“2. The Letter of Intent section (iii) also states that Müller will “reimburse RTS for the reasonable demonstrable out of pocket expenses incurred by RTS up to the date of termination”
“Thank you for your letter of 1st March and your acceptance (subject to the qualifications you list) of the terms of the letter of intent dated21st February 2005 . In accordance with section (iii) of the letter of intent above, we agreed that a formal contract with full contractual terms would be executed within 4 weeks of the date of the letter of intent. We have now mutually agreed to extend this period up to and including16th May 2005 during which period the terms of the letter of intent will continue to havefull force and effect. Please confirm your acceptance of the above by signing below where indicated.”
“Given that the contract is now almost agreed we hereby confirm that the expiry date for the current letter of intent can be extended until the27th May 2005 , or, if sooner, the date the contract is actually signed…”
“My view was that whilst we had agreed the wording in principal (sic), until the whole contract including the schedules had been compiled as a complete document and signed as accepted by RTS then it wasn’t enforceable. Whether this is right or not I don’t now know, but it was what I thought then. Therefore, to my mind, the milestone event at which the terms and conditions of the anticipated contract were agreed and in force was when RTS signed the document”
“This Contract may be executed in any number of counterparts provided that it shall not become effective until each party has executed a counterpart and exchanged it with the other”
“Once the equipment has been commissioned, the Site Acceptance Test (SAT) will be carried out. The SAT is a repeat of the CFAT, and is therefore carried out according to the CFAT procedure described in 7.5 to confirm compliance with the Specification. The equipment will be formally taken over when the SAT has been successfully completed. SAT trials are expected to take place within 7 days of completion of commissioning… Similarly, section 1.2.8 of the FDS provides in relation to take-over that: “once the equipment has been commissioned, the Site Acceptance Test (SAT) will be carried out…..The equipment will be taken over when the SAT has been successfully completed…” ”
“1. ASSUMPTIONS RTS cannot be held responsible for delays incurred due to the late delivery of any of the Free Issue items of equipment Date of delivery to RTS and completion of integration of the free-issued items, particularly Flow-wrapper and Cartoning machines will be agreed as required by our programme ……. We have assumed that the performance of free issued items will be sufficient to perform the SAT and CFAT tests. Should the performance of free issued items be insufficient to test the elements of RTS’ scope of supply, the CFAT and SAT tests are expected to be based on the maximum throughput allowed by the free issued items. … RTS cannot be held responsible for delays incurred due to the late delivery of any of the Free Issue items of equipment Date of delivery to RTS and completion of integration of the free-issued items, particularly Flow-wrapper and Cartoning machines will be agreed as required by our programme ……. We have assumed that the performance of free issued items will be sufficient to perform the SAT and CFAT tests. Should the performance of free issued items be insufficient to test the elements of RTS’ scope of supply, the CFAT and SAT tests are expected to be based on the maximum throughput allowed by the free issued items. … 2. FLOW WRAPPER It is a requirement of this project that the flow-wrapper be delivered to RTS in Manchester for system testing in accordance with the agreed timing plan …. 3. CARTONING MACHINE It is a requirement of this project that, as a minimum, the conveyor that transports the trays formed by the tray erector to the tray closer will be delivered to RTS in Manchester for system testing in accordance with the agreed timing plan Preferably the tray erector and tray closer will be also delivered to Manchester for a period of time to facilitate the performance tests.”
“Once all tests detailed in this test document for the SAT have been passed or otherwise agreed, a System Acceptance Certificate shall be signed by the RTS and customer representative to confirm take-over of the system by the customer”
“ 1. ASSUMPTIONS RTS cannot be held responsible for delays incurred due to the late delivery of any Free Issue items of equipment Date of delivery to RTS and completion of integration of the free-issued items, particularly Flow-wrapper and Cartoning machine, will be agreed as required by our programme The delivery, set-up and integration & support of the free issue equipment will be the responsibility of [Müller], and has not been included in this proposal. RTS cannot be held responsible for delays incurred due to the late delivery of any Free Issue items of equipment Date of delivery to RTS and completion of integration of the free-issued items, particularly Flow-wrapper and Cartoning machine, will be agreed as required by our programme The delivery, set-up and integration & support of the free issue equipment will be the responsibility of [Müller], and has not been included in this proposal. 2. FLOW-WRAPPER . It is a requirement of this project that the flow-wrapper be delivered to RTS in Manchester for system testing in accordance with the agreed timing plan . It is a requirement of this project that, as a minimum, the conveyor that transports the trays formed by the tray erector to the tray closer will be delivered to RTS in Manchester for system testing in accordance with the agreed timing plan”
“Take-over Once the equipment has been commissioned, the Site Acceptance Test (SAT) will be carried out…”