“The request for an order to obtain quantity surveying evidence at the Case Management Conference on8 March 2007 ” – I think it is 9 March, but anyway that does not matter – “was rejected by the Court at that time. I understand from my subsequent conversations with Counsel that His Honour Judge Thornton QC confirmed that it was not necessary for the Court to make an order at that stage but said that it was open to the parties to obtain expert evidence from a quantity surveyor if either party felt it was necessary to do so and that any reasonable decision to rely on such evidence could be reflected in an appropriate Court order subsequently. The Court certainly did not rule out the possibility of an application for permission to rely on quantity surveying evidence being made at a later stage in the proceedings.”
“The Defendant requires permission to adduce expert quantity surveying evidence to support its case as to the costs of the remedial work that the Defendant now acknowledges would have been necessary in order to remedy the inability of the few areas within each Boarding House to meet the required internal design temperature. In his report, Mr Welch [Hannaford’s engineering expert] will identify the specific areas that require attention together with the works that he believes would have remedied the problem. The Defendant needs the evidence of a quantity surveyor to put a price on those remedial works.”
“Further and in any event, the provision of stand-by pumps, new boiler flues, new control valves and modifications to the control system are all items of betterment over Hannaford Upright’s original design and represent a revision and/or fundamental change in the Governing Body’s [Charterhouse’s] requirements. In the circumstances, the cost of the same is not properly recoverable from Hannaford Upright.”
“… it is admitted that the provision of stand-by pumps and of new boiler flues are items of betterment over Hannaford Upright’s original design and the Governing Body will give credit for those sums once they have been assessed. The Governing Body avers that these are modest sums totalling no more than approximately£35,000 . Save as aforesaid, Paragraph 70 is denied.”
“During the February 2007 data-acquisition exercise conducted at the Daviesites House by myself and Mr Child, I was shown the remedial works completed at Lockites Dormitory. The viewing was brief, but various items were pointed out or noted by myself as constituting an enhancement to the original heating scheme design completed by Hannaford Upright.”
“It is further admitted that the design undertaken by Hannaford Upright for the Year 1 Works was to be suitable and sufficient for the buildings to enjoy a further 30 years’ life after the Works had been performed.”
“At the first Project Meeting, held on Thursday8 March 2001 , and attended by (amongst others), Mr Grant, Mr Szymanski and Mr Kingston on behalf of the Governing Body, Mr Grant was issued with a copy of … the 1999 Regulations. At some point, whether prior to, during, or shortly after the meeting, GTMS/GTCM instructed Hannaford Upright to comply with the 1999 Regulations. On a date that Mr Grant cannot recall, he confirmed that Hannaford Upright would comply.”
‘I have been shown the minutes of a meeting dated8 March 2001 at which I was present and from which I can see that a copy of the … 1999 Regulations was provided to me “For information”. I have a very clear recollection that Gardiner & Theobald had at some point, whether before or after this meeting, made it very clear to us that we had to comply with the requirements of those Regulations. I cannot recall whether this was done over the telephone or by way of email, but I had no doubt that Hannaford was asked to confirm that it would be complying with the Regulations in carrying out its design for the heating system. I am sure that I confirmed compliance in circumstances, whether requirements of the Regulations for internal temperatures were significantly lower than the room temperature requirement that had been specified to us by the school.’
“(18) The replacement of the heating and hot water services at the Boarding Houses was completed in all material respects in accordance with the specifications and drawings produced by Hannaford Upright. The Year 1 Works were completed and commissioned during the School’s summer holidays in 2001 by Aircool Engineering Ltd. The Year 2 Works were completed and commissioned during the School’s summer holidays in 2002 by Dudley Bower Services Ltd (in respect of Lockites and Weekites), Aircool Engineering Ltd (in respect of Bodeites and Hodgsonites) and Kershall Mechanical Services Ltd (in respect of Pageites and Robinites). (19) Commissioning was carried out by Russell Commissioning and Validation Services Ltd on completion of the Works. Recommissioning of the system was carried out by Barfield (Commissioning Services) Ltd in mid-2003. Yet further commissioning and also flushing of the system was carried out by Paul Banyard & Associates and Seaton Associates in late 2003. The Governing Body avers that Year 1 and Year 2 Works were commissioned and recommissioned as adequately as possible within the parameters of the system as designed and installed. Recommissioning was performed in an attempt by the Governing Body to improve the performance of the systems.”
“It is denied that the Year 2 Works were commissioned as adequately as possible within the parameters of the system as designed and installed and further denied that the Year 2 Works were re-commissioned as adequately as possible within the parameters of the system as designed and installed.”
“It is further denied that such re-commissioning was carried out in accordance with the recommendations provided by Mr Grant of Hannaford Upright in July 2003. However, it is noted that in its report in relation to Lockites dated7 July 2003 , Barfield confirmed that: There seems to be no reason why the water cannot be distributed to allow all radiators to reach temperature …”
“In the circumstances, I said that it remained our view that any reported performance problems with the heating circuit were likely to arise from inadequate commissioning procedures.”
‘• From the numerous and varied items of correspondence circulating after works completion and the witness statements of House Masters and Matrons, it appears that various of the heating systems were not or not adequately commissioned or handed over once installed. • From Clause 4 of the “Site Refurbishment Meeting” dated13 Nov 2002 , the School confirmed their view “that no proper handover had been achieved”. I take this to confirm that (as well as other issues of inadequate balancing; cleansing; and commissioning) no adequate operational “teach in” had been given to the School’s Maintenance and Estate staff by GTMS. • I am of the opinion that if a heating system as designed had been installed; commissioned; handed over; operated; and maintained adequately, then the remedial works required to comply with the School’s brief would be minor in nature.’
“8.6 I note from documents scheduled at Appendix 22 that the individual heating systems were not adequately balanced, commissioned or handed over at practical completion … 8.9 In conclusion, I consider that the performance of the heating systems designed by Hannaford Upright was critically compromised by the lack of proper maintenance …; lack of adequate commissioning and water balances …”
“CPR Part 17 also requires me to apply the overriding objective (CPR Part 1 ) by considering whether the proposed amendments will enable the Court to deal justly with the claim in a way that is proportionate to the importance and complexity of the case and to the financial position of each party.”
“The Court may allow a party to amend or withdraw an admission.”