“Q The£200,000 /£36,000 split was not discussed? A. It was brought up in conversation. We did not necessarily sit down to discuss it. It was brought up by way of a reply. The Defendant asked if any further sums were due to Preprint. We said, no, it was all in the figures. It was mentioned. Q That was just the overall price? A. It was not specifically said:£200,000 and£36,000 . Q It was not said? A. Not in those terms, no.”
“9 Whilst the Claimant was undertaking works under the initial contract it became clear that additional work over and above those agreed in the initial contract would be necessary in order for the works to meet the Landlord’s specifications. Without such works the original contract could not be complied with. The extent of the works and the necessity therefore were explained to the Defendant at a site meeting on14th October 2003 . 10 The Defendant agreed at the meeting that the Claimant should undertake the works and that following satisfactory completion of the works the Defendant would pay to the Claimant the costs of such works upon receipt of an invoice. 11 The Claimant, in accordance with the agreement of the Defendant, undertook the additional works. The meeting and the agreement of the Defendant is evidenced by an email from the Claimant to the Defendant dated16th October 2003 which is annexed hereto.”
“Q Mr. Barrand wanted to pull people off site. That was not acceptable to Mr. Alavi? A. Correct … Q It was not reasonable to expect the Defendant to pay the additional costs? A. Mr. Barrand wanted to leave. He could not do the works in a proper way. Mr. Alavi would not allow him to do that. Q Mr. Alavi was entitled to do that? A. He did say, ‘I’ll make the bastards pay’. Q There was no agreement that Mr. Alavi would meet the bill? A. No. We expected him to get the costs from the landlord. Q Mr. Alavi did not agree? A. There were no figures. He did say he wanted Mr. Barrand to stay on site.”
“Q There was no agreement to meet your addition costs, was there? A. Not on the face of the meeting. He did not sanction the extra costs at that meeting but he wanted to keep us on site. Q Why did you say he agreed to meet the costs? A. He agreed it with Storey … Q So it is all based on implication which you say was an agreement? A. I take it on board that it was agreed with Paul Storey … Q After that, nothing further was said about extra work? A. Not by myself.”
“Q He would not have appreciated that you were looking to him to pay these costs? A. Probably not, no.”
“Q This was a matter of EQ’s contractual risk? A. Yes, I accept that.”
“My tile contractor can and will rectify this problem quite easily. It is a repair and does not warrant a new floor as suggested.”