“We write to instruct: (a). That others are to be employed to comply with the30th January 2004 direction insofar as it relates to the staircases, with the costs consequences set out in clause 4.5. (b). The consequential immediate omission of the four metal staircases (recited as having a value of£44,500 in the addendum order) from the works instructed by the addendum order and … subcontract works as from the date of this letter. This instruction is issued pursuant to clause 4.5 following the notice under that clause in our letter of the24th March 2004 . We are prepared as a gesture of goodwill, subject to your not challenging our entitlement to issue the omission instructions and to your providing the information requested below by the14th April 2004 , effectively to treat the instruction as a clause 4.2 variation amending the January variation instruction addendum order, and to value and pay for design work in respect of the staircases. To that end we therefore request the issue of all design information in relation to the immediate element of the work referred to above to our site address, along with your cost for the completion of the design and drawings and all substantiating backup so as to allow an assessment to be made and values to be agreed for payment to Capital Structures Ltd. for the same. Please forward all of the above requested information by14th April 2004 . Please note that we have not yet instructed others to carry out work in respect of the balconies, juliettes and other undelivered elements. Given the fact of their fabrication obviously others will have to be so instructed if a further termination notice has to be issued under clause 29.2.2.”
“We write to give you notice pursuant to clause 29.2.1 that you have – (i). without reasonable cause wholly or substantially suspended the carrying out of the subcontract works and/or (ii). without reasonable cause failed to proceed regularly and diligently with the subcontract works in that you have withheld or delayed the delivery of fabricated balustrading, balconies and juliettes to the site or otherwise progress your subcontract works.”
“If you continue the above default for ten days from receipt of this notice, which is being delivered by hand delivery, then we may, in accordance with 29.2.1 on or within 10 days from the expiry of that 10 days by further notice determine the employment of your company under the subcontract.”
“In consideration of the above and save as set out above both parties acknowledge the above payments will be in full and final settlement of all and existing and/or future claims by Capital Structures, their servants, agents or any of them against JL Construction Ltd. in relation to or arising out of the works carried out at the above project and of all and any existing and/or future claims by JL Construction Ltd., servants, agents or against any of them against Capital Structures in relation to or arising out of the works carried out by Capital Structures at the above project. It provides that: “For the avoidance of doubt it is confirmed that if for any reason either party defaults on the terms of this agreement the parties are free to take any dispute to adjudication using the scheme rules under theHousing Grants Construction and Regeneration Act 1996 .”
“I agreed to the terms of the settlement letter as drafted by Allway, as slightly amended [he says] by JLC as I had no reason to believe that the balcony materials would not be fit for the purpose. Further, whilst I was aware of a problem with bolted connections with Capital I believed that bolted connections could be tightened for less than the sum of£20,000 . I was concerned at the time of entering into the settlement letter about paragraph 10 of the letter, which stated that this letter was to be in full and final settlement of all claims, but due to the pressure I was under I had no choice but to accept this. In any event, it had not been possible to get Capital to accept a settlement without such a term.”
“Commercial pressure without coercion is insufficient. If there is no sufficient coercion a threat to a pre-existing contractual obligation or an unfair use of a dominant bargaining position is insufficient to invalidate the consideration for the agreement.”
“At all times in connection with this adjudication JLC challenges the jurisdiction of the adjudicator to determine the matters in the referral notice. In particular, jurisdiction is disputed on the following bases: 1.1. JLC was forced to enter into the settlement letter under economic duress, the details of which are set out in section A of the response above.”
“I am accordingly of the option that is what is commonly called repudiation or total breach of a contract, whether acquiesced in by the other party or not, does not abrogate the contract thought it may relieve the injured party of the duty of further forfeiting the obligations which he has by the contract undertaken to the repudiated party. The contract is not put out of existence though all further performance of the obligations undertaken by each party in favour of the other may cease. It survives for the purpose of measuring the claims arising out of the breach and the arbitration clause survives for determining the mode of their settlement.”
“(a). enabled the parties to give notice at any time of its intention to refer a dispute to adjudication …”
“Even if the contract had been terminated the matters referred to the adjudicator remain disputes under the contract. Where there is a contract to which the Act applies, as in this case, and there are disputes arising out of the contract to be adjudicated, the adjudication provisions clearly remain operative just as much as an arbitration clause would remain operative. Had it been the intention of Parliament to limit the time wherein a party could give notice of intention to refer a matter to adjudication, in the exercise of his right under section 108(1) it could have imposed a clear limit.”
“… if proper steps are taken to avoid the agreement from which his jurisdiction derives.”
“If there has never been a contract at all there has never been as part of it an agreement to arbitrate. The greater includes the less. Further, a claim to set aside a contract on such grounds as fraud, duress or essential error, cannot be the subject-matter of a reference under an arbitration clause in the contract sought to be set aside.”