“We have also spoken with Martin Hayes of Orchard Construction who is doing the renovation work in Higham House; Martin is keen for his company to be considered a contractor for the pool project, and will be contacting you in the near future. He is aware you will manage the project, and that the selection of the contractor is your responsibility.”
“Habitus issued a proposed specification for upgrading security to the groundsman’s accommodation and the stable block. Orchard to price and return to Habitus” and at point 5.02: “Habitus to draw up proposals for external works to the front and side of the coach house”
“Invoice Please also find our invoice for this month – we will send an updated statement of account as this is now several months behind. There are some separate items due for invoicing which I will send you in due course.”
“We should also like to complete the kitchen and library. Again, we would like to see detailed drawings, examples of finishes etc. We are meeting with our kitchen designer this week to confirm the equipment we are buying.”
“As you know, because of the long delays caused by the necessary details not being in place and the subsequent long delays in starting the pool construction, this has disrupted our projected programme and will inevitably cause further delays.”
“1.19 MH (Mr Hayes) tabled a proposed schedule of programme dates indicating a provisional completion in December 2004. PG (Mr Gallant) thought that this was unreasonable and requested that the programme be reviewed instantly to confirm an improved completion date. [Stephen Langer] SL/MH to liaise and produce a bar chart for completion of the pool building.”
“5. We would remind you once again that you have an obligation to your employer to make all reasonable efforts to progress the works.”
“PG (Mr Gallant) asked CB (Mr Basford) what SLA’s role in the project was. CB replied ‘It was the role as normally assigned to the ‘Architects’ under JCT contracts, namely provision of information for pricing and construction of the works by the contractor, the monitoring of progress and quality of same and agreement of a fair value for the works on behalf of the employer’. CB also stated that SLA undertook responsibility for the approval and design information from three specialist sub-contractors on the project, namely Penguin Pools, Structura and Spiral. PG stated that this was not his understanding of his agreement with SLA and that he expected ‘full project management’. PG stated that he had originally been given a budget figure of£600,000 for the works by SLA and he considered that it was the responsibility of SLA to provide him with a revised budget.”
“8. Programme assessment: OC stated they were still on programme to complete the works by 30 September.”
“Again, the house has changed considerably so it needs to be surveyed again.”
“Sorry for the delay with breakdowns. I have nearly completed the ‘Old House’ budget costing and works for completion. I have got about another two days’ work for the costs to date of the various elements, i.e. labour, materials etc. I put this on the back burner and never finished it so will start work on the remaining figures tomorrow …”
“Please find enclosed the breakdown of the final costs for the Old House in the format you requested. This now includes all the provisional figures for the cupboards/wardrobes from Quality Joinery (total cost£195,000.00 , the final costs for plumbing and heating installation, electrical costs including the boiler control panel, sanitary ware for the small cloakroom and the last of the decoration works. The first column denotes the original budget costs which excluded the above, the second column denotes work complete – this figure will be used in the monthly valuations. The third column denotes the new items which were either in progress or TBC on the original costings, and the fourth column shows the total of the new budget costs. The final column is the anticipated completion date subject to availability of materials and manufactured items on order.”
“We are very much aware of your attempts to accelerate the finishing period and some advance warning of some dates would be beneficial.”
“A discussion on design took place. An Indian ‘feature’ was to be incorporated. SLA was to produce a design for approval.”
“Spiral tread sample – client approved 70 psi texture to treads. SLA to confirm. All treads will be sealed.”
“We require Martin (Hayes) to be there on Friday and at all future meetings. If he is not there on Friday we will need to think about our on-going relationship with Orchard.”
“25. OC tabled a revised construction programme showing an end date extended from end of October to end of January 2005. OC advised that Structura would be complete by 20 September but that joinery would not be installed until end of October. OC would temporarily close off the windows until then. SLA/client requested a date for laying of floors, which is currently shown as TBA on the programme. Client asked that OC complete all builders work by 17 December.”
“26. Client stated that any additional preliminary costs associated with the new programme were to be contained in the existing budget (for the pool) of£1,083,000 .”
“If you are not satisfied with the finish I will endeavour to correct this to the best of my ability.”
“We write to confirm that as at 10.30 you informed us that you were unilaterally terminating our contract in respect of the works at Higham House without our agreement. This is a repudiatory breach of the contracts between us but we confirm our acceptance of your repudiation …”
“If I have not received the list by Monday,20 September 2004 , I will assume that any equipment on site has been paid for by me.”
“I will take action against you and Orchard if your non-payments of these agreements impedes in any way the completion of the works in Higham House.”
“I am writing to enquire why I have not been paid for my labour at Higham House for the weeks ending 17 and 24 September and also week ending1 October 2004 . As you have not informed me that I have been dismissed I have to assume that I am still employed by Orchard Construction. Please would you provide me with my outstanding wages by return of post to the site office at Higham House.”
“Our clients should provide a comprehensive statement first, which they have done. This sets out what they are owed, what this is for and what your client has already paid. The next step is for your client to identify clearly what items are in dispute and why.”
“(b) The defendant would explain to the first claimant, Mr Hayes, on site what he wanted done. The claimants would carry out the work and charge the defendant an amount calculated in the same way as the estimates save that actual rather than estimated labour and materials figures were used. On receipt of the invoice the defendant would review the invoice, inspect the work done, and having resolved any queries with the claimant would agree to pay the amount charged.”
“(iii) … the work would be carried out for a price to be charged by the claimants on the basis of costs actually incurred [by] the claimants plus a reasonable percentage for overhead and profit.”
“The cause for the dismissal is the refusal by you and Orchard to provide the support needed to continue the works, evidenced by the closure of supplier accounts, providing materials needed for construction and your refusal to pay wages and salaries to your employees yesterday. The dismissal also reflects the cumulative dissatisfaction with your performance, including incompetent management, wildly inaccurate financial budgeting or forecasting, refusal to work to project timetables, inability or refusal to produce accurate financial analyses of money spent, gross overcharging, low productivity, use of sub-standard materials, initiating and charging for work not approved or budgeted and the inability to establish a good working environment for your employees, sub-contractors and suppliers.”
“In spite of this dismissal I will look to you and Orchard to financially compensate me for poor work such as the cost of correcting the unacceptable quality of the limestone flooring laid on the ground floor of the Old House.”