“(1) the arbitrator has failed to take into account and apply Surefire’s condition on the order form, that applications for the cost of variations should be accompanied by day work sheets. This has led to decisions based on pure speculation in the total absence of any evidence, as to the number of hours actually employed on the claimed variations (item 1/4 and 3/24; item 1/17; item 1/28; item 2/8); (2) the arbitrator failed to take into account the evidence provided at the hearing as to what was involved in the variations for which Guardian had claimed, wrongly determining questions (a) either in the absence of any evidence at all (item 2/8; item 3/20) or (b) on the basis of what the parties discussed and did on Guardian’s applications for interim payments (item 1/7; item 1/14; item 3/24; item 1/17; item 1/28); (3) the arbitrator failed to take into account Surefire’s own contractual conditions relating to payments on account and wrongfully concluded that the terms relating to payments on account were governed by terms relating to Surefire’s contract with its client Shitayama who owned the site (all items).”
“(1) item 1/7, increase in cable size; (2) items 1/4 and 3/24, the aquarium; (3) item 1/16, stair cores C to F; (4) item 1/17, stair cores A, B, G, H, J; (5) item 1/28, sprinklers; (6) item 2/8 fire core alarm; (7) items 3/20 to 3/23, labour.”
“(1) Unless the parties otherwise agree, the court may by order extend any time limit agreed by them in relation to any matter relating to arbitral proceedings or specified in any provision of this Part having effect in default of such agreement... (3) The court shall not exercise its power to extend a time limit unless it is satisfied (a) that any available recourse to the tribunal, or to any arbitral or other institution, or person vested by the parties with power in that regard, has first been exhausted and (b) that a substantial injustice would otherwise be done.” (a) that any available recourse to the tribunal, or to any arbitral or other institution, or person vested by the parties with power in that regard, has first been exhausted and (b) that a substantial injustice would otherwise be done.”
“Where any provision of this Part requires an application or appeal to be made to the court within a specified time, the rules of court relating to the reckoning of periods, the extending or abridging of periods and the consequences of not taking a step within the period prescribed by the rules apply in relation to that requirement.”
“(50) In determining the relative weight that should be attached to the discretionary criteria, the starting point must be to take into account the fact that the 1996 Act is founded on a philosophy which differs in important respects from that of the CPR. (51) Thus, the twin principles of party autonomy and finality of awards, which pervade the Act, tend to restrict the supervisory role of the court and to minimise the occasion for the court’s intervention in the conduct of arbitrations…”
“(1) the length of the delay; (2) whether, in permitting the time limit to expire and the subsequent delay to occur, the party was acting reasonably in all the circumstances; (3) whether the respondent to the application or the arbitrator caused or contributed to the delay; (4) whether the respondent to the application would, by reason of the delay, suffer irremediable prejudice in addition to the mere loss of time if the application were permitted to proceed; (5) whether the arbitration has continued during the period of delay and, if so, what impact on the progress of the arbitration or the costs incurred in respect of the determination of the application by the court might now have; (6) the strength of the application; (7) whether, in the broadest sense, it would be unfair to the applicant for him to be denied the opportunity of having the application determined.”
“Please note that payment for any additional works will only be made when accompanied with an instruction and day work sheets authorised by our site manager.”
“On a few occasions, Guardian did submit day work sheets but not time sheets. Where it did, the day work sheets were signed by Surefire ‘for record purposes only’. I accept Mr Felstead’s evidence that Surefire did not generally ask him for day work sheets and did not use their non-provision as a specific reason for disputing the value of variations.”
“I accept that Guardian bears the burden of proof in establishing first, that a variation under the contract has occurred and second, what is its entitlement to extra payment.”