“the fees were to be paid in equal monthly tranches over that period” (Paragraph 22). He went on to say: “If one of the consequences of that might, in the event, mean that all the fees were paid long before the work was completed, then so be it”
“1. The [Stern Trustees are] to identify any issues as to quantum by12th October 2007 . 2. [Mr Levy] is to respond to the Respondent’s case on quantum by26th October 2007 . 3. The Arbitrator is to decide any dispute on a documents-only basis (unless otherwise ordered) with a view to issuing an Award on quantum by14th December 2007 …”
“4. The submissions filed on both sides are voluminous and detailed, and refer me to a number of cases, but in the end both sides admitted that there is no case law directly in point, and I must, therefore, apply simple logic to the issues involved. What I must remember here is that in October 2004 the contract between Mr Levy and Mr Stern was, as I have already decided, wrongly terminated by Mr Stern. That gave rise immediately to the right for Mr Levy to claim damages for breach of contract, and that right of action accrued at that point. That claim for damages consisted of two elements, the first being a claim in respect of outstanding fees for work already done under the Contract, and the second being a claim for general damages in respect of the breach of contract, and at all material times the claim was pleaded and conducted on that basis. In my view both of those parts of the claim crystallised at the point of breach, and events, such as the agreeing of a later final account with the builder, could not affect the quantification of those rights. It is true that had the Contract continued to full term, and there had been a final account to which Mr Levy was a party, then under the terms of the Contract there might have been an adjustment of some sort to Mr Levy’s final entitlement. But, in the nature of the events which happened, that end result could never take effect, and Mr Levy ceased to be a party to the transaction at the point when his Contract was terminated. I am therefore firmly of the view that the quantification of damages in respect of outstanding fees can only be based on the evidence which was adduced at the original hearing as interpreted by me in my Award No. 1. It follows, therefore, that the outstanding quantum in respect of unpaid fees must be based on the Scott Schedule as amended during the course of the hearing and subject to my deletions of the claim in respect of the cobbles. 5. It should be possible now for the parties to agree those figures without further guidance from me, but, if necessary, I will consider any applications. That then leaves the question of general damages. The Claimant, in Paragraph 10 of the letter of 28 August, 2008, submits that the only evidence which I have heard on this question was the evidence presented at the hearing by Mr Jonathan Russell, a forensic accountant, and the Respondent called no evidence to contradict that evidence, so that, in default of agreement, I ought to base my assessment of quantum on that evidence. If the parties are not able to agree a figure within 28 days of the delivery of this Award, then I will permit the Respondent to make further submissions on the issue of quantum within 28 days thereafter, but, subject to further applications, I am not minded to have an oral hearing on the point.”
“I therefore award, declare and direct as follows:- 1. Leave for the Respondent to adduce further evidence on quantum is refused. 2. Leave to amend the Defence is refused. 3. Liberty to apply. 4. Costs are reserved.”
“(a) The identification of a true question of law, as opposed to complaint about the Arbitrator’s findings of fact masquerading as a point of law; (b) that the Arbitrator was obviously wrong on the relevant point of law or, if it is a point of general or public importance, that the Arbitrator’s decision was at least open to serious doubt; (c) that the point of law substantially affects the rights of the parties in the arbitration (see The Northern Pioneer[2003] 1 Lloyd’s Rep 212 ); (d) that it is just and proper for the court to determine the point of law (see Kershaw Mechanical Services Ltd v Kendrick Construction Ltd[2006] EWHC 727 (TCC) ).”
“(1) A party to arbitral proceedings may … apply to the court challenging an award in the proceedings on the ground of serious irregularity affecting the tribunal, the proceedings or the award. … (2) Serious irregularity means an irregularity of one or more of the following kinds which the court considers has caused or will cause substantial injustice to the applicant – (a) failure by the tribunal to comply with section 33 (general duty of tribunal) …” (a) failure by the tribunal to comply with section 33 (general duty of tribunal) …”
“(a) act fairly and impartially as between the parties, giving each party a reasonable opportunity of putting his case and dealing with that of his opponent …”
“Both of those parts of the claim crystallised at the point of breach, and events, such as the agreeing of a later final account with the builder, could not affect the quantification of those rights.”
“… the quantification of damages in respect of outstanding fees can only be based on the evidence which was adduced at the original hearing as interpreted by me in my Award No. 1.”