“2.26.5 Any impediment, prevention or default, whether by act or omission, by the Employer or any of the Employer’s Persons, except to the extent caused or contributed to by any default, whether by act or omission, of the Contractor or of any of the Contractor’s Persons. 2.26.6 The carrying out by a Statutory Undertaker of work in pursuance of its statutory obligations in relation to the Work, or the failure to carry out such work…”
“2.29.1 Provided: 1 the Employer has Issued a Non-Completion Notice for the Work or a Section; and 2 the Employer has Informed the Contractor in writing before the date when the Final Account and Final Statement (or, as the case may be, the Employer’s Final Account and Employer’s Final Statement) became conclusive as to the balance due between the Parties that he may require payment of, or may withhold or deduct, liquidated damages, the Employer may, not later than 5 days before the final date for payment of the debt due under clause 4.12, give notice in writing to the Contractor in the terms set out in clause 2.29.2.” 1 the Employer has Issued a Non-Completion Notice for the Work or a Section; and 2 the Employer has Informed the Contractor in writing before the date when the Final Account and Final Statement (or, as the case may be, the Employer’s Final Account and Employer’s Final Statement) became conclusive as to the balance due between the Parties that he may require payment of, or may withhold or deduct, liquidated damages, the Employer may, not later than 5 days before the final date for payment of the debt due under clause 4.12, give notice in writing to the Contractor in the terms set out in clause 2.29.2.”
“150 Loudoun Road Employer Response to Final Account/Final Statement I refer to your Final Account submission of17th November 2009 and Final Statement dated1st July 2010 in relation to the above project. I have considered and reviewed your Final Account submission in full on the basis of all of the substantiation provided, the relevant adjudication decisions and my own knowledge of the project together with the discussions in our recent meetings. Having completed this review, please find enclosed on behalf of Fenice Investments Inc its response to your final account identifying those adjustments to the Contract Sum identified in your Final Account submission which are agreed and those which were incorrect in your original submission and so for the purpose of the Contract are identified as disputed. Where an item is disputed, there is included in the enclosed response the correct valuation for that item. You will note that some of the items shown as disputed have been agreed between us in the sum recorded in this response in discussions which took place after your original Final Account submission. Where this is the case the items are nevertheless identified as disputed (on grounds that the correct assessment differs from that which was included in your formal Final Account submissions) but have been annotated to record the agreement subsequently reached for the relevant item. As you will see from the enclosed, when properly assessed the final Contract Sum as adjusted in accordance with Clause 4.2 of the Contract is£3,945,531.64 . Fenice has made payment to you to date of£4,067,634.00 . A balance of£122,102.36 is therefore due and payable to Fenice, relating to and calculated in accordance with the content if the enclosed response to your Final Account and is required to be paid in accordance with the timeframe set out in Clause 4.12.9.”
“that party may commence arbitration or legal proceedings within 28 days…”
“i) actions by the employer which are perfectly legitimate under a construction contract may still be characterised as prevention, if those actions cause delay beyond the contractual completion date. ii) Acts of prevention by an employer do not set time at large if the contract provides for extension of time in respect of those events.”
“The conduct therefore has to render it “impossible or impracticable for the other party to do the work within the stipulated time”
“It has been drawn to my attention your design for the setting out of the ground floor slab of the houses to the above is lower than the adjacent highway pavement levels. The works have therefore not been constructed in accordance with the design resulting in the main entrance doors being lower than the pavement level and the inevitable introduction of a combination of ramps and steps. Under clause 2.12 sole responsibility and ownership of the design is with JFC and as such any additional costs to rectify the works will be your responsibility… We urgently await your proposals to remedy these defects and deliver the project by the contractual completion date.”
“4.4 Architectural Matters a. ATP tabled the latest contractor’s proposals to overcome the defect to the main entrance levels to house 4 and 5. The proposals incorporate an internal step to house 4 and 5. b. HDG confirmed the internal step arrangement had been approved and JF should proceed as ATP drawing with the exception of the step to the hall and last step from stairs should align in a single plane.”
“I have agreed with Jerrams that completion of house 4 will not be a formal handover, Jerrams will maintain security, insurances etc, but we can get access for marketing. I have said that if the house and the externals are complete we would discount this off any claim we might make for LAD’s. Jerrams were going for a formal partial possession.”