“Following our telephone conversation of24th May 2002 in connection with our fee submission for the design of the mechanical, electrical and public health services for the above project, I have attached a copy of section 5 of our fee proposal amended to reflect our discussion. This now confirms a lump sum fee of£15,000 for the design of the services and negotiations with the utilities. Post-tender supervision during the construction period to be reviewed at a later date is therefore currently excluded.”
“It was apparent from my review of the time records submitted by the design team on the job that far more time was being recorded against the project than had been anticipated by the proposal. I discussed the matter with Neal Day who had the day to day control of the project. He informed me the Claimant had been required to redesign a number of areas of the design and had been instructed to undertake additional work. Mr. Day informed me that he raised the issue of additional costs with Mr. Ingham and that Mr. Ingham indicated that a detailed additional claim should be passed to him for consideration. At that time no such details had been passed to Mr. Ingham. I had a meeting with both Neal Day and Mr. Ingham in our office. The meeting took place on16th April 2004 . I am satisfied that Mr. Ingham had arranged the meeting to obtain drawings that he considered overdue. I am satisfied that he complained of delay to both KT directly and through Mr. Day.”