“It follows that this is a case where there is no reason for the failure to serve other than the incompetence of the claimant’s legal representatives.”
“We are in no doubt that the applications for an extension of time for service of the claim form should have been allowed if they had been made on 15 August and10 December 2003 . The claimant had a good reason for not serving the claim form within the period prescribed by rule 7.5(2) and for requiring a further few weeks thereafter. The claimant's solicitors behaved sensibly and responsibly in not serving proceedings when they did not know whether the claimant had a claim which had real prospects ofsuccess against any, and if so which, of the three defendants. They could not responsibly proceed against any of the defendants without the support of an expert, and the reason why they needed the extension of time was that they were awaiting the expert's report. The report was delayed because the first defendant himself had not responded to proper requests for his clinical notes. The situation was quite different from that which often arises where the claimant seeks an extension of time for service of the claim form because he or she wants further time to prepare a schedule of loss. In the present case, the outstanding information went to the very heart of the claimant's case. Without the expert's report, she did not know whether she had a viable case. In these circumstances, we think that both extensions of time should have been granted. We do not find it at all surprising that those representing the second and third defendants in the present case understood that the claimant was seeking an extension of time for service of the claim form, and did not object to it.”
“… the apparent justification advanced on behalf of the claimant, namely that his solicitors were awaiting receipt of the accountant’s report, is not a reason for delaying service of the claim form. In the first place, if that point could justify any extension of time, it would be an extension for the service of the particulars of claim, not the service of the claim form … Quite apart from this, although the accountant’s report may have been received later than the claimant’s solicitors had hoped, it was received more than a month before the time for the service of the claim form expired. Further, the particulars of claim had actually been drafted by counsel some two weeks before the expiry of the 4 months period for service of the claim form. Accordingly, the matters relied on by the claimant as a reason for not serving the claim form in time would not, in our view, even have justified an extension of time for service of the particulars of claim.”
“Without an assessment of the cost of the remedial works and the losses that will be caused to the Claimant’s business, it will not be possible to produce particulars of claim that will promote settlement of the claim. As the court will have seen, it seems likely that liability will not be disputed and that the only issue will be as to the proper assessment of the Claimant’s loss. I decided that serving particulars of claim without the requisite figures would be to risk incurring litigation costs unnecessarily.”
“The reason given by Mr Paterson was stated in Leeson’s case to be “no reason at all” for not serving the claim form. It is true that it is possible to think of more egregious examples of failure to serve. Mr Patterson did not overlook the need to serve within the 4 months period. He stated in terms in his witness statement that, if the application to extend time was dismissed, he would serve the claim form before the end of the 4 months’ period. He took the trouble and incurred the expense on behalf of his client making an application without notice to extend time. But in out view, he made a serious error of judgment.”
“…the Claimants require additional time in which to obtain the information necessary to properly particularise the claim.”
“The Claimants were at the time convinced that the grounds on which they based the application provided sufficient justification for an extension of time and they remain so convinced. The Claimants were aware of the nature of the defects that had materialised at the laboratory and believed that these had been caused or alternatively contributed to by errors in the design of the works. As the Defendants had acted as engineers with a design responsibility, it was probable that they had some liability for the deficiencies in the design of the structure that have caused the current water ingress problem.” (2) At paragraph 16: “At the time for service of both Claim Forms approached, the Claimants’ expert had still not seen the necessary project documentation and designs (on account of the behaviour of the Defendants) and, although he had undertaken an inspection of the building and prepared an initial report, he had advised that extensive subterranean excavations and further documents would be required to specify the nature of the problem and liability for the breaches. In the circumstances it would not have been sensible for the Claimants to proceed to serve the First Claim Form on the Defendants, without knowing the particulars of the design breaches levelled against the Defendants by the expert. At the time it appeared as though a considerable period would be required for arranging the subterranean excavation of this working laboratory, performing those works, preparing a written report and for a discussion of the findings between the expert and the Claimants’ legal representatives.” (3) At paragraph 18: “By way of an update on the progress of the Claimants’ expert, the expert has now undertaken an invasive investigation of the condition of the water-resisting membrane system installed to the junction of the reinforced concrete basement walls and cavity wall construction. That investigation confirmed shallow excavation adjacent to the building in three areas to expose the top of the concrete wall and the water-resisting membrane, together with the removal of a number of courses of brickwork from the outer leaf of the cavity wall construction. This enabled the observation of the quality of the installation of the membrane across the basement wall and the inner leaf of the cavity wall up to the damp-proof course installed above ground level. A consolidated report has been prepared, but the expert has now been instructed to consider the documents recently provided by the Defendants to evaluate whether they have any impact upon his opinions. The expert expects to be in a position to respond during the course of next week.”