“Before I turn to the facts it is important to consider briefly the approach to be adopted to the issue of contract formation in this case. It seems to me that four matters are of importance. The first is the fact that English law generally adopts an objective theory of contract formation. That means that in practice our law generally ignores the subjective expectations and the unexpressed mental reservations of the parties. Instead the governing criterion is the reasonable expectations of honest men. And in the present case that means that the yardstick is the reasonable expectations of sensible businessmen. Secondly, it is true that the coincidence of offer and acceptance will in the vast majority of cases represent the mechanism of contract formation. It is so in the case of a contract alleged to be made by an exchange of correspondence. But it is not necessarily so in the case of a contract alleged to have come into existence during and as a result of performance. See Brogden v Metropolitan Railway(1877) 2 AC 666 ; New ZealandShipping Co Ltd v A.M. Satterthwaite & Co Ltd[1974] 1 Lloyd’s Rep 534 at p.539, Col 1;[1975] AC 154 at p.167 D-E; Gibson vManchester City Council[1979] 1 WLR 294 . The third matter is the impact of the fact that the transaction is executed rather executory. It is a consideration of the first importance on a number of levels. See British Bank for Foreign Trade Ltd v Novinex[1949] 1 KB 628 . at p 630. The fact that the transaction was performed on both sides will often make it unrealistic to argue that there was no intention to enter into legal relations. It will often make it difficult to submit that the contract is void for vagueness or uncertainty. Specifically, the fact that the transaction is executed makes it easier to imply a term resolving any uncertainty, or, alternatively, it may make it possible to treat a matter not finalised in negotiations as an inessential. In this case fully executed transactions are under consideration. Clearly, similar considerations may sometimes be relevant in partly executed transactions. Fourthly, if a contract only comes into existence during and as a result of performance of the transaction it will frequently be possible to hold that the contract impliedly and retrospectively covers pre-contractual performance. See Trollope& Colls Ltd v Atomic Power Construction Ltd[1963] 1 WLR 333 .”
“645. The power to accept an offer may be terminated by any unambiguous intimation, expressed or implied, by the offeree to the offeror that he rejects the offer. This will generally remain true notwithstanding that the offer was stated to be open for a certain period as yet unexpired. A rejection cannot be effective as such unless and until communicated to the offeror; but, thereafter, the offer cannot be accepted unless subsequently revived by the offeror, or unless the original offer was intended to continue notwithstanding the rejection. An offer can only be rejected by a definite indication of intention to reject. … A counter-offer is often seen as having the effect of a rejection of the original offer.”
“The counter-offer kills the original offer”
“We should be pleased to receive from you a most competitive tender for the supply of all supervision, labour, plant and materials to carry out the Directional Drill works at our Burrows site, as detailed in the Scope attached. The tender should be based on fixed rates and be returned to the above address by no later than21st October 2005 at the earliest availability. The tender quotations MUST be valid for a minimum of 6 months from receipt. We are looking to mobilise week commencing 21st November 05. Please could you also provide a programme for works. The tender, if accepted will be carried out under the IChemE Form of Contract for Civil Engineering Works ‘The Brown Book’ Second Edition 2004 incorporating Completed Sub-Contract Schedules 1 to 15 and this will be incorporated in Vol. 1 of the Sub-Contract Order for the above works. The following documents have been enclosed: 1. Scope of Works …. 2. Drawings …. 3. Daywork Schedule …. 4. Schedule of Attendances …. 5. Fully Qualified Workforce Group Statement (on CD). 6. Fully Qualified Workforce Guidance (on CD). 7. Fully Qualified Workforce Conditions (on CD). 8. Gleeson …. ‘Engineering Division Health and Safety Policy’ (on CD). 9. Gleeson … Health and Safety Management System Procedures: All listed on enclosed CD ( inc Engineering Division Health and Safety Policy – Current at TODAY’s DATE)…. This Subcontract enquiry document and related information and specifications will be incorporated into Volume 2 of the Subcontract Order for the above works. The quotation received by Gleeson as well as the letter of appointment will be incorporated into Volume 3 of the Subcontract Order for the above works. … Please also note the following important details: … (9) The Sub-Contractor will at some time be required to attend a pre-contract subcontract meeting as confirmed by Gleeson … Gleeson … are not obliged to accept the lowest tender and the successful tenderer will be subject to South West Water approval and a Sub-Contract ‘Pre-Let’ interview with Gleeson ….”
“Please find attached our quotation for the installation by hdd at Dawlish. I have priced three scenarios ….. I have got concerns with the depth and ground conditions near the river, the borehole number 2 indicating gravel beds, and would propose to dig a ‘burp’ hole in here if possible to avoid the risk of any fluid break out under/into the river … We have not included waste removal as this is not a function of the ground conditions …”
“Re: Burrows-WTW-Directional Drill We thank you for your recent enquiry regarding the above and now have pleasure in submitting our ‘QUOTATION’ for the above directional drilling sub-contract works duly priced for your requirements, as per the attached schedule … Prior to entering into a formal contract, we will require a site visit.”
“… Yates … is pleased to submit this proposal to Gleeson … to provide ‘Horizontal Directional Drilling Solutions’ (HDD) in accordance with the attached “Terms and Conditions of Contract and Price Schedule”
“Please note the following: 1. This offer is subject to availability of resources at the time of placing the order … and to our confirmation of this offer in writing. 2. Work will normally be carried out in accordance with the Civil Engineering Contractors Association “Form of Sub-contract for use with the ICE Conditions of the contract” except that clauses 3(3), 3(4), 10(3), 11, 15(4) and 17(3) shall be deleted from the Form of subcontract or the “Engineering and the Construction subcontract – 2nd Edition”. 3. The conditions in this letter will form part of the contract documentation (second schedule of the Blue Form or Works information for the NEC/ECC) and in the event of any conflict between these conditions and any other documents (including the subcontract order or the form of subcontract) these conditions shall prevail. We will not undertake work under nonstandard forms of contract that do not contain clauses similar to Clauses 12 and 13 of the ICE Conditions of Contract or 60.1 of the NEC/ECC. … 6. Our offer is based only on the information provided. We are not deemed to have any knowledge of any other documents. 7. In the event that we exceed the agreed contract period for reasons that do not entitle us to an extension of our contract period we will pay Liquidated Damages to the main contractor of£500 /week to an overall maximum of 5% of our contract value. This figure is our total liability to the main contractor for delays or any other costs arising from our delay … 12. Unless agreed to the contrary in writing we do not accept any responsibility for any design of the works…. 19. We have not inspected the site and our knowledge of ground conditions is limited to any geotechnical information supplied to us. Our tender is based on the assumption that the ground is suitable for the directional drill specified …. 22. Our price is based on the use of our Horizontal Drilling M/c as shown on page 1 and the boreholes provide[d]. If rock is encountered we reserve the right to renegotiate the drilling rates to allow for increased drilling times and change of drilling bits, reamers etc. If installation with this machine is not practicable we will have no responsibility for the completion of the works by other methods or machines and will be reimbursed for abortive work in accordance with the enclosed schedule …”
“this date is the overall completion – looking to actually finish23rd December 2005 ”
“Sub-Contractor’s Offer: Date of Offer: 20/10/05 Price:£221,827.92 Discount Offered: 6% off drilling rate Quotation Expiry Date: 28 days … Amendments to Subcontract Offer: less 6% on drilling rate =£255 /m x 600 =£153,000 new total =£212,828.00 ”
“For Lateness in Completion The amount due from the Subcontractor for each complete week, or part thereof, of delay for which the Subcontractor is responsible in completion of the Construction of the Subcontract Plant (or any part of the Subcontract Plants so designated) in accordance with Schedule 9 shall be 2% to a maximum of 20% of the Sub-Contract price”
“The order number for the above job is SC34489. By having this number we are giving you the go ahead for the work and therefore you are now able to order the required materials. The Subcontract will follow as soon as possible hopefully by the end of this week. If you have any queries please do not hesitate to contact me”
“Thank you very much for the order. I have a couple of questions raised by my Director of Tunnelling following our meeting on Tuesday,1st Nov 2005 . As you can appreciate timescale is tight before Xmas, especially as pipe is coming from Germany. They are assuring me of delivery beginning week commencing12th December 2005 . If there is a delay on delivery then inevitably there would be a delay in installation and given the possibility of harsh winter conditions; Can you clarify your date Feb 10th is the completion date by works? And would the Liquidated Damages (Lateness in Completion) commence from this date?”
“Re: Burrows WTW … Subcontract Order No. SC34489 Please find enclosed [herewith] our Subcontract Agreement (Vol. 1), The Enquiry (Vol. 2) and Further Documents (Vol. 3) on the above project. Please complete the Subcontract Agreements where indicated and return both copies to this office within 7 days to ourselves to complete. Please note we are now operating a Self-Billing System. Could you please sign and return the enclosed form. If you have any queries regarding the above please do not hesitate to contact the writer”
“Subcontract Agreement – relating to – I Chem E Form of Contract, Subcontract ‘The Brown Book’ second edition 2004 incorporating Schedules 1 to 15 with South West Water Ltd Amendments – between - Gleeson…. -and- Yates .. Sub-Contract Order No. SC34489 (I Chem E Brown Book)”
“I have received contract documents, many thanks and will forward them to head office for approval. Two issues that were discussed in our meeting, waste removal and pressure testing. I am putting together prices for waste removal by tanker vs. on site flocculation and centrifuge systems and should have these ready shortly. In addition I am putting together price for pressure testing … I cannot find any mention of the testing as an additional item, nor the waste removal. Is the waste removal which is an additional item covered by the email I sent on20/10/2005 in Volume 3? Cost of tankering waste removal will be at costs + 10%. Are these two items described under the existing order or do you need to revise the document? I should have all other documentation with you by the end of next week.”
“CONTRACTOR’S INSTRUCTION Sub-Contract: SC 34489 Dear Sirs CI TITLE: SLURRY CONTROL/PRESSURE TESTING In accordance with the SubContract Please carry out the additional works to incorporate the slurry control/ pressure testing of the pipeline to the Burrows works as requested by our Mr. Davin Eversett and detailed upon your quotation dated11th November 2005 for the sum of£24,112.50 /£3,993.43 … (ii) Please notify us within 7 days if compliance of this Contractor’s Instruction will delay completion of the Sub-Contract Works.”
“Within our terms and conditions we require the main contractor to provide us with a suitable water supply point and require a 2½” stand pipe feed (the usual ¾” feed off a main is impractical and will take too long to fill a 2000 gallon bowser). Especially as we will require filling it up at least twice if not three times prior to drilling commencing. The Record of interview meeting states that potable water can be taken from the main treatment works. Can you confirm this?”
“As a result of postponement of the contract, AE Yates would require a sum of£3,000 per week to reserve the drilling rig for the contract, charge to commence on Monday,9th Jan 2006 until such time as we commence the project or the project is cancelled …”
“As you are aware we are experiencing a number of problems on the above directional drill, which are or have affected our works in a number of ways … The bore was advanced by the above method until it was approximately 300m away from the launch pit. During this period, unexpected ‘frac-outs’ of drilling mud to the surface occurred on a number of occasions. These breakouts were appearing up to 15m away and up hill … At 300m the ground became harder so that the head would not steer, but could be advanced by rotation of the drill head ... The probability of drilling mud break outs can be reduced by going deeper but this will take the bore profile beyond the parameters of walk over guidance, and necessitate the use of a wireline guidance system and tracking engineer, which obviously has cost implications as set out below. … Our extra over costs for using wire line and installing the sleeve are set out below …”
“Under the subcontract order number. SC 34489 you have given an undertaking to complete a directional drill of 600m of 300mm I/d ductile iron, within a five week programme period. The construction methods utilised in order to achieve this are your responsibility, bearing in mind the conditions you could have reasonably expected within the information provided at the time. We are not in a position to instruct to you with regard to your method of working, please therefore complete the directional drill of 600m of 300mm I/d ductile iron. If you have any claim for additional costs, you should provide full substantiation of those costs, along with a demonstration and substantiation of any difference between the conditions envisaged and those encountered. We will then be able to comment further …”
“From discussions with … Yates … personnel, and with reference to an email sent by Chris Brodie of [Yates] to [Gleeson] dated20/10/2005 and included within Vol. 3 of the Sub-Contract Agreement, it is understood that [Yates] considered that the ground conditions for the directional drill would comprise predominantly firm to hard clay with a variable granular content as described in the drillers logs”
“We refer to your letter of17th January 2007 including your interim claim submission and to our earlier reply of31st January 2007 . The basis of your claim is not made clear. If it is being made under Sub-clause 6.3 of the Subcontract, which appears to be your intention, it is a condition precedent to any entitlement that you have first complied with the notice provisions. Please, therefore, provide copies of any notices that you believe that you have given to us… Without prejudice to the position in respect to notices, we have reviewed your submission… Your claim is deficient in that it does not satisfy the requirements of the Subcontract, in particular Sub – Clause 6.3 (if that is the clause under which you are claiming entitlement) and Clause 18. Please reconsider your claim and, if you still believe that you have an entitlement, re-submit it in accordance with the requirements of the Subcontract.”
“…We are disappointed with your latest response received some four months later. [Yates] advised in numerous letters and emails, as the situation developed, that the technical difficulties experienced during the drilling and reaming at Dawlish were attributable to conditions which could not reasonably have been foreseen at the date of tender by an experienced contractor. Our letters dated 16 February and26 July 2006 formally advised notification in accordance with Brown Book Sub clauses 6.2 and 6.3. Due to the ongoing difficulties being encountered we reconfirm that the final paragraph of 6.2 and 6.3 (referring to Sub-clause 18.2) are still applicable…”
“This notification is given under subclause 6.2 and 6.3 of the brown book.”
“I do remember Davin (Eversett) making reference to terms and conditions. It is difficult to remember the exact wording used by me after so much time has passed, but I clearly remember saying that our terms and conditions had to be incorporated into contract document, specifically the ground conditions clause. This is because ground conditions are absolutely vital to the work we do, and this is the basis is the basis on which we always work. We always insist that the main contractor bears complete responsibility for unexpected or different ground conditions.”
“Davin may have made reference to the IChemE but I can’t remember him doing so. I know that I did not and could not have agreed to the contract being governed by an IChemE form. I have no authority to and would never do so.” (b) He said in evidence that it was at the end of the meeting that he talked about his “terms and conditions” being incorporated. He had not said that in his witness statement. (c) He said in evidence and did not mention in his statement that he had retained on his own files a copy of the Record of Interview. Although overnight after giving evidence he was unable to find it, this is something which I would have expected to have been mentioned before cross-examination at least. (d) He said in evidence (Day 1, at page 121 of the trnascript) that Mr. Morant filled out the first page and as he filled it he read it out: “Q. He [Mr. Morant] said, “Name of subcontractor, A E Yates; scope of work, directional drilling; form of subcontract, IChemE Brown Book” did he not? A. Yes. Q. You can remember that? A. I can remember going through and filling the form out. I can’t remember him specifically reading sentences out. Q. And in the form that you had, you filled in the same thing did you? A. I put in notes, yes. Q. So you would have filled in form of contract IChemE Brown Book? A. Yes.”
“(a) This Subcontract Agreement. (b) The Special Conditions (enclosed). (c) The General Conditions of Contract being Clauses 1-46 as set out in the I Chem E Form of Contract of Civil Engineering Subcontracts (the “Brown Book”), 2nd Edition, 2004. (d) The Subcontract Specification (e) The Schedules: Schedule 1: Description of the Sub-Contract Works Schedule 2: Documentation; Schedule 3: Responsibilities of Contractor… Schedule 9: Times of completion; Schedule 10: Liquidated damages for delay; Schedule 14: Terms of payment; Schedule 15: Main Contract particulars; For the purpose of identification, the contents of the Subcontract, including the number of pages in each part, are listed in the Annex to this Subcontract Agreement.”
“2. The Subcontract constitutes the entire agreement between the Contractor and the Subcontractor with respect to the performance of the Subcontract Works and supersedes all prior negotiations, representations or agreements thereto, whether written or oral, except to the extent that they are expressly incorporated in the Subcontract… 6. In case of conflict between any of the documents accompanying the Subcontract Agreement, the order of precedence shall be set out in Clause 2 of the General Conditions…”
“Documents Forming the Subcontract Agreement: • The terms and conditions of the I Chem E Form of Contract for Civil Engineering Works “The Brown Book”
“The Subcontract documents shall be construed as mutually explanatory of one another. In the event of conflict between any of the documents comprising the Subcontract, the order of precedence shall be as follows: (a) The Subcontract Agreement; (b) The Special Conditions; (c) The General Conditions of Contract; (d) The Subcontract Specification; (e) The Schedules.”