"... the right to refer any matter in dispute arising under or in connection with the Sub-Contract or the carrying out of the Sub-Contract Works to adjudication and either party may at any time give notice in writing (hereinafter called the Notice of Adjudication) to the other of his intention to do so. The adjudication shall be conducted under 'The Institution of Civil Engineers' Adjudication Procedure (1997)' or any amendment or modification thereof being in force at the time of the said Notice of Adjudication."
"(b) Unless the adjudicator has already been appointed he is to be appointed by a timetable with the object of securing his appointment and referral of the dispute to him within 7 days of such notice."
"4.1 The referring Party shall within two days of receipt of confirmation under 3.1, or notification of selection under 3.2, or appointment under 3.3 send to the Adjudicator, with a copy to the other Party, a full statement of his case which should include: (a) a copy of the Notice of Adjudication; (b) a copy of any adjudication provision in the Contract, and (c) the information upon which he relies, including supporting documents. 4.2 The date of referral of the dispute to adjudication shall be the date upon which the Adjudicator receives the documents referred to in paragraph 4.1. The Adjudicator shall notify the Parties forthwith of that date."
"I consider that it is undesirable that every breach of the terms of the scheme, no matter how trivial, should be seized upon to impeach the process of adjudication. To do so would increase the tendency of parties to take a fine tooth-comb to every aspect of the adjudication in the hope of finding some breach of the Scheme on which to impeach an otherwise valid adjudication decision. I do not consider that that was either intended or the natural effect of a failure to comply with the Scheme. There may, of course, be cases where the documents included with the referral notice are so deficient that it affects the validity of the adjudication process. However, I do not consider that a failure to include the relevant construction contract until a day later can do so or does so on the facts of this case. Nor do I consider that a failure to include the construction contract can be said to amount to such a serious breach of the rules of natural justice that the decision should not be enforced. There is nothing obviously unfair in the documents relied on in relation to the construction contract being received by the adjudicator later than the referral notice ..."