"All account of all monies paid to and incurred by the Defendant in connection with the project management and construction works at 16 Chepstow Villas, London, W11 2RB. Damages for breach of oral contract between the Claimants and the Defendant in relation to the project management and construction of works at 16 Chepstow Villas, London, W11 2RB. Repayment to the Claimants by the Defendant of monies had and received by the Defendant in respect of which the Defendant has been unjustly enriched. Delivery up of garden furniture and/or damages in respect thereof. Value We expect to recover more than£15,000 ."
"25.7(1) The court may only make an order for an interim payment where any of the following conditions are satisfied. --- .... (b) the claimant has obtained judgment against that defendant for damages to be assessed or for a sum of money (other than costs) to be assessed. ... (4) The court must not order an interim payment of more than a reasonable proportion of the likely amount of the final judgment."
"The Defendant has not filed an acknowledgment of service to the claim and the time for doing so has expired. It is ordered that the defendant must pay the claimant an amount which the court will decide and costs. ... "
"Very little data, however, has been produced by the defendant to support the tendering of packages or invoiced general items. I have therefore valued the work on an ad hoc basis using what little genuine data the Defendant has provided and/or applying reasonable market rates and prices to my assessment of works completed."