“Please accept this as our Letter of Intent to enter into a Contract with Ellis… to carry out and complete the repair & refurbishment works to Bush Mews… At this point in time, certain elements of the design are required to be finalised by our directly employed Design Team and in the interim, to establish a Contract Sum we will base this Letter of Intent on Ellis…letter dated9 February 2009 and letter…dated17 March 2009 identifying a contract sum of£429,270.28 plus VAT. To this will be added a contingency sum of 10% which gives a Contract sum of£472,197.31 plus VAT… This letter provides you with the authority to commence all necessary preconstruction works to facilitate the earliest possible commencement date from the date of this letter. These works will be carried out under the specific terms of JCT 2005 Intermediate Building Works Contract, Clause 2.23 Liquidated Damages at the rate of £Nil per week…Date of issue of Interim Certificates as per Contact Particulars 4.6.1 shall state 14 days from date of possession. In the event of failure to conclude the Contract or either party deciding that the provision of the work should cease for whatever reason, the Employer’s total liability will be Ellis… pre-construction costs together with any costs and expenses reasonably and properly incurred together with associated overheads and profit. In the event that the formal Contract is not prepared prior to commencement, following commencement the parties agree that the works will be carried out under the specific terms of the JCT 2005 Intermediate Building Contract.”
“…we have conducted a periodic review…and are aware that the value of the works is fast approaching the value of that stated in your letter of intent dated18 June 2009 for a Contact sum of£472,197.31 plus VAT. Normally this would not be an issue as the letter of intent would have been superseded by the Contact Documents which had the necessary mechanism within them to cater for an increasing contract value. However, for reasons which are unclear to us, these documents are yet to be formally issued and therefore need to bring this matter to your urgent attention. As we see it there are two options for dealing with this situation:- As we see it there are two options for dealing with this situation:- 1. Issue a further letter of intent to cater for the increase in value of the works. 2. Formally issue the Contract Documents. We would anticipate that we are currently very close to the contract sum for the works actually carried out on site and have committed orders to various sub-contractors and suppliers that will exceed the value of the letter of intent. We would therefore very much appreciate if you could see your way clear to organising a prompt response to these matters…”
“Further to your letter of intent dated18 June 2009 , we now write to you to extend the authority of the aforementioned letter to expire on the execution of the Contract unless extended again in writing by us. These works will be carried out under the terms of JCT 2005 Intermediate Building Works Contract, Clause 2.23 Liquidated Damages at a rate of £Nil per week and Clause 6.7 Option C shall apply in respect of insurance. Dates of Interim Certificates as per Contract Particulars 4.6.1 shall state 14 days from date of possession. In the event of failure to conclude the Contract or either party deciding that the provisions of the work should cease for whatever reason, the Employer’s total liability will be Ellis… pre-construction costs together with any costs and expenses reasonably and properly incurred together with associated overheads and profit. We undertake to pay you the proper and reasonable costs incurred by you in working in accordance with the Drawings, Specification and Instructions issued by [FA] (acting as our Agents) for properly providing services, works, goods and materials for the Authorised Works, in accordance with this letter, providing that our liability to you will be extended by£107,802.69 …and will not exceed£580,000 …(the "Maximum Amount"). Both parties agree that the works will be carried out under the specific terms of the JCT 2005 Intermediate Building Contract. Please acknowledge receipt of this letter and confirm the acceptance of its contents by signing the duplicate copy and returning it to us.”
“FA issued two copies of the contract documents to [Ellis] for signature prior to being forward to [Mr Conway] for signing. [Mr Conway] is to then return a single signed copy of the contract to [Ellis]. FA requested [Ellis] include the second Letter of Intent prepared within the Contract Documents and forward a copy of this to FA for their records.”
“was concluded through direct negotiations between the parties. These negotiations culminated in a Letter of Intent dated18 June 2009 in the total sum of£429,270.28 , to which was added a 10% contingency making the total value of the Letter of Intent£472,197.31 …”
“The version of the IBC in force at that time [18 June 2009 ] was the version containing Revision 1 2007 with Attestation Update. This version of the IBC came into effect on1 April 2007 . This can be verified from the inside cover of the contract prepared by the Architect and handed to Ellis at the site meeting on30 June 2010 . However, should Mr Goldstein seek to challenge this and rely on the earlier and original version of this Contract, which is accepted by the Adjudicator, it matters not because all the relevant clauses and provisions relied upon by Ellis in this adjudication are common to both forms." 14. "The position regarding the contract documents developed on30 June 2010 , when at a site meeting held on site on that date, the Architect issued two copies of the contract documents to Ellis for signature. These documents, one signed by Ellis were to be sent to Mr Andrew Conway who was representing Mr Goldstein. Mr Goldstein would then sign them and forward one copy of the executed contract documents to Ellis. The minutes of this meeting are attached and item 2.20 refers.”
“The core of Mr Goldstein’s Response is that by a further Letter of Intent signed by both parties and dated4 May 2010 , as the contractual works were reaching an end, the parties agreed that Mr Goldstein’s maximum liability to Ellis would not exceed£580,000 (excl VAT); accordingly, Ellis’s claims for payment are not to be allowed save to the extent that they do not in aggregate (excluding VAT, and any interest) exceed£580,000 .”
“(b) the note at paragraph 2.20 of the30 June 2010 Project Meeting… may record the architects as having issued contracts for execution, and as having asked Mr Conway to return a single signed copy; but there is nothing which records Mr Conway as having formally agreed [so] to do, or to be bound by its terms. In the event, he and Mr Goldstein did not choose to sign a copy of the IBC so as to be bound fully, not only by its standard terms, but also by the parts which had been inserted by Ellis. In any event, there is no doubt that any such signature would have been accompanied by a formal record and insertion of the Maximum Amount which had been agreed in writing between the parties; and (c) it is not accepted that the parties have conducted themselves as though the contract document produced by Ellis…is in full effect; the parties have conducted their affairs in accordance with the terms of the two Letters of Intent and (in general terms, and save as otherwise amended) the general standard terms of the IBC, but subject (as from4 May 2010 ) to the Maximum Amount…”
“The sequence of events was that following the first Letter of Intent dated18 June 2009 , a second Letter of Intent was issued on4 May 2010 …Following this [FA] issued the contract documents at a site meeting on30 June 2010 . Item 2.20 refers as does paragraph 20 of the Referral. Nowhere in these contract documents is there reference to an agreed financial limit of£580,000 , despite the fact that the IBC documentation was issued after the Second Letter of Intent. Had there been the type of agreement contended for by Mr Goldstein then it is expected that [FA] would have recorded it in the contract documents, or in writing. They did not.”
“What is clear is that a cap was not incorporated into the contract documents issued after the second Letter of Intent…”
“23. The parties are agreed as to the issue of two Letters of Intent one on18 June 2009 and the other on4 May 2010 . The parties are also agreed that on30 June 2010 Mr Goldstein’s Architect issued a set of Contract Documents for Ellis to complete. 24. It is not disputed that Article 2 of those Contract Documents refers to a Contract Sum of£472,197.31 or such other sum as shall become payable under the Contract. 25. The disagreement arises because Mr Goldstein contends that the IBC incorporates the maximum financial cap as set out in his4 May 2010 Letter of Intent. 26. However, the copy of the Contract provided at Referral Appendix 8 does not incorporate any such term or cross reference to the letter itself, and in response Mr Goldstein does not direct me to any alternative set of documents in which such a term or cross reference is set out. 27. It is thus clear to me that the Parties contracted firstly on the Letter of Intent dated18 June 2009 second on the Letter of Intent dated4 May 2010 and finally on the Contract Documents prepared by Mr Goldstein’s Architect and handed to Ellis on30 June 2010 for completion. These documents were completed by Ellis and returned to Mr Goldstein and they do not include any term or cross reference to a maximum financial value in the manner set out in the4 May 2010 Letter of Intent and as contended by Mr Goldstein in this Adjudication.”
“In making this Decision I have taken into account all submissions made whether or not specifically mentioned herein.”
“From this and other cases, I conclude as follows in relation to breaches of natural justice in adjudication cases: “(a) It must first be established that the Adjudicator failed to apply the rules of natural justice; (b) Any breach of the rules must be more than peripheral; they must be material breaches; (c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant. (d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this. (e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto.” “(a) It must first be established that the Adjudicator failed to apply the rules of natural justice; (b) Any breach of the rules must be more than peripheral; they must be material breaches; (c) Breaches of the rules will be material in cases where the adjudicator has failed to bring to the attention of the parties a point or issue which they ought to be given the opportunity to comment upon if it is one which is either decisive or of considerable potential importance to the outcome of the resolution of the dispute and is not peripheral or irrelevant. (d) Whether the issue is decisive or of considerable potential importance or is peripheral or irrelevant obviously involves a question of degree which must be assessed by any judge in a case such as this. (e) It is only if the adjudicator goes off on a frolic of his own, that is wishing to decide a case upon a factual or legal basis which has not been argued or put forward by either side, without giving the parties an opportunity to comment or, where relevant put in further evidence, that the type of breach of the rules of natural justice with which the case of Balfour Beatty Construction Company Ltd -v- The Camden Borough of Lambeth was concerned comes into play. It follows that, if either party has argued a particular point and the other party does not come back on the point, there is no breach of the rules of natural justice in relation thereto.”
"The "without prejudice" rule is a rule governing the admissibility of evidence and is founded upon the public policy of encouraging litigants to settle their differences rather than litigate them to a finish. It is nowhere more clearly expressed than in the judgment of Oliver L.J. in Cutts v. Head[1984] Ch.290 , 306: "
"The Court must first ascertain all the circumstances which have a bearing on the suggestion that the Judge was biased. It must then ask whether those circumstances would lead a fair-minded and informed observer to conclude that there was a real possibility, or a real danger, the two being the same, that the tribunal was biased. 21. I am in no doubt that a fair-minded and informed observer would not reach any such conclusion here, and any suggestion to the contrary is entirely unrealistic. The adjudicator's letter of19th July 2010 , and his written decision, made clear that he was wholly unconcerned with the fact that an offer had been made. On the face of both documents, the adjudicator treated his knowledge of the fact of the offer as irrelevant. There is other evidence that supports that conclusion. On 14th July, that is to say at a time before the adjudicator was aware that an offer had been made, he noted that "many elements of the decision have been decided"
“The Court has then to decide whether, on an objective appraisal, the material facts give rise to a legitimate fear that the judge might not have been impartial…The material facts are not limited to those which were apparent to the applicant. They are those which are ascertained by the court.”