“Direct loss and or expense claim 6.1 The contractor has submitted a claim in the sum of£294,158.83 . 6.2 The sum currently certified amounts to£40,541.59 . 6.3 Having considered the submissions by both Parties and particularly File 5 submitted by the Contractor, I consider the claims made to be extravagant and exaggerated. 6.4 I consider the claim made and the information compiled, down to the telephone bills, to be nothing other than an attempt to claim as much as possible on the proviso that they may achieve some success if not all their claim. 6.5 I do not dispute that some claim over and above the£40,541.59 may be due and I would grant the Contractor leave to pursue this claim via a further Adjudication if they so wish. 6.6 For the claim to be analysed in detail, I believe a 3rd Party Quantity Surveyor would need to be appointed to assist the Adjudicator. The tight timescales associated with Adjudication, even considering the extension of time granted to me, would, I believe require a dedicated adjudication to consider the claim within the prescribed time frame. 6.7 I am not prepared therefore, to grant any further monies relating to the Contractors loss and/or expense claim.” 6.1 The contractor has submitted a claim in the sum of£294,158.83 . 6.2 The sum currently certified amounts to£40,541.59 . 6.3 Having considered the submissions by both Parties and particularly File 5 submitted by the Contractor, I consider the claims made to be extravagant and exaggerated. 6.4 I consider the claim made and the information compiled, down to the telephone bills, to be nothing other than an attempt to claim as much as possible on the proviso that they may achieve some success if not all their claim. 6.5 I do not dispute that some claim over and above the£40,541.59 may be due and I would grant the Contractor leave to pursue this claim via a further Adjudication if they so wish. 6.6 For the claim to be analysed in detail, I believe a 3rd Party Quantity Surveyor would need to be appointed to assist the Adjudicator. The tight timescales associated with Adjudication, even considering the extension of time granted to me, would, I believe require a dedicated adjudication to consider the claim within the prescribed time frame. 6.7 I am not prepared therefore, to grant any further monies relating to the Contractors loss and/or expense claim.”
“The sum due from BCC to Paddison … includes ... (c) the amount of direct loss and/or expense incurred by Paddison as a result of delay and disruption to the regular progress of the Works amounts to£294,158.83 .”
“Where the only difference between disputes arising from the rejection of two successive applications for an extension of time is that the later application makes good shortcomings of the earlier application, an adjudicator will usually have little difficulty in deciding that the two disputes are substantially the same.”