“ that the decision to paint the pool hall steelwork on site rather than off site was taken by the Defendant in October 2006 and was not taken as a result of the late finalisation of the steelwork design.”
“1. The original steel frame scheme was drawn and issued for approval on3rd August 2006 . 2. Comments regarding this issue were not received from WSP until27th September 2006 , which we are now in the process of looking at and subsequent changes are being actioned as necessary. 3. Revised GA’s will be issued in due course. 4. Also on the8th September 2006 we received from WSP up-dated drawings incorporating cladding rails added to elevation against the existing building. We confirm we are also in the process of adding these into the structure. 5. WSP have confirmed further revised drawings are due showing additional cold rolled. Finally you have confirmed more changes are in the pipeline, however these cannot interrupt the manufacture and therefore will be carried out as site work.”
“[WSP] have still not received a revised drawing following comments on [FBS] drawings. [Jackson] to chase [FBS].”
“Accordingly, so far as the CPR are concerned, the power to make declarations appears to be unfettered. As between the parties in [this action], it seems to me that the court can grant a declaration as to their rights, or as to the existence of facts, or as to a principle of law, where those rights, facts or principles have been established to the court’s satisfaction. The court should not, however, grant any declarations merely because the rights, facts or principles have been established and one party asks for a declaration. The court has to consider whether in all the circumstances, it is appropriate to make such an order … It seems to me that, when considering whether to grant a declaration or not, the court should take into account justice to the claimant, justice to the defendant, whether the declaration would serve a useful purpose and whether there are any other special reasons why or why not the court should grant the declaration.”
“i) The correct approach to the question of whether to grant negative declarations was one of discretion rather than jurisdiction. ii) The use of negative declarations should be scrutinised and their use rejected where it would serve no useful purpose, but where such a declaration would help ensure that the aims of justice were achieved, the court should not be reluctant to grant a negative declaration. iii) Before a court can properly make a negative declaration, the underlying issue must be sufficiently clearly defined to render it properly justiciable.”
“if a proper programme analysis, including changes to logic links, etc, was carried out, then it is likely this would demonstrate entitlement to an extension of time”