"Employer's Changes. The Employer may at any time issue a notice proposing a Change in the form set out in the Employer's Requirements (a 'Change Notice Proposal'). The term 'Change' means: .1 a change (including any omission of work, services or obligations) to the Employer's Requirements ..."
"Works: the demolition of existing structures, Site clearance, ground and enabling works, construction, fit out and other works, the supply of goods, materials, components and parts, and all other work specified in or as may reasonably be inferred from or implied in the Employer's Requirements, the Contractor's Proposals or otherwise in the Contract and including all work, actions and services and any changes made to the foregoing in accordance with the Contract necessary or required to implement and complete the design, construction, fit-out, testing, commissioning, setting to work and handover of the Project and any works performed or defects, shrinkages or other faults or outstanding items corrected and/or completed during the defects liabilities period in accordance with the Contract. Contract: The Design and Construct Contract including the Contract Appendices thereto dated26 September 2002 between the Employer, (Wembley National Stadium Limited) and Multiplex Constructions (UK) Limited and Multiplex Constructions PTY Limited as guarantor, and referred to as the 'contract'. Inspection: The contract, the Contract Appendices, the Employer's Requirements, the contractor's proposal and the Contract Sum Analysis (excluding any detailed priced of the Contractor) and following additional documents, if any have been issued to the Sub-Contractor on Compact Disc. Any document referred to herein and/or contained on the compact disc may be viewed at the Contractors offices at a conveniently arranged time ..."
"the term 'Variation' means any 'Change' under the Contract so far as the same relates to the Sub-Contract Works or any change to the Numbered Documents."
"Relationship of Sub-Contract Documents If any conflict appears between the Conditions and/or the Appendix and/or the Numbered Documents and/or the Special Conditions the foregoing shall take precedence in the following order:- .1 the Articles of Agreement, .2 the Appendix, .3 the Conditions, .4 the Special Conditions, .5 the Numbered Documents." .5 the Numbered Documents."
"When the Contractor gives written notice of dissent under clause 14.1 practical completion for all the purposes of this Sub-Contract will be deemed to have taken place on such date as may be agreed or, if the parties fail to agree, as may be determined by the Adjudicator. Failing such agreement or determination practical completion will be deemed to have taken place on the date of practical completion of the Works as certified by the Employer's Agent in accordance with clause 16 of the Contract and 'practical completion' of the Sub-Contract Works for the purposes of the Sub-Contract shall mean either the date notified by the Sub-Contractor under clause 14.1, the date agreed between the Contractor and Sub-Contractor pursuant to clause 14.2, the date determined by the Adjudicator pursuant to clause 14.2 or failing such determination the date of practical completion of the works under the Contract as appropriate."
"The contractor will so far as he lawfully can at the request and cost, if any, of the Sub-Contractor obtain for him any rights or benefits of the Contract so far as the same are applicable to the Sub-Contract Works but not further or otherwise."
"Project Agreements The Subcontractor may, from time to time, be allowed access to or have been supplied with copies of agreements now or hereafter entered into between the Employer and/or the Contractor and third parties, or between third parties (including those identified in clauses 41, 41A, 41B and 41.1.15) which affect the Employer and/or the Contractor, or further information concerning the Project, including funding agreements, security agreements, shareholder agreements, consultancy agreements, planning agreements, Statutory Agreements, and agreements for lease or sale. Subject to the Sub-Contractor having had access to or receiving copies of such agreements or information (or such parts of the same as shall be material) and to the extent that such agreements or information relate to or affect the performance of, directly or indirectly, the Sub-Contract Works including any design of the Sub-Contract Works for which the Sub-Contractor is responsible: .1 the Sub-Contractor shall at all times so perform its duties and obligations under the Sub-Contract having due regard to such information and so as not to, by any act or omission, cause or contribute towards a breach or act or omission of default on the part of the Contractor and/or the Employer under such third party agreements. .2 the Sub-Contractor shall comply with any and all procedures set out in such third party agreements requiring liaison, consultation and/or submission of plans and/or proposals for approval by third parties. .3 except in relation to agreements between the Contractor and such statutory undertakers, to the extent such agreements or information were not available to the Sub-Contractor until after the Base Date and such performance or compliance constitutes a Variation, the Sub-Contractor shall be entitled to claim an extension of time and an adjustment to the Sub-Contract Sum in accordance with clause 4.6."
"1. On a true construction of the sub-contract between Multiplex and Honeywell dated27th May 2004 , Appendix Part 1 of the Articles of Agreement confers on Honeywell the right to view at a conveniently arranged time the main contract ('Main Contract') between Multiplex and Wembley National Stadium Limited ('WNSL'). 2. Honeywell's right to view the main contract described in paragraph (a) above extends to any variations thereof irrespective of whether such variations are formally described as such). 3. The completion agreement entered into between Multiplex and WNSL on or about19th October 2006 is presumed to vary the terms of the main contract. 4. Honeywell is entitled under the sub-contract to view the completion agreement described above."
"The recital of an agreement does not create a covenant where there is an express covenant to be found in the witnessing part relating to the same subject matter."