“1. Ensuite fan not working. 2. 230v fan in Zone 1. 3. Single socket in airing cupboard poorly terminated. 4. No earth fly leads to metal back boxes. 5. Kitchen ring circuit incorrectly wired spurs off of spurs. 6. Shower pull cord indicator not working 7. No fan isolators fitted. 8. Distribution not correctly identified or labelled, also requires an insulating back plate and fire barrier. 9. CPC’s not correctly terminated in plasterboard switches. 10. Smoke alarm requires terminations checked and base fitted. 11. Unknown condition of Hob outlet plate/Cooker fusing. 12. Many cord grips have been removed or damaged. 13. No ID on RCD CPC. 14. No visual 4mm2 CPC around bathroom. 15. Many electrical appliances/equipment in the wrong zones in bathrooms. 16. CPC’s twisted together throughout.”
“60 no Plasterboard partitions… Whilst the Claimants’ costing of these works has significantly reduced (from£4,839 down to£1,421.58 ) the quantum of this claim has not been finally agreed, as the experts have not reached agreement over the duration…for each element of the works… 27 no Plasterboard/insulation to bathroom/shower… Whilst the Claimants’ costing of these works has significantly reduced (from£8,899 ) down to£258.58 the quantum of this claim has not been finally agreed, as the experts have not reached agreement over the duration…for each element of the works…”
“Mr Easton has allowed 10 anchors @£2000 each at one metre centres. The cost per anchor is taken form SPONS [a well known pricing publication]. No schedule of works is required, they are just rock anchors.”