"AIG Consultants" means AIG Consultants Limited. "
"With regards to your quotation dated3rd May 2001 , I am pleased to confirm that you have been allocated the above development for the site infrastructure and foundation/floor construction works. "
"We are pleased to confirm our instruction to carry out civil engineering works and external works at the above site in accordance with your quotation dated3rd May 2001 and6th September 2001 ... "
"1. All works to be carried out in accordance with the Joynes Pike Report and AIG Consultants Report in relation to details, recommendations and requirements with regards to gas and any other abnormal bodies which require precautions. "2. The responsibility for setting out lies with yourselves ... "16. Our "
"All workmanship and all materials where such are supplied by the subcontractor as part of its works shall comply with the requirements of any relevant local authority, the NHBC or any associated or successor body, all statutory and other obligations, current building regulations and further with the requirements of the company, including any specification which the company has supplied for that purpose, and in any event and without operating to reduce the effect of any and all implied conditions or terms to qualify and without prejudice to the generality of the foregoing all workmanship and materials shall be of a high standard, free from defects and fit for their purpose. "
"(a) The subcontractor shall be liable for and shall indemnify the company against any expense, liability, claim, loss or proceedings in respect of any injury or damage whatsoever, to any property including the subcontract works, any temporary subcontract works, any materials or any other things delivered to site for incorporation therein, and construction plant, tools, equipment, temporary buildings and contents owned or hired by the subcontractor or for which he is responsible, insofar as such injury or damage arises out of or in the course of the subcontract works unless due to any negligence of the company or any person for whom the company is responsible. "(b) The subcontractor shall be liable for and shall indemnify the company against any liability, loss, claim or proceedings whatsoever arising under any statute or common law in respect of personal injury or death of any person whomsoever arising out of or in the course of or caused by the carrying out of the subcontract works, unless due to any act or negligence of the company or any person for whom the company is responsible."
"19. Prior to disclosure and/or prior to further expert inspection of the piling works,the best particulars the claimant can give of the defendant's breaches are as follows. A. The defendant failed to give any or any proper consideration to the appropriate diameter/cross sectional area and length of the piles used at the phase I land and the phase II land, having regard to the soil conditions at the site. B. In particular, the defendant failed to give any or any adequate consideration to: (a) the possible negative skin friction effects caused by the soft soil settling around the piles and reducing the capacity of the pile to carry loads imposed by the structure; "(b) the performance of steel and concrete piles in the ground conditions encountered on the site (the natural topography of the site consisting of a depression of between 3m and 4m in-filled with inert waste comprising rubble and waste soils, underlain by soft alluvium); "(c) the fact that when a pile is driven through soft ground and into harder grown it is common for some of the soft material to be dragged into the interface between the harder ground and the pile, reducing the pile capacity; "(d) the driving conditions above the bearing strata, in particular, in the made ground which potentially contained object constructions such as kerbstones; "
"(a) the driveability of the slender piles in the made ground; "(b) uncertainty as to where the piles were driven to laterally; "(c) flexion occurring during the driving process, caused by the length of the piles; "(d) the need for special consideration to be given to the capacity of the piles and the stratum to which they were driven because the base area of the piles was so small that they would rely almost completely on friction on the shaft to hold the load. "d. Further, the defendant failed to give any or any proper consideration to the appropriate design of the piles. "e. The basis of the design of any bearing pile is its ultimate axial capacity in the particular soil conditions at the site where the structure is to be built. The ultimate capacity can be determined either by load tests on piles constructed at the site or by the use of an empirical formula to predict capacity from soil properties. "f. In designing the piles, the defendant failed to make any or any adequate calculation of their ultimate capacity and to adequately characterise the ground conditions of the site to allow such a calculation. "g. The defendant is understood to have calculated the driving resistance of the piles using a formula known as the Hiley Formula. The defendant is understood to have proceeded on the assumption that the ultimate capacity of the piles was the same as their driving resistance, calculated in accordance with the Hiley formula. This assumption was false. Although the ultimate capacity of piles may occasionally be the same as their driving resistance, there is not necessarily any equivalence between the two. Ultimate capacity is particularly unlikely to be the same as driving resistance in cohesive (clayey) soil conditions, such as though those on the phase 1 land and the phase 2 land. "h. Taking the piles at plot 10 by way of example from the phase 1 land, three of the piles were too short to carry the anticipated loads (ignoring the effects of negative skin friction which would have reduced the piles capacity still further). The ultimate capacity of several other piles was only just higher than the applied load whereas the usual safety factor would be at least 1.5 to allow for variations in ground strength and uncertainty in the design process. "i. Taking the piles at plot 56 by way of example from the phase 2 land (and again ignoring the possible effects of negative skin friction), the working load of the piles significantly exceeded their capacity on the assumption that the glacial till occurred at 12m below ground level which it does at BH4, which is close to plot 56). "j. In addition, taking into account the likely effects of negative skin friction (as they ought to have been, but were not, taken into account by the defendant), the ultimate capacity of the piles would be substantially exceeded by the working load. "k. Further, the defendant failed to ensure that the workmanship and/or materials used in the piling work were of a high standard and/or free from defects and/or fit for their purposes. "l. The defendant's engineering experts have carried out pile testing on the houses at plots 9, 10 and 56, each of which contains unacceptable cracks. According to their reports dated25th June 2003 and30th November 2004 , the piles which they inspected contained the following defects of workmanship and/or materials: "(a) The original design of the houses envisaged a connection between the hollow steel pile and the ground beam being supported by carrying reinforcement, from the top of the pile, a minimum of 40 bar diameters in to the ground beams, ie a plug of reinforced concrete cast in to the top of the driven pile. The depth of the concrete plug should have been about 700mm. "(b) Instead of being filled with reinforced concrete to this depth as it was designed to be, pile B1 on plot 9 was found to be hollow at depths of 150mm and 600mm below the foundation beam. "(c) Pile A4 on plot 10 was similarly found to be hollow and without the designed concrete plug. "(d) Pile A1 on plot 10 was discontinuous at about 150mm below the base of the ground beam. The top of the pile had been flame cut. The discontinuity was apparently caused by the trimming of the pile at too low a level. A satisfactory solution to this problem would have been to extend the ground beam to form a reinforced enclosure around the pile. The solution adopted by the defendant, of balancing an offcut on the top of the pile, shows a severe lack of understanding and quality control on the site. "(e) Pile A1 was similarly found to be hollow and without the designed concrete plug. In addition, the concrete piles under plot 56 appear to have had a structural discontinuity. "(f) In summary, there were significant workmanship defects in each of the houses supported by steel piles, including in particular the lack of a rigid connection between the ground beam and the pile head which would have altered the load spreading pattern between the elements of the ground beam grid as one or more piles settled under the load. Each house inspected contained at least one defective pile."
"Paragraph 13 of the Order dated20th October 2006 to be amended as so to read 'The Trial to take place on4th June 2007 in relation to all issues as to (i) liability, (ii) causation of damage including competing remedial schemes (save in respect of quantity of loss) and (iii) the Claimant's claim in the alternative for an indemnity'."
"26. As is apparent from the respective expert reports the main areas of dispute are (i) causation of loss and (ii) damage (existing and the possibility of future damage). "27. It is D's case that (i) C has in respect of many properties not proven its case on causation, and (ii) the vast majority of properties have satisfactory foundations, notwithstanding design defects and have and will only suffer minor damage ... "32. D's expert has addressed causation by creating 4 categories (A to D) which can be summarised as follows... "
"Houses to be supported on new piled raft foundations constructed from inside the property. Foundations to be constructed through holes in the raft and taken into the gravel layer: Piles to be jacked into position … Piles to be sleeved against negative skin friction. Subsequent fabric repairs to each property."
"In conjunction with the level survey, verticality measurements of the external walls and crack width monitoring may be required for some properties."
"RLN calculates higher factors of safety as a result of the piles bearing in sand and gravel. JJ has low factors of safety and notes 57 millimetres of tilt. 40 millimetres out of plumb and evidence from BSCP of progression. RLN considers that with more information it may have been possible to salvage some piles but agrees it is highly probable that foundation remediation was required."
"We agreed that there is little information to support the decision taken to remediate this building, but in the context of the low factors of safety we calculate and the evidence of the surrounding circumstances, it is highly probable that the decision was justifiable."
"There is no evidence that shows that foundations are moving at the present, so on the current evidence that would appear to be the case. But the survey data is only three weeks apart, as previously -- in view of the relatively good factors of safety at this location, noting that there are one or two piles between 1 and 1.2, with negative skin friction operating, I consider it is likely that the foundations are stable, but that hasn't been completely demonstrated yet."
"There is no existing loss or damage or claim which gives rise to an indemnity. The courts will not provide declaratory relief in respect of speculative or hypothetical matters."
"1. Damages for distress and inconvenience (see Watts v Morrow[1991] 4 All ER 937 (CA) and Farley v Skinner[2002] 2 AC 732 (HL)). "2. Loss of use/amenity -- to be assessed (if any). "3. Loss of earnings -- subject to proof."
"Like Bingham LJ in Watts v Morrow[1991] 1 WLR 1421 , 1445H, I consider that awards in this area should be restrained and modest. It is important that logical and beneficial developments in this corner of the law should not contribute to the creation of a society bent on litigation."
"SHL is entitled to recover from Encia such damages (if any) as in law are due from SHL to the owners of plots 2, 3, 4, 7, 8, 11, 12, 13, 14, 15, 16, 18, 20, 27 and 28, 30, 37, 48, 50, 52, 53, 54, 55, 57, 62, 63, 64, 65, 66, 67, 68, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 81, 83, 84, 85, 86, 87, 88 and 89 in respect of (a) diminution in value, (b) distress and inconvenience, or (c) incidental expenses in consequence of any breach by SHL of a contractual duty to provide adequate foundations."
"Trial to take place on4th June 2007 in relation to all issues in the claim ... as to liability, causation of damage (including competing remedial schemes) save in respect of quantification of loss."