“6. As originally designed the building was to be constructed so as to be structurally independent of Nos. 50 and 70; the main foundations were to incorporate large diameter bored piles below basement level; and a secant pile wall was to be installed around the perimeter of the underground car park structure. 7. The proposed method of constructions was a “bottom up” form of construction. This involved the installation of the perimeter secant pile wall to enclose the basement area; temporary propping of the tops of the secant pile wall; and excavation to the full depth of the basement. The lowest level concrete slab would then be cast, followed by the intermediate slab and supporting columns. The temporary props would then be replaced by the permanent concrete ground floor transition slab, which would support the superstructure above. This form of construction requires the excavated basement to be kept dry during construction, and requires the concrete basement slab and walls to be able to resist water penetration.”
“36. Paragraph 55 of the Particulars of Claim refers to Dann’s drawing no. D5159/50 and was produced by Dann on3rd May 2000 for [Stent’s] tender purposes. It is clearly marked as a “CONSTRUCTION” drawing. It is admitted that this drawing is different from Dann’s earlier drawing but it is denied that such inconsistency is evidence of any want of care on the part of Dann. Further, Dann contends that the Claimant and/or Stent designed and installed the secant pile wall and that the Claimant employed its own surveyor (Jules Baroudi) and set out the secant wall in the position it chose. By its letter to Dann of28th July 2000 , the Claimant issued Dann with revised co-ordinates for the secant wall. Had there been any ambiguity which required resolution or concern on the part of the Claimant or/or Stent as to the precise or proper position of the secant wall, then they or either of them as reasonably careful and competent Developers and Contractors could and should have asked Dann for clarification of its drawings. Neither did so. Paragraph 1.06 of the Piling Specification which is noted at paragraph 34 hereof, expressly requires such action in the event of “inconsistencies or discrepancies” in the drawings supplied… 40. As to paragraph 59 of the Particulars of Claim, Dann avers and asserts that the piles referred to at paragraph 58 of the Particulars of Claim were installed by Stent in a row and are therefore the same distance from the five storey section of No. 50 as those installed previously. Accordingly, the claimant is put to strict proof if its case is that this further pile was in fact constructed closer to the five storey section of No. 50. Furthermore, Dann contends that Stent’s machinery was defective and that its pile logs were and are missing. Dann calls for the production of these (Stent’s piling) logs or a formal explanation as to their whereabouts if they are unavailable. If and to the extent that it is shown that Stent’s piling rig was defective and/or its logs missing, in respect of the latter Dann will also assert that the Claimant should have regularly collected the piling logs from Stent, and maintained them. If this did not happen, Stent should not have continued to install piles when its machine was malfunctioning and/or its logs were not being produced and/or maintained and equally, the Claimant, which as main contractor had a full time present on the site and was obliged to supervise its sub-contractor, should not have allowed it to do so. In doing so, Dann contends that both the claimant and /or Stent caused or contributed to the damage which occurred… 43. The first sentence of paragraph 61 of the Particulars of Claim is admitted, the second is denied and the Claimant is put to strict proof of the actual causes of the disturbance to the footings of the party wall. Dann refers to Stent’s letter to the Claimant of2nd October 2000 , in which it stated: “…nothing untoward was noted during either the boring or concreting phases.”
“62A. Further and alternatively, the damage was caused by Stent’s breaches of contract and/or negligence. PARTICULARS (1) Extensive flighting occurred during the installation of the piles prior to the Second Incident. The flight auger system caused local shaft enlargement, resulting in settlement of the sub-soil. (2) The flighting was either the result of a failure by Stent to control the piling rig, particularly the rate of penetration, and/or mechanical malfunction of the piling rig. (3) Further, had Stent maintained proper control of the piling rig and/or had Stent’s piling equipment been functioning correctly, it would have become aware as soon as difficult or changed conditions (such as grouted sands or gravels) occurred, and should have notified Peter Dann in accordance with its obligations under paragraph 8.01 and 8.02 of section 7 of the structural engineering specification. (4) Further and alternatively, Stent should have realised, at the latest when it was setting out and constructing the guide wall, that the co-ordinates of the secant pile walling given on Peter Dann’s drawing D5159/50 were inconsistent with the requirement on Peter Dann’s drawing 5159/PW02 that there be a distance of 1100mm between the face of the party wall below ground level, and the centre line of the secant pile wall, and should, incompliance with paragraph 1.06 of section 7 of the structural engineering specification, have drawn this to Peter Dann’s attention, and sought clarification.” (1) Extensive flighting occurred during the installation of the piles prior to the Second Incident. The flight auger system caused local shaft enlargement, resulting in settlement of the sub-soil. (2) The flighting was either the result of a failure by Stent to control the piling rig, particularly the rate of penetration, and/or mechanical malfunction of the piling rig. (3) Further, had Stent maintained proper control of the piling rig and/or had Stent’s piling equipment been functioning correctly, it would have become aware as soon as difficult or changed conditions (such as grouted sands or gravels) occurred, and should have notified Peter Dann in accordance with its obligations under paragraph 8.01 and 8.02 of section 7 of the structural engineering specification. (4) Further and alternatively, Stent should have realised, at the latest when it was setting out and constructing the guide wall, that the co-ordinates of the secant pile walling given on Peter Dann’s drawing D5159/50 were inconsistent with the requirement on Peter Dann’s drawing 5159/PW02 that there be a distance of 1100mm between the face of the party wall below ground level, and the centre line of the secant pile wall, and should, incompliance with paragraph 1.06 of section 7 of the structural engineering specification, have drawn this to Peter Dann’s attention, and sought clarification.”
“(1) For the purposes of this Act any new claim made in the course of any action shall be deemed to be a separate action and to have been commenced: (a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and (b) in the case of any other new claim, on the same date as the original action. (2) In this section a new claim means any claim by way of set-off or counterclaim, and any claim involving either: (a) the addition or substitution of a new cause of action; or (b) the addition or substitution of a new party… (3) Except as provided by section 33 of this Act or by rules of court, neither the High Court nor any county court shall allow a new claim within subsection (1)(b) above than an original set-off or counterclaim, to be made in the course of any action after the expiry of any time limit under this Act which would affect a new action to enforce that claim… (4) Rules of court may provide for allowing a new claim to which subsection (3) above applies to be made as there mentioned, but only if the conditions specified in subsection (5) below are satisfied, and subject to any further restrictions the rules may impose. (5) The conditions referred to in subsection (4) above are the following: (a) in the case of a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and (b) in the case of a claim involving a new party, if the addition or substitution of the new party is necessary for the determination of the original action.” (a) in the case of a new claim made in or by way of third party proceedings, on the date on which those proceedings were commenced; and (b) in the case of any other new claim, on the same date as the original action. (a) the addition or substitution of a new cause of action; or (b) the addition or substitution of a new party… (a) in the case of a claim involving a new cause of action, if the new cause of action arises out of the same facts or substantially the same facts as are already in issue on any claim previously made in the original action; and (b) in the case of a claim involving a new party, if the addition or substitution of the new party is necessary for the determination of the original action.”
“(1) This rule applies where: (a) a party applies to amend his statement of case in one of the ways mentioned in this rule; and (b) a period of limitation has expired under: (i) theLimitation Act 1980 … (2) The court may allow an amendment whose effect will be to add or substitute a new claim, but only if the new claim arises out of the same facts or substantially the same facts as a claim in respect of which the party applying for permission has already claimed a remedy in the proceedings.” (a) a party applies to amend his statement of case in one of the ways mentioned in this rule; and (b) a period of limitation has expired under: (i) theLimitation Act 1980 … substitute a new claim, but only if the new claim arises out of the same facts or substantially the same facts as a claim in respect of which the party applying for permission has already claimed a remedy in the proceedings.”
“29. In 1965 Ord 20, r.5 of the Rules of the Supreme Court 1965 was introduced with the effect of changing this practice in certain ways. So far as is material, it provided: ‘(2) Where an application to the Court for leave to make the amendment mentioned in paragraph (3), (4) or (5) is made after any relevant period of limitation current at the date of issue of the writ has expired, the Court may nevertheless grant such leave in the circumstances mentioned in that paragraph if it thinks just to do so… (5) An amendment may be allowed under paragraph (2) notwithstanding that the effect of the amendment will be to add or substitute a new cause of action if the new cause of action arises out of the same facts or substantially the same facts as a cause of action in respect of which relief has already been claimed in the action by the party applying for leave to make the amendment.’ 30. The power of the Rules Committee to introduce these new rules without the assistance of primary legislation soon came under fire, but it was upheld in Rodriquez v Parker[1966] 2 All ER 349 ,[1967] 1 QB 116 and Mitchell v Harris Engineering Co. Limited[1967] 2 All ER 682 ,[1967] 2 QB 703 for reasons which is not now necessary to describe. 31. The Law Reform Committee considered these rules in its Twenty-First Report: Final Report on Limitation of Actions (Cmnd 6923), published in 1977. After explaining the terms of RSC Ord 20, r 5 it said (at p 67 (paragraph 5.12)); ‘The Senior Master, who has suggested to us that the discretion of the court to allow an amendment of pleadings should be stated much more widely than it now is, has helpfully drawn our attention to the terminology used in Ruler 15(c) of the American Federal Rules of Procedure, under which a new cause of action may be added by amendment if “it arises out of the conduct, transaction or occurrence of events set forth or attempted to be set forth in the original proceedings”
“10. There is a slight different in language betweenCPR 17.4 and section 35(5).CPR 17.4 and section 35 have been construed in the light of the Human Rights Act in a case called Goode v Martin[2002] All ER 620 . That case concerned a case in which a claimant alleged negligence in relation to an accident suffered on a yacht. She had no memory of the accident and alleged one way in which the accident had occurred. The defendant pleaded a detailed defence saying it occurred in another way. Outside the limitation period she sought leave to amend her pleading to say that, even if it happened in the way the defendant alleged, the defendant was negligent. The argument on behalf of the defendant resisting the amendment was that, if one followed the language inCPR 17.4 which related to “facts or substantially the same facts as a claim in respect of which the party applying for permission was already claiming a remedy in the proceedings”, then permission to amend should not be given. The Court of Appeal accepted the submission of counsel for the claimant in that case saying that the CPR should be interpreted so as to contain additional words which would allow the claimant to b ring her claim outside the limitation period. It held thatCPR 17.4 (2) should be read, so far as material, in the following way: “The Court may allow an amendment whose effect will be to add a new claim, but only if the new claim arises out of the same facts or substantially the same facts as are already in issue on the claim in respect of which the party applying for permission has already claimed a remedy in the proceedings.”
“The policy of the section was that, if factual issues are in any event going to be litigated between the parties, the parties should be able to rely upon any cause of action which substantially arises from those facts.” 11. The test to be applied is thus, whether, even if a new claim is made, the new claim arises out of “the same facts already in issue”
“The policy of the section was that, if factual issues are in any event going to be litigated between the parties, the parties should be able to rely upon any cause of action which substantially arises from those facts.”