‘15. … The parties shall not commence any action or proceeding other than adjudication arising out of or in connection with this Sub-Contract until such time as the Main Contract Works have been certified substantially or practically complete.’
‘22.1. What does clause 15 mean by the Main Contract Works? 22.2. What does clause 15 require by way of certification?’
“The supply of all Labour, Tools and Equipment, Vehicles, Fuel, Plant and Materials … as required to facilitate the installation/alteration of new/existing service/main laying works, including reinstatement, at various locations in the Lincoln area It is common ground that the sub-contract was extended to cover a greater geographical area than Lincoln. on our First Connect Connections Engineering Period Contract (The Main Contract) under our Enterprise Utility Services Ltd Standard Form of Sub-Contract.”
“Works means all or any of the Projects … to be performed by the Contractor under any Contract Order issued under this Contract”
“Contract Order means the written signed instruction given by the Manager to the Contractor to perform the Works specified in that Contract Order”
“Manager means the person nominated by the Employer to act as its representative in relation to the management and performance of the Works of this Contract”
“Project is a specific task issued under a Contract Order”
“Project Completion Certificate is a certificate authorised by the Manager which shall identify that all the Works comprising a Project and all the Work Documents have been completed”
“Project Completion Date is the date when the Project Completion Certificate is authorised by the Manager”
“Work Documents means those documents that the Manager deems necessary for the Contractor to complete or provide an to show that the Works have been performed in accordance with this Contract”
“Track Sheet records: (i) the Value of Works Performed on Site; (ii) the Contract Management Costs; (iii) the Material and Design Costs; (iv) any other allowable cost”
“Contract Commencement Date means the date upon which this contract comes into operation as set out in the Contract Data”
“Given my knowledge of this contract and the nature of the works and following a review of [the defendant’s] database, I can confirm that all Projects carried out in or around December 2005 and/or March 2006 (or any time before that) were completed, Project Completion Certificates were sent to [the employer] and payment was made by [the employer] evidencing [the employer’s] authorisation of completion.”
“26. The Main Contract does not prescribe a format for the Project Completion Certificate. Enterprise submitted various types of documents at different times to signify completion of Projects. 27. When appropriate, Enterprise submitted a Summary Sheet setting out details of the Project, a completion date and details of the documentation provided. The precise format of this Summary Sheet varied throughout the periods referred to above but a sample template is attached as Appendix 4. 28. The attached Summary Sheet sets out the other types of documents that work, depending on the nature of the job, submitted. A Track Sheet was always submitted along with a Job Card. Various other documents were sometimes necessary including Test Certificates and As-Laid Plans. 29. Of the documents sent to Fulcrum to signify completion of a Project, Enterprise only kept copies of the Track Sheets. 30. … By way of example, I attach a Track Sheet relating to 47a Kenilworth Drive, Oadby, Leicestershire dated23 December 2005 which was submitted to Fulcrum following completion of that Project (Appendix 5). 31. Fulcrum’s authorisation that the above Project was completed was signified by its payment in respect of that Project on1 February 2006 (the ‘WR Number’ on the Remittance Sheet matches the ‘QS No’ on the Track Sheet. Details of payments received have been removed for reasons of commercial sensitivity) (Appendix 6). … 34. [Set out in paragraph 35 above] … 36. I attach a letter received from Philip Jenkins of Fulcrum on11 January 2008 (Appendix 9) which supports my understanding regarding completion, as set out above. Most importantly, he confirms in the second paragraph that “Relevant Fulcrum officers check the completed documents and if satisfied authorise payment of the claimed charges … authorisation of the Enterprise Track-sheet signifies that Fulcrum has accepted the individual project is complete and certifies this as such for all practicable purposes”
“… Individual project instructions are contained within a project pack, which would include job cards for individual elements of the project. Individual projects are considered to be completed and certified as such when all works are satisfactorily completed and all relevant project pack documents are correctly completed and returned to Fulcrum. Returned project packs would also be accompanied by a project track-sheet that details the actual works and quantities, completed for each project. Relevant Fulcrum Officers check the completed documents and if satisfied authorise payment of the claimed charges within the Enterprise track-sheet. Although there isn't a specific completion certificate, authorisation of the Enterprise Track-sheet signifies that Fulcrum has accepted the individual project is complete and certifies this as such for all practicable purposes.”