"(1) There is no supporting substantiation for the extension of time, and on the factors raised we comment as follows. (2) Within your letter dated 4th April you state the lack of external wall plastering has delayed the works. Whilst we acknowledge there have been problems in this respect, there has at all times been sufficient areas of work available for you. Please refer to our sub-contract progress meeting No. 5. (3) We believe that: (a) your initial notice that you believed it was necessary to derogate from the IBSEC outline specification indicated that you were late addressing the final boiler and flue designs; (b) your final proposals/designs for boiler and flue configuration were submitted later than we would reasonably have expected. (4) Furthermore, we believe that another factor affecting progress which you have failed to take into account has been the fluctuating level of resource provided by yourselves over recent weeks, which at times has been insufficient to maintain planned regular progress."