“2. BAL hereby grants ODD an extension of time for completion of the Contract Works of one week up to24th July 2009 . 3. Subject to the terms of this Memorandum of Agreement and in respect of all and any matters, facts or circumstances occurring prior to21st February 2008 , ODD hereby acknowledges and agrees that it has no further claim of whatsoever nature against BAL and/or in relation to the Project for extension of time delay and/or loss and expense under the Contract… or otherwise. Therefore, in so far as any such claims, rights or entitlements may otherwise have arisen or accrued prior to21st February 2008 in favour of ODD, ODD hereby agree to waive all such claims, rights and entitlements against BAL and/or in relation to the Project generally. 4. For the avoidance of any doubt paragraph 3 above shall not in any way affect ODD’s rights and entitlements to claim money and receive payment for work done under the Sub-Contract (including the Variations) save that, in accordance with paragraph 3 above, for the period prior to21st February 2008 ODD shall not be entitled to claim for further extension of time for delay and/or loss and expense. 5. It is hereby agreed that Programme ref. “Const Prog ODD-02” (as attached and amended to show a completion date of24 July 2009 ) shall be the agreed programme for the purposes of ODD’s obligations to carry out and complete the Works, and for measuring and recording progress of ODD’s Sub-contract works…”
“1. Save for any defence of waiver or enforceable agreement to the contrary between the parties, a declaration that notices under clause 11.2.1… are conditions precedent to award extensions of time which without compliance, the Defendant is not entitled to an extension of time; or alternatively Save for any defence of waiver or enforceable agreement to the contrary between the parties, a declaration that notices under clause 11.2.1… are conditions precedent to award extensions of time prior to Practical Completion which without compliance, the Defendant is not entitled to an extension of time. 2. A declaration that any extension of time claimed by the Defendant for matters, facts or circumstances occurring on or after21 February 2008 : (i) shall be made in a manner consistent with the obligations set out in ODD-02… (ii) shall not be made in a manner inconsistent with the obligations set out in ODD-02… 3. A declaration that the Supplemental Agreement… (i) precludes claims by the Defendant in respect of the Sub Contract Works for loss and expense or extensions of time or otherwise in respect of all and any matters, facts or circumstances occurring prior to21 February 2008 ; (ii) precludes claims for delay events 2, 4 and 6 as advanced by the Defendant (assuming that the matters alleged in the claim for those delay events are correct).”
“2 (i) …ODD 2 was from4 March 2008 the contractual programme agreed by the parties, unless varied by agreement or extended in accordance with the provisions of the agreement. (ii) Any extension of time applied for after4 March 2008 had to take account of the periods, timing and sequencing of the work is shown on ODD 2. 3. … the Supplemental Agreement…: (i) precludes any claim for extension of time and/or loss and expense for any events which occurred before21 February 2008 ; (ii) in respect of claims 2, 4 and 6 notified on28 January 2008 , precludes the Defendant from recovering an extension of time in relation thereto in so far as the changes to the reinforcement were shown on the drawings issued to the Defendant before21 February 2008 ; (iii) in respect of claims 2, 4 and 6 notified on28 January 2008 , precludes the Defendant from recovering loss and expense in relation thereto in so far as the changes to the reinforcement were shown on the drawings issued to the Defendant before21 February 2008 .”
“1. Save for any defence of waiver or enforceable agreement and subject to the terms of Clause 11.7.1 of the Sub-Contract between the parties made on28th September 2007 , a failure by the Defendants to give a written notice under Clause 11.2.1 within 10 days of when a delay ought reasonably to have become apparent shall negate any entitlement of the Defendants to an extension of time. 2. In accordance with the Supplemental Agreement dated4th March 2008 ODD 2 was the agreed programme for the purposes of ODD’s obligations to carry out and complete the works and for measuring and recording progress of ODD’s sub-contract works. 3. The Supplemental Agreement dated4th March 2008 precludes any claim for extension of time and/or loss and expense for any events which occurred before21st February 2008 . In relation to delay claims 2, 4 and 6, the Supplemental Agreement precludes any claim for extension of time and/or loss and expense in relation to changes to the reinforcement shown on drawings issued to the Defendant before21st February 2008 .”