“12A. The Preliminary Issue Judge found that the rates set out in the Claimant's faxes of21 August 2000 and31 August 2000 were the contractual rates to be paid by the Defendant to the Claimant in respect of the items of plant and equipment identified in those faxes. “12B. Following and consequential upon such finding, the parties reached the following further agreement in relation to the rates to be paid in respect of items of plant or equipment which did not feature in the lists of plant rates notified by the Claimant to the Defendant on either 21 or 31 August: (2). Where no rate is specified in the FCEC 1992 schedules in respect of any item of plant or equipment, a reasonable rate should be agreed between the parties for that item of plant based upon industry custom and practice. Such rates have been referred to by the parties previously and are referred to in this statement of case as ‘star rates’. As found by the Preliminary Issue Judge, the parties expressly agreed. a number of star rates in August 2000, in that some of the rates specified in the faxes of 21 and31 August 2000 were star rates because they related to items of plant or equipment for which no rate is specified in the FCEC 1992 Schedules. Paragraph I2C below sets out the Claimant's case as to the manner in which those star rates which have not yet been agreed (‘outstanding star rates’) should be arrived at. The said agreements were incorporated by consent into the Preliminary Issue Judge's order made at the conclusion of the trial. I2C. The Claimant's case on outstanding star rates is that a reasonable rate for each of the relevant items of plant or equipment is the same rate as the star rate agreed by the parties for the same or a similar item of plant or equipment in respect of the FMD Works. The Claimant avers that the only industry custom and practice that was applicable, relevant or comparable to the CSF Works was that adopted by these parties in respect of the FMD Works. In further support of its case, the Claimant relies on the fact that, where the parties specifically agreed star rates for items of plant hired to the Defendant for the CSF Works (namely the star rates contained in the faxes of 21 and 31 August faxes), such star rates were the same as the star rates agreed for the same or similar items of plant when such items of plant were hired to the Defendant for the FMD Works. I2D. In the Final Account submitted to the Defendant in May 2007, particulars of which appear in paragraph 17 below, the Claimant has applied the approach set out in paragraph 12C above in arriving at the outstanding star rates. Plant and other equipment - Charges Due for Failure to Give Notice to Off-Hire 12E. At the trial of the preliminary issues, it was an issue between the parties whether the Defendant was required to give the Claimant notice when the Defendant wished to off-hire the Claimant's plant or equipment and, if so, what the period of notice should have been. The Claimant contended that seven days' notice was required pursuant to Clause 24 of the CPA Conditions. The Preliminary Issue Judge found that Clause 24 set out a procedure for determining the contract between the parties, and not for determining the hire of any individual item of plant or equipment. 12F. The Preliminary Issue Judge went on to find that there was a requirement on the Defendant to give notice to the Claimant when it desired to off-hire any item of plant or equipment, in that a term was implied into the Contract requiring the Defendant to give the Claimant reasonable notice in the circumstances and context of the Contract was seven days (“the implied term concerning notice to off-hire”). 12G. The Claimant’s case is that, as at the date of the preliminary issue trial, it had not invoiced the Defendant for hire of plant and other equipment for any part of the seven-day notice to which it was entitled following receipt of the Defendant’s instruction to take the item of plant or equipment off hire. Following the Preliminary Issue Judge’s findings set out at paragraph 12F above, the Claimant submitted its Final Account to the Defendant on or about4 May 2007 , which includes charges, pursuant to the implied term concerning notice to off-hire, in respect of such seven days period for each item of plant or equipment hired to the Defendant. The submission to the Defendant of the Claimant’s Final Account amounts to a demand for payment of the said sum. The Defendant’s unparticularised case at the trial of the preliminary issues was (and it is understood still to be) that the Claimant did not charge the Defendant within the invoices specified in Appendix 3 to the Particulars of Claim for hire during periods following the giving by the Defendant of notice of off-hire of certain unspecified items of plant or equipment. The Claimant’s case at the trial of the preliminary issue was and remains that this is not so and that there is no overlap between the plant hire charges contained in the invoices specified in Appendix 3 to the Particulars of Claim and the said further plant hire charges now contained with the Final Account. Subject to determination of this issue of the fact, the Claimant avers that the Defendant is liable to pay the said further plant hire charges as a consequence of the Preliminary Issue Judge’s findings set out in paragraph 12F above. … 16A. Alternatively, pursuant to regulation 7 of the 1998 Regulations, the payments outstanding under the Contract became due either (a) on the expiry of 7 days following the completion of the work to which the payment related or (b) on the making of a claim by the Claimant, whichever is the later. l6B. Where, as in this case, the parties failed to provide any or any adequate mechanism for determining when payments became due under the Contract and/or when the final date for payment would be, the final date for the making of the payments outstanding is, pursuant to regulation 8(2) of the 1998 Regulations, 17 days from the date that the payment became due, as determined in accordance with paragraph 16 or paragraph 16A above.”
“In trying this question, I believe I state the rule of the Court correctly when I say that, where a given matter becomes the subject of litigation in, and of adjudication by, a Court of competent jurisdiction, the Court requires the parties to that litigation to bring forward their whole case, and will not (except under special circumstances) permit the same parties to open the same subject of litigation in respect of matter which might have been brought forward as part of the subject in contest, but which was not brought forward, only because they have, from negligence, inadvertence, or even accident, omitted part of their case. The plea of res judicata applies, except in special cases, not only to points upon which the Court was actually required by the parties to form an opinion and pronounce a judgment, but to every point which properly belonged to the subject of litigation, and which the parties, exercising responsible diligence, might have brought forward at the time.”
“(1). These Rules are a new procedural code with the overriding objective of enabling the Court to deal with cases justly. (2). Dealing with a case justly includes, so far as practicable - (a) ensuring that the parties are on an equal footing; (b) saving expense; (c) dealing with the case in ways which are proportionate: (i) to the amount of money involved; (ii) to the importance of the case; (iii) to the complexity of the issues; and (iv) to the financial position of each party; (d) ensuring that it is dealt with expeditiously and fairly; and (e) allotting to it an appropriate share of the court’s resources, while taking into account the need to allot resources to other cases.” (a) ensuring that the parties are on an equal footing; (b) saving expense; (c) dealing with the case in ways which are proportionate: (i) to the amount of money involved; (ii) to the importance of the case; (iii) to the complexity of the issues; and (iv) to the financial position of each party; (d) ensuring that it is dealt with expeditiously and fairly; and (e) allotting to it an appropriate share of the court’s resources, while taking into account the need to allot resources to other cases.”