“Mayhaven’s primary case is that DAB’s wrongful suspension of work on20 July 2006 , which was accompanied by a complete clearance of and withdrawal from site, amounted to repudiatory breach. Alternatively, Mayhaven submits that DAB’s entire conduct and breaches of contract up until20 July 2006 , including wrongful suspension, amounted to a repudiation of the contract”
“Both parties point out that breaches of contract are repudiatory if they go to the root of the contract”
“I would only add that it would be a regrettable development of the law of contract to hold that a party who bona fide relies upon an express stipulation in a contract in order to rescind or terminate a contract should, by that fact alone, be treated as having repudiated his contractual obligations if he turns out to be mistaken as to his rights. Repudiation is a drastic conclusion which should only be held to arise in clear cases of a refusal, in a matter going to the root of the contract, to perform contractual obligations. To uphold the respondents’ contentions in this case would represent an undesirable extension of the doctrine. ”
“DAB issued a Notice of Intention to Suspend on 12 July and suspended work on20 July 2006 . This suspension was not valid under Clause 4.4.2 as set out previously. Mayhaven on20 July 2006 , knowing DAB had received the money that they claimed, wrote to DAB’s solicitors, bringing the contract to an end on the ground of wrongful suspension. The Contract Administrator, also was aware that DAB had received the monies claimed and failed to inform DAB DAB had expressed a willingness to complete the work in their suspension letter dated20 July 2006 I have considered the matters raised by Mayhaven relating to DAB’s suspension being a repudiatory breach and the additional justification set out in paragraph 115A and I find that at20 July 2006 DAB’s action was not a repudiatory breach.”
“…there is no magic in the words “fundamental breach”; this expression is no more than a convenient shorthand expression for saying that a particular breach or breaches of contract by one party is or are such as to go to the root of the contract which entitles the other party to treat such breach or breaches as a repudiation of the whole contract. Whether such breach or breaches do constitute a fundamental breach depends on the construction of the contract and on all the facts and circumstances of the case.”
“Refusal or Abandonment. An absolute refusal to carry out the work or an abandonment of the work before it is substantially completed, without any lawful excuse, is a repudiation.”
“Short of such an express refusal or declaration, however the test is to ascertain whether the action or actions of the party in default are such to lead a reasonable person to conclude that he no longer intends to be bound by its provisions. The renunciation is then evidenced by conduct. Also the party in default “… may intend to fulfil (the contract) but may be determined to do so only in a manner substantially inconsistent with his obligations” or may refuse to perform the contract unless the other party complies with certain conditions not required by its terms. In such a case, there is little difficulty in holding that the contract has been renounced. Nevertheless not every intimation of an intention not to perform or of an inability to perform some part of a contract will amount to a renunciation.”
“Our client will not return to site until it has been paid the balance of Valuation Number 9 as confirmed by the Adjudicator’s decision dated12 June 2006 . Our Client, however, remains willing and able to return to site and confirms to us that it has approximately two weeks worth of work left on site to do to complete the contract”
“In this case, Mayhaven are developing a business plan, moving into the provision of care for YPD; in my opinion, this is not a special contract referred to in Victoria Laundry, nor are the circumstances similar to those in the Czarnikov case which related to a cargo of sugar. The circumstances relating to this case are a change in the provision of care to produce a significant increase in profit, to which Mayhaven were privy, and I find it is most unlikely that DAB could have discovered this possible change in Mayhaven’s business plan.”
“The crucial question is whether, on the information available to the defendant when the contract was made, he should, or the reasonable man in his position would, have realised that such loss was sufficiently likely to result from the breach of contract to make it proper to hold that the loss flowed naturally from the breach or that loss of that kind should have been within his contemplation.”
“Referring to the words of Lord Reid in Czarnikow Ltd v Koufos as set out above, I do not consider that at the time when the contract was made, sufficient information was available to DAB, or a reasonable man in the same position to have realised “that such a loss was sufficiently likely to result from the breach…” or a loss of that kind should have been within his contemplation.”
“Doing the best I can with the evidence received I consider and find that Mayhaven could have commenced the Phase 2 after a twelve month period following completion of Phase 1.”
“I find, based on the evidence placed before me that, the loss of profit relating to Phase 2 has not been established.”
“Mayhaven have expressed an intention as dealt with earlier, however, no tender/contract documents were adduced in evidence, which, in my opinion could have been expected if Mayhaven had intended to proceed as quickly as stated: the absence of this evidence highlights the fact that the true extent of the defects was not known at the time of contract termination.”
“It seems to me most unlikely that the parties to the contract contemplated that the builder should be excused for faulty work at an early stage merely because the architect failed to carry out some examination which would have disclosed the defect. … For my part, to reach that result I should want to find quite clear words in clause 24(f) relieving the builder of liability. … I cannot see why he should be allowed to escape from the ordinary consequences of his negligence when discovered years later, a consequence which would undoubtedly flow if the building owner had not appointed an architect for his, the building owner’s protection.”