for years, so we have no excuses… It is your responsibility to ensure we deliver a quality product, of which Cleveland Bridge has built its reputation on, so do not let us down and put the business at risk…”
“As you are aware the Works forward load has indicated an extraordinary overload since October 2009. We have expressed concern over this, in particular the Shard programme and have requested that we sublet some of that work to reduce the load, of which to date we have not [been] able to achieve. We understand that we have managed to have some movement in other programmes that has assisted, but the Shard programme has actually increased (due to changing priorities, late issue of drawings and generally not meeting the specified tonnage). We have been trying to recruit, with little success and have been working excessive overtime. The RRP suggests that we employ a further 135 men, but this is a period of 2 months of which, you can appreciate, is impossible/impractical. I am looking at introducing 12 hour shifts, throughout the works, but this is at great expense and we will need to negotiate with the union. Our best option is to move the Shard programme out, but I am unsure what our contractual arrangements are. I suggest we review all of the programmes, as there has been further favourable movement on M74 and A46…”
“You will also need to fully demonstrate any programme implications relating to this matter rather than simply states that three weeks have been added to the programme???”
“Scope of Works:- • All things necessary for the fabrication of all tower steelwork between the ground and ninth floor levels, including all connection details the temporary works and other trades… • All ‘black’ steelwork necessary for the above works is deemed to have been procured under the terms of your previous agreement with Mace Ltd and is held at your works… • Delivery of all fabricated steelwork to our works to suit a pre-agreed programme and sequence-details to follow… Exclusions:- • Procurement of any further ‘black’ steelwork (any additional requirements which may arise will be provided free issue by ourselves)… Price:- A final account value is to be determined partly by re-measurement and partly by the inclusion of lump-sum values, comprising the following six items:- 1) Fully fabricate and deliver approximately 3826 tonnes of structural steelwork up to level 9, including forming all service penetrations (remeasured at£617.00 per tonne nett) 2) Design and detailing to completion up to level 9 (£85,000.00 lump sum nett) 3) Blast and prime steelwork (remeasured at£6.00 per m2 nett)… Programme:- Programme details to follow… Materials:- …Any further main bar or plate materials required to levels 0-9 required by CBUK will be requisitioned through SRS. All fittings material required by CBUK…will be supplied by SRS. Listing of any CBUK materials requirements to be issued in good time without detriment to the programme dates. Specifications and documents:- …Structural Specification-Section G… Movement and Tolerance Specification…”
“(1) Save where the provisions of the Sub-Contract otherwise requires, the Sub-Contractor shall carry out, complete and maintain the Sub-Contract Works such that no act or omission of his in relation thereto shall constitute, cause or contribute to any breach by the Contractor of any of his obligations under the Main Contract. (2) The Sub-Contractor shall carry out, perform and provide the Sub-Contract Works fit for purpose described in the Main Contract. Materials, goods and workmanship shall be the specified quality and to the satisfaction of the Contractor… (4) The Sub-Contractor shall commence, carry out and complete the Sub-Contract Works in accordance with the Contractor’s requirements in accordance with the Programme forming part of the Main Contract. Notwithstanding the foregoing, the Sub-Contract Works shall be performed at any time and/or in any sequence and with any degree of continuity of working as may be required from time to time by the Contractor and generally to suit the progress of the Works. (5) The Sub-Contract works are to be completed within the period specified in the Programme subject to such fair and reasonable extensions of time as the Contractor shall allow where the Sub-contract works are delayed by causes which resulted in an extension of time under the Main Contract.”
"Where the sufferer from a breach of contact finds himself in consequence of that breach placed in the position of embarrassment the measures which he may be driven to adopt in order to extricate himself ought not be weighed in nice scales at the instance of the party whose breach of contract has occasioned the difficulty. It is often easy after an emergency has passed to criticise the steps which have been taken to meet it, but such criticism does not come well from those who themselves created the emergency. The law is satisfied if the party placed in a difficult situation by reason of the breach of a duty owed to him has acted reasonably in the adoption of remedial measures, and he will not be held disentitled to recover the costs of such measures merely because the party in breach can suggest that other measures less burdensome to him might have been taken."