“2. By way of brief overview Mr Dawes contends that the Adjudicator’s Award was wrong and has overcompensated Treasure by up to£869,195 which sum Mr Dawes seeks to be paid back to him by Treasure by way of Defence and/or Cross Claim in these proceedings together with the interest on the sums Mr Dawes is repaid and appropriate cost award [sic]. 3. In addition Mr Dawes does not accept that the works are complete and/or had been properly constructed by Treasure. The quality of Treasure’s work is part of Mr Dawes’ Defence and Cross Claim in these proceedings [this of course is subject to discussion and further information]. 16…the certificates of making good defects should not have been issued by the Architect since the day they were issued defects existed in the works carried out by Treasure. Mr Dawes does not know why certificates of making good defects were issued by the Architect but would invite the Arbitrator to rule in due course that the certificates were improperly and invalidly issued. Annexed hereto are Schedules of the defects which still exist in Treasure’s work. These Schedules are served pursuant to the Arbitrator’s directions order… 21…Treasure is put to strict proof that the work instructed by the Architect is apparently to be valued as an architect’s instruction because it is Mr Dawes’ case that the work instructed by the Architect post practical completion is work of remedying defects in Treasure’s work or competing Treasure’s incomplete works…Insofar as the Arbitrator finds that works instructed by the Architect are works of remedying Treasure’s defective work or completing Treasure’s incomplete work then Mr Dawes invites the Arbitrator to declare that those works are not to be the subject of any further payments by Mr Dawes…the agreement contended for by Treasure…does not allow Treasure to be paid for remedying their own defects or completing their own incomplete work. 42… neither the certificates of practical completion nor the certificate of making good defects should have been issued by the Architect. In the premises therefore no retention is due to Treasure and the entire sum of£191,321.20 is not due to Treasure from Mr Dawes and in so far as it has already been paid to Treasure it falls to be repaid. In particular the reason and basis for the issue of the certificate of making good defects is wholly unknown to Mr Dawes not least because as at the date of issue of the same numerous defects remained at the premises and were being attended to by Treasure, as particularised in the Schedules annexed hereto… AMENDED CROSS CLAIM 68 The contents of the Amended Defence hereinabove are repeated. 69 Mr Dawes reclaims the sums paid to Treasure in the Adjudication, namely: • the Prime Costs Not Yet Claimed sum of£127,612.57 • overheads in the sum of£634,360.74 • management costs in the sum of£12,695.60 • contract fee of 76,197.33 • any VAT overpaid • the interests of£78,327.92 Total£869,195 plus VAT In the alternative the Learned Arbitrator is invited to decide the amount over-awarded to Treasure by the Adjudicator and to award the same by way of repayment to Mr Dawes, and/or to determine the sums properly due to Treasure in this arbitration and to so declare.”
“…For the avoidance of doubt, all offers previously made are now withdrawn. The present Arbitration divides into 2 parts. The first part is the claims made by Treasure in the amended Statement of Case and the Respondent’s claim for defects. The second part is the Respondent’s reclaim for money. An offer in relation to the first part is set out below. No offer is made in relation to the second part, but Treasure accept that an overall account will need to be taken when the position in relation to previous payments by Hayley Dawes is taken into account… The offer in relation to the claims made in the amended Statement of Case and the defects is set out below: 1. The amount claimed in the amended Statement of Case was£1,678,444.02 with am alternate amount claimed of£1,891,256.25 . Treasure will deduct the£800,000 which Mr Dawes is seeking from the lower of these two figures and waive the£162,256.90 extra from the additional claim. The net amount to go forward for the overall reckoning is, therefore,£878,444.02 . From this figure nothing is to be deducted in relation to defects but the Respondent’s claim to defects is settled at the same time…”
“It is very disappointing that you have not even acknowledged the letters we have written to you in relation to offers. Our client is keen to settle the dispute…The offers made by our client have not been met with any reciprocal offers from your client or any productive way forward. To demonstrate our client’s genuine attempt to resolve all the issues, our client is prepared to make a further and final offer which is time-limited. This offer does not reflect, in any way whatsoever, the underlying merits of our client’s position-it just reflects a desire to move forward. This offer is a Calderbank offer and is to be read by analogy with a Claimant’s Part 36 offer under the CPR and to have the same consequences. The Claimant will settle all of the claims and counter claims in the Arbitration for the sum of£400,000 plus VAT. A payment has been made for and on behalf of the Respondent in the sum of£1,018,000 , net of VAT and net of the Adjudicator’s fees (which the Court ordered to be borne by your client in any event). If this offer is accepted, it will involve a payment by the Claimant to the Respondent of£618,000 together with such VAT as is applicable. 1. The proper amount of VAT shall be determined by HMRC… 2. The sum in paragraph 1 includes all claims for interest to a date which is 28 days from the date of this offer. 3. To avoid any arguments about the meaning of this offer, both liability for and quantum of costs up to date which is 28 days from the date of this offer, shall be determined by the Arbitrator. Similarly, the Arbitrator shall determine the liability for his fees and expenses up to date which is 28 days from the date of this offer. 4. This offer is open for a period of 28 days from date of this offer on the terms in this letter provided it has not previously been rejected, superseded or replaced. Thereafter it may not be accepted…”
“We refer to your offer dated15th October 2008 . We confirm that it is accepted. We would suggest that a consent order to be prepared by you confirming the terms of the settlement. We would suggest that the order confirms the payment of£618,000 in 14 days as we see no reason for the payment of that principal sum to be delayed while the consideration on VAT and costs are on going.”
“9B.1 .1 Where pursuant to article 9A either Party requires a dispute or difference to be referred to arbitration then that Party shall serve on the other Party a notice of arbitration to such effect in accordance with [CIMAR] Rule 2.3… and an arbitrator shall be an individual agreed by the parties or appointed by the person named in the Appendix in accordance with Rule 2.3… .3 After an arbitrator has been appointed either Party may give a further notice of arbitration to the other Party and to the Arbitrator referring any other dispute which falls under article 9A to be decided in the arbitral proceedings and Rule 3.3 shall apply thereto.” .3 After an arbitrator has been appointed either Party may give a further notice of arbitration to the other Party and to the Arbitrator referring any other dispute which falls under article 9A to be decided in the arbitral proceedings and Rule 3.3 shall apply thereto.”
“The Claimant will settle all of the claims and counterclaims in the Arbitration…”