“Demolition and Alterations Carefully demolish areas of the buildings not required for the development, and place all debris within the floor voids. Infill areas of the perimeter where demolition has taken place, matching the existing as near as possible. Facing Bricks used to be Charnwood Multi imperial bricks, similar to those being used in adjacent buildings. Remove internal walls where not required, placing all debris within the floor void. Allow for all temporary propping required to support the roof slab prior to installation of new steel. Remove all existing windows and doors, adapt openings as required, and make good to receive new. Remove all existing roof coverings. Remove existing chimney breasts where necessary, and provide permanent support to the stacks at roof level. Remove all existing stairs. Remove all existing ceiling finishes, wall finishes and the like. Remove any remaining services, fittings and fixtures, both internally and externally. Allow for the specialist removal of asbestos in accordance with the Asbestos report provided with the tender documentation... Roof Allow for removal of defective roof timbers and replace with new. Our assessment of the quantity that will need to be replaced, bearing in mind the limited access to the roof, is no more than 30%. (See Clarifications) Allow for treating all roof timbers against future rot growth and damage. Provide new felt, battens and Spanish slates, including all hips, valleys, ridges and the like, and 100mm rockwool rollbatts, or similar. Allow for removing all existing guttering, rainwater pipes, fascias and soffits, and replace with new UPVC. Guttering to incorporate a leaf mesh. Fascias to include vents for roof space ventilation... External Walls Allow for cutting out severely defective bricks and replacing with new, as described above – 30% of total elevation area. (See clarifications) Allow for raking out and repointing mortar joints, again where severely defective – 25% of total elevation area. (See clarifications) Prepare 2nr test panels 2.00m x 2.00m including stone and brick detailing, to illustrate level of cleaning and repair that will be offered. Allow for fine sand blasting of the elevations to remove dirt, algae and the like, as being used on the adjacent clock tower building. Chemically inject the existing external walls with damp proof course to the perimeter of each block. Treat the cavity to prevent future damp growth and damage”
“On re-evaluation of our allowance for the repairs to the roof, we confirm that we will remove our qualification regarding the percentage of repairs allowed”
“With regard to the repairs to the external elevations, we acknowledge your request to include a Provisional Sum for this work. We confirm our allowance and subsequently our provisional sum for this work at£180,000.00 . As requested a schedule of rates is attached”
“In response to your fax dated14th July 2000 , we confirm that we have included for all structural works necessary following alterations made to the buildings by us in order to complete the development proposed. We confirm that this allowance is within our tender, and will not form part of the works covered by the Provisional Sum for external façade repairs and cleaning”
“1. Did the Employers retain the risk of unforeseen works to the existing structure of the building which might be necessary (a) before the specified works of design, refurbishment and conversion could proceed, or (b) as a consequence of the said works? 2. Did the allegedly unforeseen structural works to the underlying fabric of the buildings carried out prior to, during or after performing the specified contract works constitute a change in the Employers’ Requirements which require evaluation under Clause 12 of the JCT WCD?”
“No, save for those works to the external façade which are the subject of the provisional sum of£180,000.00 ”
“The judge has to consider the application on its inherent merits. If he is not satisfied that the question of law proposed for determination ought to be determined at that stage he should refuse the application... Section 2 is the successor in title to the old consultative case which more aptly describes its nature. Put colloquially the arbitrator or the parties nip down the road to pick the brains of one of Her Majesty’s judges and, thus enlightened, resume the arbitration. It is essentially a speedy procedure designed to interrupt the arbitration to the minimum possible extent and it is an exception to the general rule that the courts do not intervene in the course of an arbitration”
“2.1 The Contractor shall upon and subject to the Conditions carry out and complete the Works referred to in the Employer’s Requirements, the Contractor’s Proposals (to which the Contract Sum Analysis is annexed), the Articles of Agreement, these Conditions and the Appendices in accordance with the aforementioned documents, and for that purpose shall complete the design of the Works including the selection of any specifications for any kinds and standards of the materials and goods and workmanship to be used in the construction of the Works so far as not described or stated in the Employer’s Requirements or the Contractor’s Proposals... 2.5.1 Insofar as the design of the Works is comprised in the Contractor’s Proposals and in what the Contractor is to complete under clause 2 and in accordance with the Employer’s Requirements and the Conditions (including any further design which the Contractor is required to carry out as a result of a change in the Employer’s Requirements), the Contractor shall have in respect of any defect or insufficiency in such design the like liability to the Employer, whether under the statute or otherwise, as would an architect or, as the case may be, other appropriate professional designer holding himself out as competent to take on work for such design who, acting independently under a separate contract with the Employer, had supplied such design for or in connection with works to be carried out and completed by a building contractor not being the supplier of the design. 2.5.2 Where and to the extent that this Contract involves the Contractor in taking on work for or in connection with the provisions of a dwelling or dwellings the reference in clause 2.5.1 to the Contractor’s liability includes liability under theDefective Premises Act 1972 ...”
“No, save for those works to the external façade which are the subject of the provisional sum of£180,000.00 ”
“Did the Employers retain the risk of unforeseen works to the existing structure of the building which might be necessary (a) before the specified works of design, refurbishment, and conversion could proceed or (b) as a consequence of the said works?”