“Liability for Payment The Parties are to be jointly and severally liable for payment of my fees and expenses in any event. … Acceptance Any objections to this Scale and these Terms by the Parties shall be made in writing to me within 7 days of receipt.”
“This letter is written without prejudice to the responding party’s contention that the adjudicator does not have jurisdiction to deal with the matters purportedly referred to him.”
“A copy of the Notice of Adjudication was served by fax and post on the Responding Party on22 May 2008 . Accordingly, service of the Referral on both the Adjudicator and the responding Party should have occurred on29 May 2008 at the latest. It is clear from the correspondence referred to above that service of the Referral did not in fact take place until4 June 2008 . The Referral was therefore served out of time. In the circumstances, we invite the Adjudicator to now withdraw from the Adjudication. For the avoidance of doubt, we do not grant the Adjudicator the power to decide upon his jurisdiction. Should the Adjudicator not be prepared to withdraw from the adjudication, we invite the Adjudicator to revise the directions given in his letter dated5 June 2008 requiring service of the Response by Friday6 June 2008 to provide for service 7 days from the date of receipt by him of the Referral i.e by11 June 2008 .”
“This document, together with all future documents generated in this Adjudication is submitted without prejudice to the Responding Party’s contention that the Adjudicator does not have the Jurisdiction to deal with the matters purportedly referred to him.”
“18. As a result of the fundamental variations to the original Contract, the Adjudicator does not have jurisdiction to deal with the matters purportedly referred to him. … 20. The Responding Party invites the Adjudicator to consider his jurisdiction in light of the above and, having done so, invites the Adjudicator to withdraw from this misconceived Adjudication. For the avoidance of doubt, the Responding Party does not grant the Adjudicator the power to decide upon his jurisdiction.”
“You do not have jurisdiction to deal with the issues purportedly referred to you for the following reasons:- 1. If a contract is a construction contract to which the Act applies, the parties must comply with the Act and all the terms must be in writing. In circumstances where the contract is one to which the Act applies, but is not Act compliant in that not all the terms are in writing, then the Adjudicator does not have jurisdiction. This is the position here. The Adjudicator is referred to Treasure & Son Ltd v. Dawes[2007] EWHC 2420 (TCC) , which follows and clarifies the position in RJT Consulting Engineers Ltd v. DM Engineering (Northern Ireland) Ltd[2002] BLR 217 . 2. Any decision in the Adjudication would be a nullity as the Referral and its accompanying documentation were not served on the Adjudicator on30 May 2008 but rather on4 June 2008 . This is contrary to the prescriptive provision of the clause 41 of the original contract, and also contrary to the requirements of the Act, and accordingly the Adjudicator does not have jurisdiction.”
“In the light of [Halliwells’]contention that the Adjudicator does not have jurisdiction, we trust you will understand that return of a completed questionnaire has not been deemed necessary.”
“Given that there was a written contract between the parties and given that there was no evidence to support the submissions that this contract was changed, either fundamentally or at all, it would have been inappropriate for me to resign for want of jurisdiction on the basis on this first challenge.” (2) In relation to the late service of the Referral he said at paragraph 34: “It seems to me the only impact of the first copy of the Referral documents being lost in the post was that Halliwells were given an extra five days to prepare and serve the Response. My late receipt of the supporting documents caused no difficulties whatsoever and it cannot possibly have caused any prejudice to Halliwells.”
“The apportionment of my fees and expenses above does not alter the fact that, by virtue of clause 41A.6.2 of the adjudication provisions and paragraph 6 of my Terms of Engagement, the parties are jointly and severally liable for my fees and expenses. In the event of default by Halliwells I reserve the right to invoice the entire amount to ISG.”
“You will recall that throughout the Adjudication our position was that you did not have jurisdiction. That remains our position. Accordingly, we will not be making any payment in respect of your invoice.”
“The adjudication was commenced by ISG. The appointment was made at ISG’s request. At no time during the adjudication did we agree to your appointment, and we most certainly did not agree to be liable to pay you for anything you did in the adjudication. Any appointment as adjudicator (as you recognise in your terms and conditions) is contractual and we never had a contract with you. Again, we can only suggest that you request payment from ISG.”
“All that is required to found such a remedy is a request by one party that the other party shall perform a service, in circumstances where it is contemplated that the service will be rewarded. The request here is present in fact, in the express terms of the appointment so that there is no need for a request to be implied; and the right to remuneration is taken for granted, and indeed is not infrequently quantified by agreement before any services are performed.”
“Even when the parties have not made any specific provision for the arbitrator to be paid, an arbitrator appointed to decide a commercial dispute has a right to be paid a reasonable fee.”
“There may, however, be circumstances in which the arbitrator has a restitutory claim, based on the fact that the useless work was carried out at the request of the parties or one of them, where the arbitrator was appointed by one party.”
“The parties are jointly liable for the fees of the arbitrator and where the tribunal consists of more than one arbitrator, each party is liable for the fees of the whole tribunal, and not merely those of the arbitrator whom he has himself appointed.”
“By accepting appointment in this case the arbitrators by implication undertook to conduct the arbitration with due diligence and at a reasonable fee.”
“3. The scheme apparently implicitly confers on the adjudicator a power to apportion his fees and to decide who should pay the apportionment. The adjudicator has done so on the basis of all the work that he carried out. However in the light of my decision it is clear some of that work was unauthorised as it was beyond his jurisdiction and accordingly the defendant cannot be liable for it. Only the party that sought adjudication is liable for the fees, expenses and costs incurred by asking for a decision which the adjudicator had no authority to make and to which it was not entitled under the contract and which in breach of contract it sought. Section 114(4) of the 1996 Act provides: 'Where any provisions of the Scheme for Construction Contracts apply by virtue of this Part in default of contractual provision agreed by the parties, they have effect as implied terms of the contract concerned.' Thus the scheme took effect as implied terms of the sub-contract. The claimants were only entitled to exercise their right to call for adjudication if they first complied with para 1(3) of the scheme. They did not do so in part and were thus in breach of contract.”
“we invite the Adjudicator to revise the directions given in his letter of5 June 2008 …”
“If an Adjudicator is agreed or appointed within 7 days of the notice then the Party giving the notice shall refer the dispute or difference to the Adjudicator (the “referral”) within 7 days of the notice…. The said Party shall include with that referral particulars of the dispute or difference together with a summary of the contentions on which he relies, a statement of the relief or remedy which is sought and any material he wishes the Adjudicator to consider. The referral and its accompanying documentation shall be copied simultaneously to the other Party.”
“My initial reaction to this point was to consider that, in the overall scheme of things, it might be difficult to say that the delay of one day in the provision of the referral notice should be accorded great significance, and that it would be harsh to rule that the whole adjudication was a nullity because of that one day's delay. But, on a more detailed analysis, I do not consider this reaction to be so easy to justify.”
“Does that finding mean that the referral notice was not served in accordance with its provisions and is therefore a nullity?”
“In my view, cl 41A.5.6 is concerned with procedural relief. It cannot confer jurisdiction on an adjudicator who does not have any jurisdiction in the first place. An adjudicator, in order to have the power to make directions, must be in receipt of a valid referral notice. If that has not happened, then cl 41A.5.6 cannot rescue the situation. Take as an example an adjudicator who is appointed in a situation where there is then no referral notice for three months. In such circumstances the responding party is entitled to say, if and when the belated referral notice turns up, that the adjudicator has no power to make any directions at all. Under cl 41A the referral notice would be a nullity. It would make a nonsense of the whole adjudication process if the referring party could then rely on cl 41A.5.6 to argue that the much delayed referral notice had not invalidated the decision of the adjudicator.”
“In my judgment, where there is a contractual agreement to adjudicate, as here, that adjudication process is not undermined, jurisdictionally or otherwise, by the fact (if it be the case) that the terms of the original contract (containing the adjudication clause) were orally varied. There could only be such undermining if it was an express term of the contract itself to the effect that oral variations of the terms were not to be considered valid unless recorded or evidenced in writing. Essentially the parties will have agreed in a binding contract that disputes will be referable to adjudication. If there is some oral variation to the terms of that contract, that does not itself undermine the contractual enforceability of the adjudication process. If the original agreement is binding and whether or not the oral variation is binding, there still remains a binding adjudication agreement of which either or both parties may make use from time to time.”
“1. A decision from the Adjudicator that Halliwells shall pay to ISG the sum of…£450,179.51 …”
“3.6 Part of the sum claimed by ISG is£12,830.58 which ISG asserts is unpaid from the principal amount awarded by the previous adjudicator. Halliwells submit that the amount is not due because of an agreement reached with ISG whereby ISG would not seek to enforce the Adjudicator’s decision if payment of£450,000.00 plus VAT was made 3.7 In any event, Halliwells submit that the previous Adjudicator’s decision could only be enforced by the Court.”
“I accept and agree with Halliwells’ assertion that I cannot order payment of the£12,830.58 . It has already been decided by Adjudication that this amount (and£450,000.00 already paid) was to be paid by Halliwells to ISG. As Halliwells say, an Adjudicator’s decision can only be enforced by the Court.”
“what the defendant could not do was to assert that the decision was a decision for the purposes of being the subject of a reference to arbitration but was not a decision for the purposes of being binding and enforceable pending any revision by the arbitrator. In so holding, I am doing no more than applying the doctrine of approbation and reprobation or election. A person cannot blow hot and cold - see Lissenden v. CAV Bosch Limited[1940] AC 412 , and Halsbury's Laws, Fourth Edition, Volume 16, paragraphs 957 and 958. Once the defendant elected to treat the decision as one capable of being referred to arbitration, he was bound also to treat it as a decision which was binding and enforceable unless revised by the arbitrator.”