“Further to our telephone call yesterday. I am pleased and relieved that we have reached agreement regarding our appointment details, I will prepare the appointment documents and forward them to you for signature, I confirm the following basic points: 01. Lump sum fee of£277,000.00 02. CFW to propose the payment instalment. 03. Form of appointment to be the standard RIBA Standard Form of Appointment for Design & Build 04. Appointment to include up to 40 site visits. The instalment breakdown will be subject to the programme of design information, the details of which will no doubt become clearer at the meeting on [13 June 2000 ]; it is therefore probable that I won’t be able to issue the appointment document to you until week commencing19 June 2000 as I am on leave next week.”
“Further to my fax earlier today, I have again liaised with the team in our office who will be producing the drawing information, and confirm that we will discuss/agree the ‘milestone’ payments at our meeting tomorrow, however I propose the following which perhaps you could give some thought to prior to tomorrow:10 July 2000 -£75,000 > see notes below for definition of milestone stages7 August 2000 -£75,000 > leading up to completion by30th October 2000 4 September 2000 -£30,000 >2 October 2000 -£30,000 >30 October 2000 -£30,000 > [a list of 19 small monthly payments from November 2000 to April 2002] … Month 1 –10 July 2000 - general arrangement plans for sites 1, 2 & 3 - general arrangement house sections for sites 1, 2 & 3 - sit layouts for sites 1, 2 & 3 Month 2 –7 August 2000 - block elevations for sites 1, 2 & 3 - general arrangement plans for site 4 - general arrangement sections for site 4 Month 3 –4 Sept 2000 - site layout for site 4 - external works details for sites 1, 2 3 & 4 - external fabric details for sites 1, 2, 3 & 4 Month 4 –2 Oct 2000 - block elevations for site 4 - miscellaneous details/kitchen layouts for all four sites Month 5 –30 Oct 2000 - completion of miscellaneous details - overall completion on checking of production information”10 July 2000 -£75,000 > see notes below for definition of milestone stages7 August 2000 -£75,000 > leading up to completion by30th October 2000 4 September 2000 -£30,000 >2 October 2000 -£30,000 >30 October 2000 -£30,000 > [a list of 19 small monthly payments from November 2000 to April 2002] … Month 1 –10 July 2000 - general arrangement plans for sites 1, 2 & 3 - general arrangement house sections for sites 1, 2 & 3 - sit layouts for sites 1, 2 & 3 Month 2 –7 August 2000 - block elevations for sites 1, 2 & 3 - general arrangement plans for site 4 - general arrangement sections for site 4 Month 3 –4 Sept 2000 - site layout for site 4 - external works details for sites 1, 2 3 & 4 - external fabric details for sites 1, 2, 3 & 4 Month 4 –2 Oct 2000 - block elevations for site 4 - miscellaneous details/kitchen layouts for all four sites Month 5 –30 Oct 2000 - completion of miscellaneous details - overall completion on checking of production information”
“11. The services that were to be performed by CFW were as described in SFA/99 with Amendment DB2/99. As part of these services, the architect is to identify any key dates that the contractor client wishes to achieve and to advise on the consequences of any subsequent changes on cost and programme. [The adjudicator referred to Note 3 and E5 of DB2/99] 12. There is both an express and an implied duty on the architect that he will actively seek out the key dates, advise if these are achievable and notify the contractor of the consequences if these dates are changed or are failed to be met. The architect is therefore under a duty to produce the information that he has been commissioned to produce in a timely manner that will meet the contractor’s programme, provided always that such a programme is reasonable and achievable.”
“… what we needed to put in our appointment document was a schedule of drawings and dates when they would be completed by. So that became our design programme which was attached to our appointment document.”
“In accordance with well-known and settled principles, therefore, any time obligation would be set at large by any prevention event. CFW would simply have an obligation, in these circumstances, to complete its design within a reasonable time taking into account the impact of the acts of prevention.”
“I do regard there [as] being advanced [by CFW] a general case that the finalisation of the design drawings to be produced pursuant to the design set up programme were dependent upon the input from, amongst others, DHE’s approval [and to] to variations as pleaded … . Those are, however, very general allegations that do not identify in any way what the nature of the variations were and how that approval process delayed any particular set of drawings, and in the absence, as apparently there is, of expert evidence, I regard the case at the moment as being one which is only being advanced in very general terms. If, therefore, reliance is sought in closing submissions on a great deal of detail to make good in any more detailed way than the general way I have summarised, I regard that as not being within the ambit of the present pleadings and that that more detailed case is not currently open to be advanced.”
“(1) Whilst a party is entitled to present its case as it thinks fit and it is not to be directed as to the method by which it is to plead or prove its claim whether on liability or quantum, a defendant on the other hand is entitled to know the case that it has to meet. (2) With this in mind a court may – indeed must – in order to ensure fairness and observance of the principles of natural justice – require a party to spell out with sufficient particularity its case, and where its case depends upon the causal effect of an interaction of events, to spell out the nexus in an intelligible form. A party will not be entitled to prove at trial a case which it is unable to plead having been given a reasonable opportunity to do so, since the other party would be faced at the trial with a case which it also did not have a reasonable and sufficient opportunity to meet. (3) What is sufficient particularity is a matter of fact and degree in each case. A balance has to be struck between excessive particularity and basic information. The approach must also be cost effective. The information may already be in the possession of a party or readily available to it so it may not be necessary to go into great detail.”
“On the basis of the information provided, we are unable to confirm that the design will achieve the quality, functionality and performance of the brief.”
“Tim TIDWORTH Regarding the above, Jeff, Darren & I managed to achieve the target of22 August 2000 after some very long & arduous days drawings. Colin [Clark] rang us to express his views that if the 22nd August package is not enough to enable Cowlin to start then they must be f***ing barmy. However, on a far more serious note, if you come into the office over the bank holiday weekend, it is essential that you DO NOT touch the Tidworth drawings. We, (all 5 of us) must sit down with you and discuss, amongst other things, the technical standard & accuracy of your drawing work. Many hours were spent last week correcting your work, and as a practice, I feel (and I am sure that the other 4 feel also) that we cannot continue in this manner for the next 10 years, and therefore it is vital that you acknowledge there is a serious problem which must be properly addressed. I have saved several of these if you require examples, but there have unfortunately been too many discovered to save them all. For the sake of the Practice and everyone’s sanity, we must all speak soon regarding this. Neil.”
“Neil noted that there is an awful lot of work to do. Noses to the grindstone, don’t ever go home, grow an extra arm, gird the loins etc.”
“With regard to the resources of the practice, I can assure you that whilst we were somewhat taken aback by the amount of retrospective works required following Tim Worsfold’s departure (and I understand this is our concern not yours) we feel we have now made significant gains in this area. Part of our problem of course was not knowing exactly how much work was required, which is why we failed to meet deadlines offered on tracking sheets etc …”
“Further to the departure of Tim Worsfold from CFW, Jeff Murray has assumed responsibility for the Project; the transition has highlighted several areas of concern to the practice, it has become evident that items such as tracking sheets, site queries and clarification over elements such as external finishes etc. have slipped behind programme. CFW are aware of their responsibilities to supply such information and endeavour to rectify the backlog. … East Wylie Site design ongoing …”
“Outstanding£30,000 fees against East Wylie production information is not a negotiable item, we were promised payment upon providing drawings for construction purposes, this was subsequently amended to submission of peer review and then amended to receipt of peer review report. All of these items have been satisfied and we still await payment.”
“When I came out of the meeting what I would say is that we agreed to differ on it and consider it and come back … my parting words would have been along the lines of, “I don’t think we’re going to get anywhere today, I’m going back to the office, I’ll take the opportunity to discuss this [i.e. Mr Spiller’s proposal] with my partners and we will then respond to you in due course” – as soon as possible obviously. But I was not in a position to turn round and just agree everything right there and then with Mr Spiller.”
“The above reflects the topics discussed, if there are any other items discussed which I have not mentioned, please let me know. In the meantime, I await your response.”
“On the case presented by Cowlin, CFW repudiated its contract and the contract came to an end in August 2001. The remaining progress was the best that could be achieved by way of a reasonable response to that repudiation without particular recourse to any specific programme. As a matter of fact, given the resources available, the drawings were produced as quickly as they could have been and the work was then carried out within a reasonable timescale. CFW repudiated the contract and therefore any delay that occurred thereafter was a consequence of the repudiation and is not a matter for which you are responsible. Cowlin was the “victim” of that repudiation and it had a duty to mitigate the loss that that repudiation caused. However, unless CFW can show that Cowlin acted wholly unreasonably in the steps it took to mitigate its loss, it cannot be said to have failed in its duty to mitigate its loss.”
“We took every step. We had a meeting with Strides, we set out what we required, they afforded us the amount of resources they could put to what our requirements were. There was not any way that they could afford any more resources and I could not go anywhere else in terms of architecture to procure another company to actually carry out any works. We had taken Strides on the understanding that we would soak up all their extra resources and anybody additional to that that they could put on to this project, bearing in mind the remainder of the project was virtually dealt with by one architect, where on Strides we had five people I believe working on the drawings.”
“Please find a schedule containing details of the LADs and actual handover dates as applied in accordance with the terms of the contract. The total damages under the contract are£436,000 and have been deducted from the amounts due to you … The details incorporated in the schedule are all fully in accordance with the terms of the contract and therefore are not subject to negotiation or amendment. … I can confirm that the agreement contained in Amendment 2 and 4 to the contract [which included agreement as to the extent of the extension of time and consequent additional payment] was concluded on a ‘without prejudice’ basis.”
“In my view, a pre-estimate of damages does not have to be right in order to be reasonable. There must be a substantial discrepancy between the level of damages stipulated in the contract and the level of damages which is likely to be suffered before it can be said that the agreed pre-estimate is unreasonable.”