“(1) The Employer wishes to have demolished an existing Structure and have designed and constructed a new house at 13/14 Donne Place, London, SW3 2NG in accordance with the list of Drawings…attached or any subsequent amended or additional Drawings or details… (2) A Budget Cost of the Employers Proposals has been compiled and improved by the Employer (Document Marked "A" attached)… (3) The Contractor has agreed to demolish the existing Structure and design and construct the new house previously referred to including any additional work required by the Employer.”
‘The Contractor will complete the Construction of the House within fifteen months of the Date of Possession. If the Contractor fails to complete the works within 15 months of the Date of Possession the Contractor will incur no penalty.’
‘Determination The Employer shall be entitled to determine this Contract for any reason by giving the Contractor four weeks notice in writing. The Employer shall in those circumstances pay to the Contractor on the Date of Determination or as soon as can be ascertained. (1) The cost of the works to the Determination Date. (2) A proportion of the Contract Fee, being the percentage of the fee that bears relation to the cost of the works to date in relation to the Budget Cost. (3) Any other cost that the Contractor becomes liable for as a result of the determination.(4) The Contractor shall be entitled to determine this Contract for any reason by giving the Employer four weeks notice in writing and the Contractor shall be entitled to payment in accordance with Clauses 1-3 above.’
‘… (1) The Contract Fee to be paid by the Employer to the Contractor is a lump sum calculated as 15% of the Budget Cost described in the Articles. (2) The ‘Cost’ which the Contractor will be paid is the cost of carrying out the works whether or not that figure is greater than or less than the Budget Cost. (3) If the Final Cost is less than the Budget Cost them the Contractor will be paid 10% of the difference between the Budget Cost and the Final Cost as a bonus and this will be paid when the Final Cost is known. If the Final Cost is greater than the Budget Cost them the Contractor will be paid no additional Contract Fee on the first£100,000 of additional cost above the Budget Cost but will be paid 5% of the additional cost over and above the Budget Cost plus£100,000 and this will be paid when the Final Cost is known.’
‘…In order to responsibly specify fixed positions that will be final on the construction/tender issue drawings – we need to advance the detailing. We are ready to start the detailing however prior to commencing these works, Louise has asked me to request from you confirmation on our role on the Ives Street project.’
‘…MCD have carried out over a years worth of design changes on the plan form and were awaiting permission from Metronet prior to carrying out any further possible abortive drawing work as we cannot claim fees for this work as we are under contract for 15% cost plus once the construction commences if indeed [ISIL] still wishes to build as you had stated on a number of occasions that you may not build given the budget restraints. Knowing that you might not develop the site MCD have not produced detailed information at our risk. This has not held up the tender process or indeed any project item.’
‘… [DPIL] accepts that a Party Wall Surveyor had been appointed in relation to the project and that much of the work in relation to the Party Awards would be carried out by this Surveyor. [DPIL] also accepts that information might have been required from other professionals involved in the project in order to obtain the Party Wall Awards. However, as project manager, it was [MCD's] responsibility to give such directions to the Party Wall Surveyor and such other professionals as were appropriate and/or oversee their performance of their duties and/or to ensure that the Party Wall Surveyor had all information necessary to obtain Party Awards so as to ensure that the 3 party wall awards were obtained as quickly as possible and did not hold up work or cause it to be carried out in a piecemeal and inefficient fashion.’
‘The Contractor will complete the Construction of the House within fifteen months of the Date of Possession. If the Contractor fails to complete the works within 15 months of the Date of Possession the Contractor will incur no penalty.’
‘Furthermore, it was at no time suggested by [MCD] to [SC] or [DPIL/ISIL] that the Party Wall Awards were being held up by such minor changes to the design. If it had been, then a decision could have been made on a final design on that point.’
‘The Architectural Designer does not warrant: 1 that the services will be completed in accordance with the Timetable or the budget cost for construction works; …’
‘We have sent all information to Metronet which was requested they are reviewing the final information and should be ready to give approval within the next 7 days. They have requested and had been provided with Method Statements and Risk Assessments for: Construction, demolition, scaffolding and crane hire…’
‘I have reviewed the MS for demolition. I have no further comments. I await the RA. Please send all MS/RA on two hard copies signed. I await a MS/RA for the scaffold and the relevant calculations and dwgs… I would request to send the required RA for the demolition and the MS/RA for scaffold as soon as possible in order to review it before my leave and I will deal with the rest of the MS depending upon my return.’
‘Did you get my note on the scaffolding calcs they are asking for? I can confirm that I sent the MS and RA for the demolition. You will need a RA for the scaffolding which I will do now and send over but you won’t get a method statement or calcs for that until you get your subbie on-board.’
‘If you tell them that you need it in six or seven months time, they will not give you a price. They will not just jump and give you a price.’
‘Can you please update us with the status of the Party Wall Award for Ives Street. As you know the Client would like the whole award in place prior to demolition and we are due to demolish mid September.’
“We are awaiting decisions on ground floor layout for Ives Street so that we can finalise the design with …KLH who will be manufacturing form our drawings…Could you let me know as soon as possible regarding the decisions on the layout please.”
‘the negligence [insurance] is all good to go as soon as [LU] confirm that they are satisfied… This is the last piece of information required for Richard Birchall – the awards have been drafted and this letter will be enclosed and sent to the respective Surveyors…’
‘hi, can you please tell me why are the method statements not provided, I have seen that from the recent correspondence, from what I understand, the visit to the tunnel is only informative and has no bearing on our methods. are our method statements ready? if not, what are we waiting for?’
‘hi darling, I understand that but my question relates to an e-mail by Amy in the recent correspondence stating that "the method statements are missing" whatever that means. are we ready to go after this inspection or do we still have lots of leg work to do for the party wall awards?’
‘David [Akera] has sent everything once again to Melina at Metronet and hopefully by the end of next week we will get confirmation that we can progress and we will then get Richard Birchall to action the party wall award.… There was no basis on which LM could honestly have believed that this was the case. See above. That documentation was still missing is confirmed by Mr Akera's response to this e-mail of9 October 2008 .’
‘We have now obtained the demolition quotes and LUL are now insisting that method statements and risk assessments are not generic as submitted by Jim Moss of Eldridge Moss – they now want them from the subcontractor who will work on the project – the subcontractor will only produce this once appointed. This was the latest request from 2 weeks ago – we immediately went out to tender with Akera Engineers scheme… There was no basis on which [LM] could honestly have believed the statements being made. [LM] had known throughout the dealings with [LU] that no method statement had been provided on scaffolding. In relation to demolition, Metronet's letter of4 September 2008 (7 and a half weeks earlier and not 2 weeks earlier as stated) had made clear that site specific information was required. Despite this, no attempt had been made to obtain scaffolding or demolition quotes until shortly before this e-mail was written.’