“12.1 A duty to act in the way that [Mr Dale] considered, in good faith, would be most likely to promote the success of the company for the benefit of its members as a whole (pursuant to section 172 (1), having regard to the matter is set forth in section 172 (1) (a) - (f)… 12.3 A duty (pursuant to section 174) to exercise reasonable care, skill and diligence that would be exercised by a reasonably diligent person… 12.3.1 the general knowledge, skill and experience that may reasonably be expected of a person carrying out the functions carried out by [Mr Dale] in relation to the company, and 12.3.2 the general knowledge, skill and experience that [Mr Dale] has or had at the material time.”
"principal cause of the cost overrun was the subcontracting cost of the Dragon LNG Project. The subcontracting was done by WOGL (under the control of the Defendant) and Volker Stevin. Further from about September 2007, the Defendant formed a steering committee with his counterpart at Volker Stevin (Rene Postulart) in a belated attempt to control the future costs of subcontracting on the Dragon LNG Project."
“20.1 The Defendant failed to arrange the organisational structure of WOGL and/or the joint venture so that it provided an adequate system of checks and balances and so that there was a system of adequate control over subcontractors and subcontracting expenditure; 20.2 The Defendant failed to ensure that appropriate contracts were in place with the various subcontractors, having regard to the fixed price EPC contract that WOGL had entered into for the Dragon LNG Project. As at19 October 2007 , approximately 70% of the subcontracts were 'reimbursable' contracts, meaning that the contracts effectively allowed subcontractors to charge for all labour, materials, equipment and transportation on an unlimited basis; 20.3 The Defendant failed to adequately control or supervise the subcontractors and the work that they undertook on the Dragon LNG Project (or to procure the control or supervision of the same); 20.4 The Defendant failed to adequately supervise or control expenditure on subcontractors (or to procure the control or supervision of the same). For example, the subcontracts for the mechanical works and fabrication of the inner tank and external pipework were on reimbursable contracts under which labour costs were charged on an unlimited hourly basis. The Defendant failed to implement and operate a proper system of checks to ensure that timesheets submitted for work to be charged actually reflected hours that had been worked by subcontract labour (or to procure the implementation or operation of the same); 20.5 The Defendant failed to take any or any appropriate remedial measures to try to bring the Dragon LNG Project under control. For example, even after difficulties were apparent, nearly 2.5 years into the project, the Defendant continued to hire subcontractors on reimbursable contracts.”
“By reason of matters aforesaid, WOGL and/or Cleveland have suffered loss and damage. The best particulars that they can provide prior to disclosure and/or the provision of any further information herein are as follows: 29.1 WOGL has suffered loss and damage of£50.6 million as a result of the cost overrun on the Dragon LNG Project…”
“7.2 Mr Sickles’ opinion is that the Claimant’s claims are supported, pending results of ongoing review. It is my view that Mr Sickles is not yet in a position to be able to give opinion which supports the Claimants’ allegations, yet he purports to do so. His opinion would seem to be premature and wholly unsupported by any reliable evidence. (Para 5.3) 7.3 Mr Sickles has not provided any opinion to support the case on causation or quantum at all. (Para 5.4) 7.4 Mr Sickles states at a number of points in his report that he is not able to find evidence that certain things were done by the Defendant. I consider his opinion to be inconclusive and wholly unsupported by any reliable evidence. (Para 5.5) 7.5 I do not believe that it is possible to conclude anything to support the Claimant’s claim in relation to the cause of cost overrun based on the documents provided. (Para 5.7)”
"The Defendant has incurred additional and/or wasted costs of approximately£300,000 . These include the costs of engaging additional consultants including structural engineers, CMP consultants and transport consultants"
“11.CPR 16.4 (1)(a) requires that a particulars of claim must include "a concise statement of the facts on which the claimant relies". Thus, where the particulars of claim contain an allegation of breach of contract and/or negligence, it must be pleaded in such a way as to allow the defendant to know the case that it has to meet. The pleading needs to set out clearly what it is that the defendant failed to do that it should have done, and/or what the defendant did that it should not have done, what would have happened but for those acts or omissions, and the loss that eventuated. Those are 'the facts' relied on in support of the allegation, and are required in order that proper witness statements (and if necessary an expert's report) can be obtained by both sides which address the specific allegations made. 12. It is plain that, on any view, the amendments contained in paragraph 16 of the Amended Defence and Counterclaim do not begin to meet the test in r.16.4(1)(a). It is impossible for anyone to work out from those generalised and generic allegations what particular matters were being alleged against Pantelli. It would be impossible for a solicitor to take a witness statement from those involved in providing the services in question that could hope to meet these points, because no details have been provided for a prospective witness to accept or dispute. Accordingly, paragraph 16 is not a proper pleading of a case of professional negligence. 13. Similarly, paragraph 36 is not a proper pleading of causation and loss. It is impossible to work out from that terse summary what facts CCD rely on in support of their contention that a particular breach or breaches has given rise to a particular head of loss. There is no answer to the question: but for the negligence, what would have happened and why? The damages claimed are wholly unparticularised.
“16. There is a second, separate reason why I am in no doubt that those parts of this Amended Defence and Counterclaim that purport to be allegations of professional negligence should be struck out. That is because, even though the work that is now the subject of these purported allegations was carried out three years ago, there is no expert evidence of any kind to suggest that that work was carried out inadequately, or was in some way below the standard to be expected of an ordinarily competent quantity surveyor. Not only is it simply not good enough to turn a positive contractual obligation into an allegation of professional negligence by adding the words "failing to" to the obligation, but it is also wholly inappropriate to do so in circumstances where there is no expert input to allow CCD to make such an allegation in the first place. 17. Save in cases of solicitors' negligence where the Court of Appeal has said that it is unnecessary (see Brown v Gould & Swayne [1996] 1 PNLR 130) and the sort of exceptional case summarised at paragraph 6-009 – 6-011 of Jackson & Powell, Sixth Edition, which does not arise here, it is standard practice that, where an allegation of professional negligence is to be pleaded, that allegation must be supported (in writing) by a relevant professional with the necessary expertise. That is a matter of common sense: how can it be asserted that act x was something that an ordinary professional would and should not have done, if no professional in the same field had expressed such a view?CPR Part 35 would be unworkable if an allegation of professional negligence did not have, at its root, a statement of expert opinion to that effect… 19. In the present case, although this is a claim that has been in existence for some years, CCD have chosen not to avail themselves of any expert input to support their allegations of negligence. There is no explanation for that failure. It is wrong in law and practice to make such unsupported allegations in this way, and I regret that they were ever made. In the light of the terms of the agreed unless order, they must be struck out.”