“Confirming yesterday's discussion: 5% limit on liquidated damages is accepted We will provide a 5% (GBP 80,000) bond until December 04 We will provide a milestone payment schedule by Friday 12 March If you send through a copy of your T&Cs, we can start to review.”
“Confirm all acceptable. Attached doc for your perusal. It's not yet complete as we still have loose ends to tie up with Costain so the contract specifics are still missing.”
“Further to our meeting yesterday with Iain, we seem to have one outstanding item, being settlement discount being included. As I recollect we agreed on an overall cost of£1,550,000.00 for the project, but still had issues over the payment being 60 days and also the fact that we could not make any payment for anything off-site. We agreed that we would raise the contract figure to£1,600,000.00 on the basis that£22,000.00 would accommodate your financing the project costs due to non-payment off site and£28,000.00 for the deduction of 2.5% settlement discount in order that we could make payment in 35 days from application dates agreed. If you are now stating this causes a problem then we have no alternative but to reduce the contract price by£28,000 and revert to 60 days payment terms.”
“Confirming our conversation this morning. We accept your proposal of 30-35 day payments, with valuations of onsite materials only; at a price of GBP 1,600,000. . . .”
“I understand that the only outstanding issue related to the 2.5% Discount Clause in the Sub-Contract is now resolved with Tony. To confirm, the agreement reached is that the Sub-Contract Amount is£1,637,500.00 which is subject to 2.5% Discount. Payment Terms to be based on 35 days. Therefore all remaining terms are now agreed in principle - could you please therefore confirm when we can anticipate receiving the formal sub-contract for signature. . . .”
“37. . . . We were only able to agree that the contract price should be£1.6 m , and that we could only apply for payment in respect of on-site materials. This price compensated us for financing the purchase of offsite materials. As to the issue of MCD, I believed that by the end of the conversation we had not reached agreement on whether the£1.6 million did or did not include any allowance for the MCD. 38. It was important to us that the£1.6 m did not include MCD because£40,000 (i.e. 2.5% MCD) would have a significant impact on the profitability of the project for us especially in the light of the reductions to the sub-contract sum already negotiated by [the Defendant]”
“Sub Contract Sum: Amend to reflect agreed amount of£1,637,500 (as attached E-Mail I Paterson to A Edwards dated 30/3/04) . . . Employers Liability£10 m /Public Liability£5 m ” . . . Employers Liability£10 m /Public Liability£5 m ”
“Further to receipt of your letter dated22 April 2005 as referenced above, we are very concerned that the proposed Contract Value does not reflect the final agreement between yourself and our Mr T Wells and respond to the individual points using your annotation: 1. We confirm the following and attach supporting correspondence [The relevant e-mails of March 2004 - to which I have already referred above - were then listed] The agreed value was£1,637,500 less 2.5% discount for 30/35 day payment terms - please therefore amend. 2. Noted. 3. Do not fully understand your comment - if the intention is that any shortfall between [the Claimant] insurance level of£5 m and the stated£10 m level, is to be covered by Site Insurances, then where is this stated. We would anticipate this being documented.”
“Level of Insurance (Referred to in Condition 4 (3) and to be£5,000,000 for any one occurrence unless otherwise stated):£10,000,000 ”
"But there is no legal obstacle which stands in the way of the parties agreeing to be bound now while deferring important matters to be agreed later. It happens every day when parties enter into so-called "heads of agreement"."