“(1) The Court has discretion as to- (a) whether costs are payable by one party or another; (b) the amount of those costs; and (c) when they are to be paid… (4) In deciding what order (if any) to make about costs, the court must have regard to all the circumstances, including- (a) the conduct of all the parties… (6) The orders which the court may make under this rule include an order that the party must pay- (a) a proportion of another party’s costs… (c) costs from or until a certain date only.. (e) costs relating to particular steps taken in the proceedings… (f) costs relating only to a distinct part of the proceedings at…” (a) whether costs are payable by one party or another; (b) the amount of those costs; and (c) when they are to be paid… (4) In deciding what order (if any) to make about costs, the court must have regard to all the circumstances, including- (a) the conduct of all the parties… (6) The orders which the court may make under this rule include an order that the party must pay- (a) a proportion of another party’s costs… (c) costs from or until a certain date only.. (e) costs relating to particular steps taken in the proceedings… (f) costs relating only to a distinct part of the proceedings at…”
“Expert evidence shall be restricted to that which is reasonably required to resolve the proceedings.”
“At [the meeting of the21 July 2008 ] it became clear that, even on a best case scenario, the Contractor was in considerable difficulties, was technically insolvent and not in a position to trade. The Claimant’s representative David Drew formed the view that the Contractor had not hitherto fully appreciated its financial position. However, the Claimant now has reason to believe that Mr Drew was mistaken in this regard and in fact the Contractor had for some time been aware of the extent of its financial difficulties. It was apparent to all at that meeting that the works would not be completed by the Contractor as it was not able to perform its obligations under the Building Contract despite the assistance provided by the Claimant. As the minutes of that meeting (Attached…) record, the Contractor indicated that it had no option but to cease all works on site and the Claimant confirmed that, if it did so, security would be brought to the site to secure the site and minimise the Contractor’s losses.”