“The first step in establishing causation is to eliminate irrelevant causes and this is the purpose of the “but for” test. The Courts are concerned, not to identify all of the possible causes of a particular incident but the effective cause of the resulting damage in order to assign responsibility for that damage. The “but for” test asks: would the damage of which the claimant complains have occurred “but for” the negligence (or other wrongdoing), or to put it more accurately, can the claimant adduce evidence to show that it is more likely than not, more than 50 per cent probable that but for “the defendant’s wrongdoing the relevant damage would not have occurred. In other words, if the damage would have occurred in any event the defendant’s conduct is not a “but for” cause.”
“The logic of a global claim demands, however, that all the events which contribute to causing the global loss be events for which the Defender is liable. If the causal events include events for which the Defender bears no liability, the effect of upholding the global claim is to impose on the Defender a liability which in part is not legally his. That is unjustified. A global claim, as such, must therefore fail if any material contribution to the causation of the global loss is made by a factor for which the Defender bears no legal liability.”
“I had instructed outside lawyers [Mallesons] to come to our offices and search through our files and begin looking to see what the records were with respect to these matters.”
“There may be more than one critical path depending on workflow logic of delay to the progress of any activity in the critical path which, without acceleration or resequencing, may cause the overall Project to be extended.”
“To reduce the number of disputes relating to delay, the contractor should prepare and the employer should accept a properly prepared programme showing the manner and sequence in which the contractor plans to carry out the works. The programme should be updated to record actual progress and any extensions of time granted. If this is done then the programme can be used as a tool for managing change and determining periods of time for which compensation may be due.”
"Note added by BAILII: The text of the Delay and Disruption Protocol in fact reads as follows (see http://www.eotprotocol.com/) - "
“(a) measured movements of the steel columns needed to be verified and reconciled with movements of the concrete foundations (currently undertaken by Alstom’s staff); (b) the depth of the decomposed materials should be verified.”
“Overall the Project is presently showing critical delay of 160 days in the area of the water treatment plant. The construction delay in the civils is the master delay which is masking a delay in the supply of materials of 43 days. The construction programme is currently being rescheduled to address this problem.”
“The onshore construction contract continues to show the critical Project delays. Overall progress continues to be 4 weeks behind programme as per the April report.”
“The delay to present dates back to April 14 ’97 when the problem was first identified to you. From April 14 ’97 normal boiler erection has not been possible. “As you are aware, the boiler erection lies on the Project critical path and therefore this delay is affecting the Project end date and your speedy resolution of this issue is required.”
“9. We reiterate our opinion that there has been no necessity to suspend erection and that the structural integrity of the superstructure can be maintained with necessary jacking as has been effected to date and as recommended by our respective engineering consultants …”
“In our judgment excessive movement with as little as 1250 psf on a footing designed for 25+tons/ff² says this foundation has failed. We think it would be fruitless beyond this point to try to assess its further use as is, or adjust to the load. In our judgment time would be better invested in the core borings and plan to remediate the condition.”
“After working together for the last few months we have reluctantly concluded that your management style is not compatible with ours. On that basis we have requested your resignation from the company.”
“Option 1: Piles used as temporary support to allow excavation for underpinning with mass concrete below the existing foundation. Option 2: Piles used as temporary support initially but also forming part of the permanent works with a pile cap replacing the existing foundation.”
“They are currently reviewing site operations from top to bottom and making recommendations to further improve morale and production.”
“We do understand that the timely completion of the CW intake structure is critical to the overall completion of the Project and we are prepared to add additional resources to complete the works as quickly as possible.”
“The Project cost does not vary very much from the original plan submitted in November 1996. CEPA does not feel that the five month delay discussed by the Independent Engineer (Brown & Root) will have a material effect on the Project cost as stated in the November 1996 Revised Base Case because in the Revised Base Case CEPA had already imposed a six month cushion Projecting completion in December 1999. The Independent Engineers’ estimated five month delay is based on its original estimated Project completion in June 1999. One of the other potential problems areas, the transmission lines, was said to be expected to be completed by the end of January 1999.”
“There is ‘no official commercial operation date’. The boiler delay caused a five month schedule delay and we have developed a recovery plan called Revision G of the schedule which if we are able to recover it, will recover two months of the five months lost. Our agreement a couple (sic) ago was that we would pay for three months of schedule delays with an option of two months if we needed it. Our boiler delay will not affect the installation date of the transmission line which is scheduled to be complete by the end of October 1998. However by losing three months of the schedule we will not require the transmission until some time in December 1998.”
“The export of power from one unit can be accomplished through the 230-KV tie line and the new bay at the old Labrador substation. The new Labrador substation must be complete to be able to export power from both Unit 1 and Unit 2 simultaneously. Synchronisation of Unit 2 is presently scheduled for March 18 1999.”
“5. Finally, limited consideration of our possible counterclaims against Ove Arup & Partners (“OAP”) arising from their involvement at Sual … We propose to use these counterclaims in our ongoing negotiations with OAP in relation to their outstanding payment claims … (reference to Mr Delkousis) In my opinion you and your team can add real value to Sual. It is important however for us to strike a balance between your on-going role and the transfer of know-how from Shajiao [another Project]. I would therefore propose a monthly retainer for a period of nine months with a bonus to be awarded at the end of this period. This bonus would be at my discretion and in the order of 20% - 30% of the retainer. It would be payable should I determine that real value has been added by your firm. This is vague but I am certain your team is adding substantial value”
“Issue Potential liability of Ove Arup in relation to the boiler foundation problems Facts A review of Ove Arup’s role has discovered evidence to suggest a potential claim, particularly in relation to their possible role in monitoring the foundation/excavation works • A number of evidentiary uncertainties may impact on any entitlement to recover from Ove Arup in particular the role of Stewart Elliott • Draft contract issued.”
“If the assignor receives any money arising out of or in connection with the claim or the appeal it must immediately notify the assignee and the assignor: i. will hold such money on trust for the assignee, and ii. will deliver such money to the assignee within seven days of receipt of such money.”
“The manufacture period of the precipitators has extended by three month (sic) but on a phased delivery means that the first item will be available four months before programme delivery complete, seven months before the erection phase so these activities do not threaten the programme.”
“The six month delay of this design activity is at present affecting the end date of the Project.”
“The civil design of the water treatment areas is showing five months’ work to complete. This delay has utilised one month float in the programme … Impact on end date cannot be forecast at this time.”
“There have been delays in the performance of the works. SCC accepts responsibility for a 153 day delay due to the failure of the Unit 1 boiler foundation between1 April 1997 and1 September 1997 as well as from an average approximate 3 month delay across the other civil construction works as reflected under the F2 strategy programme.”
“The export of power from one unit can be accomplished through the 230 KV toe line and the new bay at the old Labrador substation. The new Labrador substation must be complete to be able to export power from both Unit 1 and Unit 2 simultaneously. Synchronisation of Unit 1 and export of power was targeted for18 December 1998 . Synchronisation of Unit 2 is presently scheduled for March 18, 1999.”
“Whilst any delay caused by the Unit 1 boiler foundation settlement, together with any acceleration measures said to have been put into effect as a result, ought to be evident from my examination of Windows 1, 2 and 3, the principal purpose of Window 4 is to permit a continuing examination of the Project through to its completion. The reason for carrying out this exercise is to consider further whether, based on the actual progress of the work during Window 4, areas of work unrelated to the Unit 1 boiler foundations would themselves have had the potential to cause delay to the key Project milestones regardless of the settlement of those foundations.”
“… in a commercial contract concerning goods, where it is in the contemplation of the parties that the proprietary interest in the goods may be transferred from one owner to another after the contract has been entered into and before the breach which causes loss or damage to the goods, an original party to the contract, if such be the intention of them both, is to be treated in law as having entered into the contract for the benefit of all persons who have or may acquire an interest in the goods before they are lost and damaged and is entitled to recover by way of damages for breach of contract, the actual loss sustained by those for whose benefit the contract is entered into.”
“In my judgment the present case falls within the rationale of the exceptions to the general rule that a plaintiff can only recover damages for his own loss. The contract was for a large development of property which, to the knowledge of both Corporation and McAlpine was going to be occupied and jointly purchased by third parties and not by the Corporation itself. Therefore it could be foreseen that damage caused by a breach would cause loss to a later owner and not merely to the original contracting party, Corporation. As in contracts for the carriage of goods by land there would be no automatic vesting in the occupier or owner of the property for the time being who sustained the loss of any right of suit against McAlpine. On the contrary, McAlpine had specifically contracted that the right of action under the building contract could not, without McAlpine’s consent, be transferred to third parties who became owners or occupiers and might suffer loss. In such a case it seems to me proper, as in the case of the carriage of goods by land, to treat the parties as having entered into the contract on the footing that Corporation would be enabled to enforce the contractual rights for the benefit of those who suffered from defective performance but who, under the terms of the contract, could not acquire any right to hold McAlpine liable for this breach. It is truly a case in which the rule provides ‘a remedy where no other would be available to a person sustaining a loss under a rational legal system ought to be compensated by the person who has caused it. ”
“It seems to me that a more realistic and practical solution is to permit the contracting party to recover damages for the loss which he and a third party has suffered being duly accountable to them in respect of their actual loss than to contract a theoretical loss in law on the part of the contracting party for which he may be under no duty to account to anyone since it is to be seen as his own loss. The solution is required where the law will not tolerate a loss caused by breach of contract to go uncompensated through an absence of privity between the party suffering the loss and the party causing it. In such a case, to avoid the legal black hole the law will deem the innocent party to be claiming on behalf of himself and any others who have suffered loss.”
“Where for its own purposes a group of companies decides which of its members is to be the contracting party in a project which is of concern and interest to the whole group I should be reluctant to refuse an entitlement to sue on the contract on the ground simply that the member who entered the contract was not the party who suffered the loss or a breach of the contract. But whether such an entitlement is to be admitted must depend on the arrangements which the group and its members have decided to make both among themselves and with the other party to the contract. In the present case there was a plain and deliberate course adopted whereby the company with the potential risk of loss was given a distinct entitlement directly to sue the contractor and the professional advisers. In the light of such a clear and deliberate course I do not consider that an exception can be admitted to the general rule that substantial damages can only be claimed by a party who has suffered substantial loss.”
“Lord Griffiths’ broader ground is not concerned with privity of contract as such. It is concerned with the damages recoverable by one party to a contract (the employer) against another (the contractor) for breach of contract and materials viz a building contract.”
“I fully accept that the courts are not normally concerned with what a plaintiff does with his damages. But it does not follow that intention is not relevant to reasonableness at least if there are cases where the plaintiff does not intend to reinstate. Suppose in the present case Mr Forsyth had died, and the action had been continued by his executors. Is it to be supposed that they would be able to recover the cost of reinstatement even though they intended to put the property on the market without delay?”
“Damages are designed to compensate for an established loss and not provide a gratuitous benefit for an aggrieved party from which it follows that the reasonableness of an award of damages is to be limited to the loss sustained.”
“I for my part cannot see that the tax reasons underlying the arrangements in the present case have any impact on the question whether Panatown is entitled to recover substantial damages from McAlpine.”
“65. The authorities in this area demonstrate the courts’ striving to ensure that wrongdoers do not escape from their liabilities by reference to the general principle that a person can only recover for his own loss because of the happenstance that a course of action lies in the hands of someone other than the person who has suffered the loss. The courts are concerned to see that justice is done between the parties.”
“A consortium comprising CEPA Slipform Engineering Limited (Slipform) and GEC Alstom (GECA) has been established to undertake the construction of a 2 x 600 MW capacity coal fired power station to be constructed at Sual in the Philippines. Slipform has requested Ove Arup & Partners (Arup) to submit technical proposals and a commercial bid for the design of the civil engineering works which will be fabricated and constructed by Slipform. This document constitutes Arup’s offer.”
“(a) Is the sum claimed reasonable; if not, what is a reasonable sum? (b) to what extent, if at all, is there a causal nexus between any delay caused by the settlement to the boiler foundations and the time-related costs allegedly incurred by Mirant? (c) which costs, if any, were incurred as a result of the failure of the boiler foundations?”
“In my judgment the reason why an insurer cannot normally exercise a right of subrogation against a co-assured rests not on any fundamental principle relating to insurance but on ordinary rules about circuity.”