“(1) Within 10 days, or such other period as may be agreed in writing, of receipt of the Contractor’s written instructions so to do, the Sub-Contractor shall enter upon the Site and commence the execution of the Sub-Contract Works and shall thereafter proceed with the same with due diligence and without any delay, except such as may be expressly sanctioned or ordered by the Contractor or be wholly beyond the control of the Sub-Contractor. Subject to the provisions of this clause, the Sub-Contractor shall complete the Sub-Contract Works within the Period for Completion specified in the Third Schedule hereto. (2) If the Sub-Contractor shall be delayed in the execution of the Sub-Contract Works: (a) by any circumstances or occurrence (other than a breach of this Sub-Contract by the Sub-Contractor) entitling the Contractor to an extension of his time for completion of the Main Works under the Main Contract; or (b) by the ordering of any variation of the Sub-Contract Works to which paragraph (a) of this sub-clause does not apply; or (c) by any breach of this Sub-Contract by the Contractor; then in any such event the Sub-Contractor shall be entitled to such extension of the Period for Completion as may in all the circumstances be fair and reasonable. …”
“13.150 Delay and disruption …£300,000.00 ”
“Pursuant to Clause 6 of our Sub-Contract we request an extension of time of 26 weeks, to extend the Contract Completion Date to14 September 2007 . This date relates to when the additional, varied works that are instructed by [Jackson] were completed. The extension of time is justified by, but not limited to, the reasons listed on the attached Delay document.”
“The purpose of this document is to describe the delays to the Contract between VGC … and Jackson … on the M3 NRTS Project.”
“… for [Jackson] and [VGC] to establish why the measurement items listed in [Jackson’s] letter … date 10 October Notice of intention to withhold payment, were in dispute. [Jackson] were also to explain how their contra-charges listed in the above referenced letter were derived.”
“[Mr Exton] stated that VGC’s claim for an extension of time and [Jackson’s] over-run would be left in abeyance. [VGC] would like to agree the measurement items prior to their inclusion in the Final Account. VGC are currently preparing the Final Account. The Final Account will be submitted mid-January 2008 when the agreement to the measurement items has been reached. VGC will attempt to finalise the extension of time claim by the end of January 2008. [Jackson] confirmed agreement to the Final Account being submitted in January 2008 …”
“At the conclusion of the meeting on7 December 2007 it was agreed and as is recorded at Item 6 on page 9 of the minutes that VGC would now submit its final account in mid-January 2008 and its ‘delay and disruption/extension of time’ claim by the end of January 2008. I understood this to mean that in the interim VGC was not pressing its ‘delay and disruption/extension of time’ claim because it was finalising it. In the meantime, that claim and JCE’s contra charge claim would continue to be held in abeyance…It was not my decision to leave the claims in abeyance. VGC said they would be finalising the claims by the end of January …”
“At paragraph 11 of his statement, Mr Brydon [of VGC] states that ‘Mr Exton suggests that he understood that the Claimant was not pressing its claim for disruption and extension of time because it had agreed that it would attempt to provide further details of the claim by the end of January 2008’. I maintain that this was in fact the position as is clearly recorded in the minutes…Whilst the minutes record that I stated that the ‘delay and disruption/extension of time’ claim and JCE’s contra charges claim would be held in abeyance I wish to make it clear that this was the product of mutual agreement. This statement followed discussions wherein it was acknowledged that VGC was still not in a position to submit a formulated ‘delay and disruption/extension of time’ claim. Previously and during the meeting of7 November 2007 Mr Mauldon [of VGC] had advised that this would take six months to prepare. However, at the meeting of7 December 2007 he advised that this would now be submitted by the end of January 2008. It follows as a matter of common sense that until the claim is properly formulated and submitted it would be held in ‘abeyance’.”
“Delay, disruption and Prelims over-run: there are several items in relation to this. As these will be subject to a separate submission, we have removed them from our attached summary.”
“… Mr Butler advised that in his view adjudication was the only means of resolving the whole dispute particularly since the parties remained so far apart. I cautioned Mr Butler against taking this step because it was my view that most of the disputed items were capable of resolution without resort to adjudication. Adjudication would not have been appropriate in relation to the ‘delay and disruption/extension of time’ claim because it had still not been tabled and there was nothing to adjudicate on. I explained to Mr Butler that I could not undertake any assessment because the claim had yet to be formulated. I reminded him that the finalised claim was still outstanding. We could only consider the claim once it had been finalised.”
“10. The parties have been, over a considerable period, negotiating the final account for the works. The basis of this has been application number 14 submitted by VGC. 11. During negotiations, the parties held several meetings to attempt to agree the value of the Final Account. These were unsuccessful. 12. VGC have prepared a Scott Schedule which they believe reflects the position of the parties at the date of the adjudication. 13. The gross value of works valued by VGC is£4,287,302.08 , against which Jackson have valued£3,623,796.94 . 14. Since Practical [Completion] has been reached, retention should be applied at 2.5% of the subcontract value. 15. Jackson are applying set-off charges to the value of£656,400 . VGC dispute these charges. 16. To date Jackson have paid a net sum of£3,040,482.35 .”
“Disputes or differences have arisen between the Parties under a Contract dated: on or around9 November 2006 …. These disputes or differences have been referred to adjudication in accordance with The Institution of Civil Engineers’ Adjudication Procedure (1997) … and the Adjudicator has been requested to act.”
“Extension of time: Appendix 29.”
“1. It is apparent from the attached analysis [the Programme sent on30 April 2008 ] that, as a result of numerous delays and additional works during the currency of the Sub-Contract Period, as defined in the Sub-Contract, together with additional works instructed after the Sub-Contract Period passed, that VGC suffered delays and consequently loss due to no fault of their own.”
“… a meeting was arranged for4 April 2008 , where again it was apparent that VGC, notwithstanding the comments made by Jackson Civil Engineering at previous meetings, had still not provided proper supporting details of their claim and there remained a substantial amount of work required before a meaningful assessment of VGC’s account could be undertaken. Clearly, this still remains the case, yet VGC have now launched a further adjudication to try and resolve its account without the substantive information usually required to back up any application for payment. Given the length of time that Jackson Civil Engineering have been requesting proper backup of the sums claimed, the only conclusion must be that such information does not exist. Without the proper proof, there can be no entitlement.”
“15. It should be noted, that within Application No 13 VGC submitted a claim for delay and disruption in the sum of£300,000.00 … with no substantiation or prior notification. Formal notification of ‘a claim’ for an extension of time was issued under cover of VGC letter dated25th October 2007 with only a ‘table of contents’. There was no supportive information, justification or financial information appended … During the meeting held with VGC on7 November 2007 , Jackson Civil Engineering requested when the basis for and the justification of the claim for delay and disruption/extension of time would be submitted and were informed that it would take them approximately 6 months to complete. Six months have passed and to date the 1½ page statement in the Referral remains the sole basis of their submission with no financial information at all. Clearly, on any view, this is insufficient for Jackson … to assess its validity, and the Adjudicator should evaluate this claim as nil. The inclusion in Application No 13 by VGC of an, on paper, substantial claim for delay and disruption (and/or extension of time as requested under VGC letter dated25 October 2007 )…when it is not supported by any substantiation or justifiable reasoning as to its validity cannot and does not show that Jackson … were in breach of their rights under the sub-contract to dispute this item.”
“For the reasons set out in paragraph 15 above, this claim lacks sufficient detail and substantiation for either Jackson Civil Engineering or the Adjudicator to assess its validity. Further, Jackson Civil Engineering will now demonstrate why VGC are not entitled to any time and/or money in respect of this claim and why VGC’s submission, based on 1½ pages of unsupported statements, does not demonstrate entitlement as follows: …”
“It can be seen that the substantiation of any claim for an extension of time/delay and disruption by VGC has not been made, and only emanates from the deduction by Jackson … of its costs due to the extensive overrun on the Contract by VGC causing severe costs to be expended by Jackson ...”
“(i) that Jackson Civil Engineering has valued the Application No 14 … correctly … (ii) that the set-off charges are applicable in the sum of£637,131.60 as contained in Appendices R and S … (iii) that VGC repay forthwith to Jackson … any monies Jackson … have overpaid VGC …”
“VGC attach their calculation of the additional OHP [Overhead and Profit] costs required due to this overrun to their subcontract works.”
“We are in receipt of a letter from VGC … dated29 May 2008 enclosing their Reply together with various attachments. Although most of these attachments are known and have been seen during the currency of the Contract, we would point out that the calculation of the VGC claim for extension of time is totally new. We therefore request the Adjudicator treat this as inadmissible in this Adjudication. We await your instructions.”
“The dispute between the Parties involves their failure to agree the value of the Final Account for work done by VGC under a sub contract to JCE in respect of duct laying, cable installation and associated works on the M3 Motorway during 2006 and 2007.”
“Having examined all of the documents provided by the Parties I am satisfied and therefore find that a crystallised dispute or difference exists between the Parties in respect of the valuation of the Final Account for the works, which includes the disputed application of Set Off Charges to the Final Account by [Jackson].”
“17.23 Extension of time.”
“1. The adjudication procedure does not involve the final determination of anybody's rights (unless all the parties so wish). 2. The Court of Appeal has repeatedly emphasised that adjudicators' decisions must be enforced, even if they result from errors of procedure, fact or law … 3. Where an adjudicator has acted in excess of his jurisdiction or in serious breach of the rules of natural justice, the court will not enforce his decision … 4. Judges must be astute to examine technical defences with a degree of scepticism consonant with the policy of the 1996 Act. Errors of law, fact or procedure by an adjudicator must be examined critically before the Court accepts that such errors constitute excess of jurisdiction or serious breaches of the rules of natural justice.”
“Secondly, however, like most words, ‘dispute’ takes its flavour from its context. Where arbitration clauses are concerned, the word has on the whole caused little trouble. If arbitration has been claimed and it emerges that there is after all no dispute because the claim is admitted, there is unlikely to be any dispute about the question of whether there had been any dispute to take to arbitration. And if the claim is disputed, any argument that the arbitration had not been justified because at the time it was invoked there had not been any dispute is, it seems to me, unlikely to find a receptive audience (although it appears that it did in Cruden Construction v Commission for the New Towns[1995] 2 Lloyd's Rep 37 ). So it is that in this arbitration context the real challenge to the existence of a ‘dispute’ has arisen where a party seeking summary judgment in the courts has been met by a request for a stay to arbitration and the claimant has wanted to argue that an unanswerable claim cannot be a real dispute. … 67. It follows that in the arbitration context it is possible and sensible to give to the word ‘dispute’ a broad meaning in the sense that a dispute may readily be found or inferred in the absence of an acceptance of liability, a fortiori because the arbitration process itself is the best place to determine whether or not the claim is admitted or not. 68. Thirdly, and significantly, the problem over ‘dispute’ has only really arisen in recent years in the context of adjudication for the purposes ofPart II of the Housing Grants Construction and Regeneration Act 1996 . Jackson J referred below to some of the burgeoning jurisprudence to which the need for a ‘dispute’ in order to trigger adjudication has given rise. In this new context, where adjudication is an additional provisional layer of dispute resolution, pending final litigation or arbitration, there is, as it seems to me, a legitimate concern to ensure that the point at which this additional complexity has been properly reached should not be too readily anticipated. Unlike the arbitration context, adjudication is likely to occur at an early stage, when in any event there is no limitation problem, but there is the different concern that parties may be plunged into an expensive contest, the timing provisions of which are tightly drawn, before they, and particularly the respondent, are ready for it. In this context there has been an understandable concern that the respondent should have a reasonable time in which to respond to any claim.”
“The defendant did not identify which houses were alleged to be defective or what those defects were nor did it call upon the plaintiff to put the defects right or to pay compensation. … The letter of Oct. 7 was the first suggestion there might be something wrong with the houses which the plaintiff had built but beyond that the plaintiff knew nothing more than that the defendant was about to start arbitration proceedings. It is of course right that the plaintiff’s solicitors in their letter of Oct. 11, did say that they were not acknowledging or admitting that the defendant had any basis for a claim against the plaintiff but it would in my judgment be wrong to treat that statement as in effect a non-admission by the defendant of the claim thereby putting the plaintiff to proof. A fair reading of the letter of Oct. 11, 1993 is that neither the plaintiff nor its solicitors knew what was going to be alleged against them in the arbitration proceedings and that the acceptance of service was not to be taken as an admission or acknowledgement that there were any matters which would give rise to a claim against the plaintiff. No such matters had been asserted by the defendant.”