“In deciding whether the parties have reached agreement, the courts normally apply the objective test. Under this test, once the parties have to all outward appearances agreed in the same terms on the same subject matter, then neither can, generally, rely on some unexpressed qualification or reservation to show that he had not in fact agreed to the terms to which he had appeared to agree. Such subjective reservations of one party therefore do not prevent the formation of a contact.”
“In a commercial contract which when dealing with the future and sometimes the long-term future, of necessity leaves out certain matters to be worked out over time - an arbitration clause assists the court to find certainty by means of the implication of what is reasonable. Which is not to say that the Court will not itself provide the dispute resolution machinery even in the absence of an arbitration clause.” d) At paragraph 69: “However, particularly in commercial dealings between parties who are familiar with the trade in question, and particularly where the parties have acted in the belief that they had a binding contract, the courts are willing to imply terms where that is possible that enable the contract to be carried out … For these purposes an express stipulation for a reasonable or fair measure or price will be a sufficient criterion for the courts to act on. But even in the absence of express language the courts are prepared to imply an obligation in terms of what is reasonable.”
“Following your agreement to tender for the above scheme we now have pleasure in enclosing herewith the following: (i) One copy of the Bills of Quantities. (ii) One copy of the Form of Tender. (iii) One set of the Architect’s and Structural Engineer’s tender drawings as listed in the specification page 1/3 Clause 110. (iv) One set of the Mechanical and Electrical Technical Specifications plus listed drawings.
“Having read the Conditions of Contract and Specification and having examined the drawings referred to herein and visited the site do hereby offer to execute and complete the Works described in a workmanlike manner to the reasonable satisfaction of the architect/ca for the FIRM PRICE of£3,191,800 .”
“Please will you price out the Bill in its entirety including the preliminary section by next Tuesday at the latest?”
“In respect of the Preliminaries please can you price each “fixed” and “time related” item as applicable. The measured sections should not include all-encompassing rates that cover a number of items.”
“We enclose herewith as requested our priced Bill of Quantities. Please note that we have included alternative suppliers/subcontractors in some instances.”
“I/We having reading the Conditions of Contract and Specification and having examined the drawings referred to therein and visited the site do hereby offer to execute and complete the Works described in a workmanlike manner to the reasonable satisfaction of the architect/CA for the FIRM PRICE sum of …”
“I/We further undertake and agree when so required to execute a Form of Contract in the form referred to in the said Conditions of Contract …”
“However, as discussed, savings are necessary in order to achieve an agreed contract sum. In the mean time we would very much welcome offers from yourselves where meaningful savings might be found.”
“Employers Requirements for Contractor Designed Pre-Cast Floors. Felton is requested to provide a price for carrying out these revised works.”
“You will recall a phone conversation we had when we asked you to indicate the minimum requirement of external works you required in order to provide your necessary hardstanding during the contract. Please will you advise on this in order that we can calculate the level of saving achievable.”
“We advise that the minimum hardstanding requirement for construction purposes would be a 5 metres wide strip to the perimeter of the building plus the access road, car park and service area.”
“We would endeavour to submit a price for the precast units on Monday next.”
“We have received a revised ironmongery schedule and would advise after subsequent discussions that we recommend a reduction in the provisional sum of£10,000 for this item.”
“Further to your telephone call last Friday we offer a saving of£400 for air filled double glazed units to windows (not doors) in lieu of argon filled.”
“B. The contractor must include for all costs associated with all preliminary items and make due allowance in the programme for all works indicated by the following PC and Provisional Sums.” and “C. The CA reserves the right to deduct the whole or any part of any PC or Provisional Sum indicated in this Bill and the contractor shall take the instructions of the CA regarding the estimates of specialists etc.”
“Following the finalisation of the measurement of the omission for the external works, the saving against the pin boards was not necessary and consequently they remained in the contract sum.”
“Item 20 was an adjustment of the contingency sum in order than an overall saving of£4,930 was achieved following the final measurement for the reduction to the external works for inclusion in the Addendum Bill the saving against contingency was not as high as had been anticipated in the “list of saving”.”
“I refer to your tender reasonably submitted for the above scheme and write to confirm that the City Council has decided to accept your tender and conditions which we have agreed. Whilst the City Council will embody the agreed terms and conditions in a formal contract document as soon as possible, it is the full intention of the City Council (as evidenced herein) that once the duplicate of this letter has been signed by your company a binding legal contract shall arise between the parties enforceable by each.”
“All those within the JCT Standard Form of Building Contract Local Authority with Quantities 1999 Edition incorporating Amending 1, 2 and 3 with Amendment 4 all as adapted by the JCT Contractor’s Designed Portion Supplement 1998 edition revised May 2000 and as amended by the Project Specific Amendments and in the conditions referred to in the “Tender Letter” dated26 February 2003 as prepared by Markhams.”
“We enclose a copy of the signed letter of intent for your attention and look forward to receiving the contract documents in due course …”
“I/We acknowledge receipt of a letter of which this is a duplicate and agree that, upon my/our signature hereof, a contractual relationship exists between Felton Construction Ltd on whose behalf I/we sign and Liverpool City Council.”
“All items marked PROVISIONAL in the Bills of Quantities are to be priced out at the same rates as other similar items of measured work and would be subject to re-measurement on completion …”
“The contract is the JCT Standard Form of Building Contract Local Authorities with Quantities 1988 Edition incorporating Amendments 1, 2 and 3 with Amendment 4 all as adapted by the JCT Contractor’s Design Portion Supplement 1988 Edition revised 2000.”
“Two blank copies of the Bill of Addendum will be issued to Feltons week commencing6 May 2003 .”
“A completed Bill of Addendum will be issued by Markhams to include the agreed changes to that tendered.”
“All revised as Bill of Addendum – omitting hard/soft landscaping, fencing, gates, safety barriers, reducing parking and access road to kerbs and hardcore only; adding 5m wide hardcore working zone.”
“John, Find attached the Addendum Bill for the above scheme. There are a couple of items which require further information from you in order that the descriptions reflect the changes made. [Reference to two savings amounting to£10,236 )] Once the information requested has been provided I will be in a position to finalise the addendum and be in a position to complete the contract documents and the two “blank bills”.”
“2.0 Carry out works as described on drawing 1495013 – timber fencing, security fencing, hard landscaping details 1-3 omitted as per Bill of Addendum – Pallisade gate, games court fencing and vehicle crossing detail retained.”
“Re: Stockton Wood Delay to the Contract In accordance with Clause 25.2.1 of the contract we write formally to advise you that the progress of the works is likely to be delayed. The cause and material circumstances of the delay is due to compliance with Architect’s instructions 31 and 32 relating to external works requirements … This is a relevant event under Clause 25.4.5.1 of the contract …”
“The delay notice has been issued as we are contractually obliged to do so under the terms and conditions of the contract should such an event become apparent.”
“Further to you(r) issue of priced BOQ (Bill of Quantities) in respect of the above, we would confirm that the rates are in accordance with our tender submission.”
“… This discussion will be held in light of the stated position of the client on this issue not to pursue damages provided costs are not raised by Felton Construction in relation to any extension of time and the project is delivered satisfactorily by20 August 2004 .”
“At present we have not received any information in support of or notification of delay to progress for the ten week period beyond11 June 2004 up to your reported programme completion date of20 August 2004 . In the absence of this information, we will be issuing a certificate of non-completion at the end of the revised contract completion date …”
“We have reviewed the contract documents for the above project and we are unable to sign the contract, as the drawings do not reflect the post tender revisions. For instance you have included the drawing for external works. These were omitted as a cost saving exercise. I would recommend that the document be reviewed with your design team to ensure the relevant information is applicable.”
“TH (Mr Herd of Felton) reported some anomalies in the tender package is to prevent FC from sign documents. HLP to contact Melanie Gill to establish the extent of anomaly.”
“HLP and FC (Felton) to progress extent of anomalies in tender documentation. HLP to contact City Solicitors.”
“Latest slip in programme due to late installation date for gas meter given as 18 August – additional of CCTV system and over painting to teaching walls.”
“In accordance with Clause 25.2.1 of the contract we write formally to advise you that the progress of the works has been delayed due to exceptionally adverse weather conditions and that this is a relevant event under Clause 25.4.2 of the contract.”
“We believe that it is pertinent to refer to Clause 30.1.3 of the Main Contract in this respect. Practical Completion has been achieved and therefore interim certificates shall be issued as and when further amounts are ascertained as payable to the contractor …”
“We should point out that it was for you to review extensions of time under Clause 25.3.3 within 12 weeks of the date of Practical Completion of the Works and to convey your decision to us irrespective of whether we had provided any further information. However the parties to the Contract are free to agree to extend such time and we are prepared to extend the period sufficiently to enable you to consider our claim when we re-submit it …”
“The correspondence between Feltons and me was in respect to the ongoing preparation of the addendum. When the extent of the omission of finished external surfaces had been finalised it was found that the saving was greater than originally envisaged. Consequently the pin boards were added back and the contingency sum adjusted. The revised addendum was sent to John Matthews on22 May 2003 . I did not at that point in time receive any correspondence from Feltons stating that they disagreed with the contents. Consequently the addendum was incorporated into the contract documents. During the course of the contact the addendum has been accepted as being part of the contract documents and has been used repeatedly including in the preparation of valuations. At no point did Feltons question the validity of the document. I consider that reverting back to a list of potential savings, other than the addendum bill, will just serve to confuse the issue and ultimately will lead to little financial adjustment. Time will be spent adjusting various instructions upon which the quantities in the addendum form an integral part. For example, the adding back of the site works will have to be re-assessed on the basis that the original bill contains more items than had been the case.”
“As to your letter of14 October 2005 , given there is no executed Contract Agreement, the JCT conditions of contract to which you allude are not at all relevant to the matter under discussion and we are certainly under no obligation in terms of clause 2.3 of those conditions.”
“If indeed this position has not already been reached HLP will meet with the employer and quantity surveyor to establish a complete and accurate set of contract documents.”
“On the basis of the list an addendum bill would be produced which would pick up the changes in measurement and specification.”
“We conclude that the variations amount to an addition of£258,311.14 compared to your application for£631,190.86 (excluding the claim and VAT). Taking into account our valuation of the variations our Final Account for the contract amounts to£3,240,111.14 excluding any substantial claim and VAT. The Final Account is therefore£217,000.64 less than Valuation No.17 issued on16 November 2004 .”
“18. It is Felton’s case that, notwithstanding the signature of the said Letter of Intent, as a result of ambiguities and uncertainties in the scope and therefore the price of the Works to be carried out, there was in fact no binding contract between the parties as a result of the exchange of correspondence.”
“Accordingly The Council is put to proof both as to the existence of any contract and the terms thereof under which the works undertaken by Felton should be valued and paid.”
“In the premises Felton contends that as at30 April 2003 the parties did not enter into a contract as contemplated in the Letter of Intent dated25 April 2003 .”
“Moreover it is Felton’s case that not only did they not do so then, they did not do so subsequently.”