“(7) Proceedings under this regulation must not be brought unless- (a) … (b) Those proceedings are brought promptly and in any event within 3 months from the date when grounds for the bringing of the proceedings first arose unless the Court considers that there is good reason for extending the period within which proceedings may be brought.” (a) … (b) Those proceedings are brought promptly and in any event within 3 months from the date when grounds for the bringing of the proceedings first arose unless the Court considers that there is good reason for extending the period within which proceedings may be brought.”
“Not compliant and which should be rejected”
"An amendment to a public contract during its currency may be regarded as being material when it introduces conditions which, had they been part of the initial award procedure, would have allowed for the admission of tenderers other than those initially admitted or would have allowed for the acceptance of a tender other than the one initially accepted."
"the mathematical formula to be used in the electronic auction to determine automatic re-ranking of tenders on the basis of the new prices or new values submitted by economic operators and incorporating the weighting of all of the criteria set to determine the most economically advantageous tender."
"sought advice of [their] solicitors and counsel and are confident that the whole tender process is flawed and was not compliant with the directive. For that reason [they] are advised that the award of the contract to 3663 is unlawful."